⩥ If visual monitoring is utilized as the means of release
detection for single walled tank, it must be conducted on a
_______ Basis.
Answer: Daily
⩥ The Purpose of spill and overfill protection equipment is to
minimize the potential for a release during:
Answer: Fuel Deliveries
⩥ Which of the following is a potential symptom of toxic
petroleum exposure:
Answer: Dizziness
Tremors
Eye irritation
All of the above(correct)
,⩥ Under-Dispenser Containment is required for ______
underground storage tank systems
Answer: All
⩥ All of the following are true for Automatic Tank Gauging
(ATG) except for:
Answer: ATG system are required to be installed in all UST
system
⩥ According to CCR Title 23, UST regulations Spill
containment (spill bucket) must meet all of the following
requirements except:
Answer: Be installed on vent risers
⩥ Suction piping may not require leak detection if it has one
check valve located where?
Answer: Directly below the suction pump
⩥ Service Technician performing work on Monitoring
equipment must be trained and certified by __________
Answer: The manufacture of the equipment.
,⩥ Air monitoring must be conducted ________ when
performing work within a confined space.
Answer: Prior to and during
⩥ A UST Service Technician must be recertified by the
equipment Manufacture at the time interval recommended by the
equipment manufacture or at least every ____ months,
whichever is greater.
Answer: 36 Months
⩥ When an automatic tank gauge is utilized for single-walled
tank leak detection, it shall test the tank at least monthly after
product delivery or when the tank is filled to within _____
percent of the highest operating level during the previous month.
Answer: 10
⩥ The following is true of spill buckets except:
Answer: Must provide drainage for spilled product into the
secondary containment sump.
⩥ If during an inspection of dispensing equipment at a retail gas
station you find that the product is dispensing at a significant
lower rate than usual. You should check:
, Answer: For piping leaks.
⩥ According to CCR title 23, UST Regulations the local agency
must be notified by the Owner/Operator how long before
conducting Secondary Containment Testing?
Answer: At least 48 hours before the test.
⩥ Poppet Valves are a Vapor Recovery Component installed:
Answer: on the vapor recovery riser
⩥ If equipped with an ATG it shall be programmed to test the
tank _______?
Answer: at least monthly
⩥ A Vacuum-assist nozzle is a component of a(n) ________?
Answer: Stage II vapor recovery system
⩥ Stage I Vapor Recovery can be installed in the following
configured(s):
Answer: Dual Point, Manifold, & Coaxial
SCRIPT COMPLETE QUESTIONS AND
ANSWERS VERIFIED FULL SOLUTION
GRADED A+
⩥ If visual monitoring is utilized as the means of release
detection for single walled tank, it must be conducted on a
_______ Basis.
Answer: Daily
⩥ The Purpose of spill and overfill protection equipment is to
minimize the potential for a release during:
Answer: Fuel Deliveries
⩥ Which of the following is a potential symptom of toxic
petroleum exposure:
Answer: Dizziness
Tremors
Eye irritation
All of the above(correct)
,⩥ Under-Dispenser Containment is required for ______
underground storage tank systems
Answer: All
⩥ All of the following are true for Automatic Tank Gauging
(ATG) except for:
Answer: ATG system are required to be installed in all UST
system
⩥ According to CCR Title 23, UST regulations Spill
containment (spill bucket) must meet all of the following
requirements except:
Answer: Be installed on vent risers
⩥ Suction piping may not require leak detection if it has one
check valve located where?
Answer: Directly below the suction pump
⩥ Service Technician performing work on Monitoring
equipment must be trained and certified by __________
Answer: The manufacture of the equipment.
,⩥ Air monitoring must be conducted ________ when
performing work within a confined space.
Answer: Prior to and during
⩥ A UST Service Technician must be recertified by the
equipment Manufacture at the time interval recommended by the
equipment manufacture or at least every ____ months,
whichever is greater.
Answer: 36 Months
⩥ When an automatic tank gauge is utilized for single-walled
tank leak detection, it shall test the tank at least monthly after
product delivery or when the tank is filled to within _____
percent of the highest operating level during the previous month.
Answer: 10
⩥ The following is true of spill buckets except:
Answer: Must provide drainage for spilled product into the
secondary containment sump.
⩥ If during an inspection of dispensing equipment at a retail gas
station you find that the product is dispensing at a significant
lower rate than usual. You should check:
, Answer: For piping leaks.
⩥ According to CCR title 23, UST Regulations the local agency
must be notified by the Owner/Operator how long before
conducting Secondary Containment Testing?
Answer: At least 48 hours before the test.
⩥ Poppet Valves are a Vapor Recovery Component installed:
Answer: on the vapor recovery riser
⩥ If equipped with an ATG it shall be programmed to test the
tank _______?
Answer: at least monthly
⩥ A Vacuum-assist nozzle is a component of a(n) ________?
Answer: Stage II vapor recovery system
⩥ Stage I Vapor Recovery can be installed in the following
configured(s):
Answer: Dual Point, Manifold, & Coaxial