The Critical Path method(CPM)

Procedure that involves the analysis of the sequence and time characteristics of projects by

the use of networks and is used for construction time control, and contractors are now

frequently required by contract to apply network methods to the planning and scheduling of

their fieldwork

Project planning

Devising of a workable scheme of operations to accomplish an established objective when

put into action

Project Planning factors

Different areas of responsibility, such as subcontracted work, which are distinct and separate

from work being done by the prime contractor directly, different categories of work as

distinguished by craft or crew requirements, different categories of work as distinguished by

equipment requirements, different categories of work as distinguished by materials such as

concrete, lumber, or steel, distinct and identifiable subdivisions of structural work such as

walls, slabs, beams, and columns, Location, owner's breakdown for bidding or payment

purposes, contractor's breakdown for estimating purposes

Precedence notation

Depicts each activity as a rectangular box, connected to other activities(boxes with arrows)

Precedence diagram

,Key to the entire time control process that requires time, work, and experience with the type

of construction involved

Network format

Illustrates the manner in which the constituent activities are joined together to create a total

operation pattern

Project scheduling

Accomplished by carrying out a series of simple computations that yield valuable project

control information

Activity durations assumptions

Each activity be evaluated independently of all others, For each activity: assume a normal

level of labor and/or equipment, a normal workday or workweek, and activity durations must

be estimated without regard to any predetermined contract completion date

Time contingency

Safety factor must be included in project time estimates to make allowance for possible

project disruptions, Not allowed for individual activities to allow for unforseen project delays

caused by fire, accidents, equipment breakdown, strikes, late material deliveries, difficult site

conditions, flood, legal delays, and other disruptions

Network computations

After duration is determined has been estimated for each activity some simple step by step

computations are performed

Total float

, The time leeway in the scheduling of some activities and none at all in the scheduling of

others(Calculated by subtracting the ES from LS or EF from LF)

Critical Path

A critical activity is quickly identified as one whose two start times at the left of the activity

box are equal as well as the two finish times at the right of the activity box

Free float

Category of spare time that is derived from the network schedule(Calculated by subtracting

its early finish time from the earliest start time of the activities directly following)

Least-cost project shortening

To reduce length of critical path: do critical activities parallel to each other instead of in a

sequence

Time-scaled networks

Provides a graphical portrayal of the time inter relationships among activities as well as their

sequential order

Bar charts

Graphical picture of the jo schedule, showing the early start and early finish times of various

project segments plotted to a horizontal time scale

Resource scheduling

Resource include materials, subcontractors, labor crews, and equipment

Progress monitoring

Document information

Uploaded on
July 18, 2026
Number of pages
23
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
KenAli
2.6
(18)
Sold
111
Followers
5
Items
23367
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions