Questions Latest 2026 Update | NITC Certification | Bold
Answers with Detailed Rationales
Introduction
This comprehensive practice exam is designed for candidates preparing for the UA STAR
Plumbing Mastery Certification Examination, administered through the National
Inspection Testing and Certification Corporation (NITC). This certification is a nationally
recognized credential for experienced plumbers with advanced installation, code, and
troubleshooting knowledge.
Exam Overview
Feature Details
Administering National Inspection Testing and Certification Corporation (NITC)
Agency
Experience Minimum 5 years experience or completion of recognized
Required apprenticeship program
Exam Format Closed-book, approximately 199 multiple-choice questions
Passing Score Approximately 79.4%
Time Allowed 4 hours
Exam Fee $136-$193 (varies by testing method)
Key Content Areas
,The exam covers advanced plumbing systems, code compliance (IPC/UPC), plumbing
mathematics, blueprint reading, water supply and distribution, sanitary drainage (DWV),
storm drainage, pipe materials and joining methods, backflow prevention, gas piping,
medical gas awareness, and troubleshooting.
Section 1: Plumbing Codes, Permits & Documentation (Questions 1-25)
1. The most widely adopted plumbing code for commercial buildings in the United
States is the:
A) Uniform Plumbing Code (UPC)
B) International Plumbing Code (IPC)
C) National Standard Plumbing Code (NSPC)
D) Local municipal code
Rationale: The International Plumbing Code (IPC) is the most commonly adopted
plumbing code for commercial buildings across the United States.
2. What is the primary purpose of obtaining a plumbing permit before starting work?
A) To generate revenue for the municipality
B) To ensure code compliance and safe installation
C) To create a record of who performed the work
D) To delay construction projects
Rationale: Plumbing permits ensure that all work is inspected for compliance with
safety and health codes, protecting public welfare.
3. Which document must be kept on-site and available for inspection during
plumbing work?
,A) Material safety data sheets only
B) Project documentation and permits
C) Worker time cards
D) Equipment rental agreements
Rationale: Project documentation including approved plans and permits must be
available on-site for inspectors to verify compliance.
4. The International Plumbing Code (IPC) is updated on what cycle?
A) Every year
B) Every 2 years
C) Every 3 years
D) Every 5 years
Rationale: The IPC is updated on a 3-year cycle.
5. The authority having jurisdiction (AHJ) is responsible for:
A) Designing plumbing systems
B) Supplying plumbing materials
C) Enforcing plumbing codes and issuing permits
D) Hiring licensed plumbers
Rationale: The AHJ (typically local building department) has the legal authority to
enforce codes and approve permits.
6. What is the minimum distance a plumbing vent must terminate above a roof?
A) 2 inches
B) 6 inches
, C) 12 inches
D) 18 inches
Rationale: Vent pipes must extend at least 6 inches above the roof surface. Vents
must extend at least 12 inches in areas with heavy snow.
7. A plumbing rough-in inspection occurs:
A) After fixtures are installed but before walls are finished
B) After piping is installed but before walls are closed and fixtures are set
C) Before any piping is installed (site prep)
D) After all work is complete
Rationale: Rough-in inspection occurs after piping is installed but before walls are
closed and fixtures are set.
8. The final (finished) plumbing inspection occurs:
A) After rough-in only
B) After all fixtures are installed and system is operational
C) Before any work begins
D) Only for commercial projects
Rationale: Final inspection verifies all fixtures are properly installed and the system
functions correctly.
9. Which of the following typically requires a separate plumbing permit?
A) Replacing a faucet washer
B) Unclogging a toilet