✔✔in CSI-MASTERFORMAT, Specifications are typically divided into ________
specific divisions to provide a standard reference. - ✔✔50
✔✔12. lead items needed for a project should be - ✔✔C. identified & ordered early
✔✔13. Employee Linda was paid a gross her pay for Medicare and Social Security?
total wage of $63,500 last year. What was the total amount withheld from (choose
closest answer) - ✔✔$4858
✔✔14. A cost-plus contract can best be described as contract that is - ✔✔A. negotiated
& open ended
✔✔15. Which of the following is a concern of the Fair Labor Standards Act? (FLSA) -
✔✔B. Child labor
✔✔16. Which of the following is not a method of scheduling within the Network Analysis
Technique, - ✔✔A. RSM
, ✔✔17. What type of contract encourages cost savings and value enginecering? -
✔✔17. A. guaranteed maximum price
✔✔18. Of the following, whose lien will be paid first? - ✔✔D. Laborer
✔✔19. Which of the following oral contacts is enforceable? - ✔✔B. a job for $475 to last
180 days
✔✔is which progress be completed 20 A procedure in the carly stages of a contract
billings are accelerated by assigning is known as higher values to contract portions to -
✔✔D. front end loading
✔✔21. The Florida Department of Environmental Protection be notified _________
working days in advance of a demolition for a project where no asbestos is present.
working days in - ✔✔A. 10 days
✔✔2. The maximum allowable civil penalty that can be imposed by OSHA for each
willful or repeated violation is - ✔✔B. $124,471
✔✔$124,471 $125,000 23. Which of the following would have jurisdiction over dredging
or excavation of navigable waters and wetlands? - ✔✔D. U.S Army Corps of Engineers
✔✔24. In the event the qualifying agent resigns from the employment of a contractor,
the contractor must replace the qualifier within ________days. - ✔✔C. 60 days
✔✔15. When employing a nonresident alien, which of the following taxes must be paid?
- ✔✔A. Medicare and Social Security B. Income Tax C. FUTA D. all of the above
✔✔Which construction site requires a licensed contractor for the job? - ✔✔C. bank
✔✔2. How long is the company required to retain OSHA 300/300A logs? - ✔✔C. 5
years
✔✔Ao unfair labor practice charge must be received by the regional office with
jurisdiction over the area here this alleged unfair labor practice occurred. What is the
time limit to file this charge? - ✔✔A. 6 months
✔✔4A contractor must serve a copy of the claim of lien on the owner and lender (if any)
within how many days of the date the claim of lien is recorded? - ✔✔A. 15
✔✔wich of the following must be true for a person to qualify for a state certification of
competency? - ✔✔be of good moral character, be at least 18 years of age and pass an
examination
SCRIPT QUESTIONS AND ANSWERS SURE A+
✔✔in CSI-MASTERFORMAT, Specifications are typically divided into ________
specific divisions to provide a standard reference. - ✔✔50
✔✔12. lead items needed for a project should be - ✔✔C. identified & ordered early
✔✔13. Employee Linda was paid a gross her pay for Medicare and Social Security?
total wage of $63,500 last year. What was the total amount withheld from (choose
closest answer) - ✔✔$4858
✔✔14. A cost-plus contract can best be described as contract that is - ✔✔A. negotiated
& open ended
✔✔15. Which of the following is a concern of the Fair Labor Standards Act? (FLSA) -
✔✔B. Child labor
✔✔16. Which of the following is not a method of scheduling within the Network Analysis
Technique, - ✔✔A. RSM
, ✔✔17. What type of contract encourages cost savings and value enginecering? -
✔✔17. A. guaranteed maximum price
✔✔18. Of the following, whose lien will be paid first? - ✔✔D. Laborer
✔✔19. Which of the following oral contacts is enforceable? - ✔✔B. a job for $475 to last
180 days
✔✔is which progress be completed 20 A procedure in the carly stages of a contract
billings are accelerated by assigning is known as higher values to contract portions to -
✔✔D. front end loading
✔✔21. The Florida Department of Environmental Protection be notified _________
working days in advance of a demolition for a project where no asbestos is present.
working days in - ✔✔A. 10 days
✔✔2. The maximum allowable civil penalty that can be imposed by OSHA for each
willful or repeated violation is - ✔✔B. $124,471
✔✔$124,471 $125,000 23. Which of the following would have jurisdiction over dredging
or excavation of navigable waters and wetlands? - ✔✔D. U.S Army Corps of Engineers
✔✔24. In the event the qualifying agent resigns from the employment of a contractor,
the contractor must replace the qualifier within ________days. - ✔✔C. 60 days
✔✔15. When employing a nonresident alien, which of the following taxes must be paid?
- ✔✔A. Medicare and Social Security B. Income Tax C. FUTA D. all of the above
✔✔Which construction site requires a licensed contractor for the job? - ✔✔C. bank
✔✔2. How long is the company required to retain OSHA 300/300A logs? - ✔✔C. 5
years
✔✔Ao unfair labor practice charge must be received by the regional office with
jurisdiction over the area here this alleged unfair labor practice occurred. What is the
time limit to file this charge? - ✔✔A. 6 months
✔✔4A contractor must serve a copy of the claim of lien on the owner and lender (if any)
within how many days of the date the claim of lien is recorded? - ✔✔A. 15
✔✔wich of the following must be true for a person to qualify for a state certification of
competency? - ✔✔be of good moral character, be at least 18 years of age and pass an
examination