SWPPP CORRECT FINAL EXAM QUESTIONS AND
ANSWERS SET A+
✔✔The document in the SWPPP that certifies the GC's commitment to compliance with
the SWPPP - ✔✔The SWPPP certification letter
✔✔The certifactions letter that identifies the name and contact information of
subcontractors on the site is - ✔✔The subcontractors certification form
✔✔The documents that reveal the total area of disturbance are - ✔✔The site maps
✔✔The document completed by the project SWPPP inspector recording site conditions
during the inspection is - ✔✔The inspection report form
✔✔The document that must be completed to report hazardous spill on site is - ✔✔The
spill report form
✔✔The document that verifies that weekly management meetings have been conducted
is - ✔✔The weekly meeting form
✔✔The document delegating responsibility of inspections to another is - ✔✔The
delegation letter
✔✔The document that must be completed when final stabilization is complete is -
✔✔The NOT
✔✔Scheduling - ✔✔Aids in protecting the site by timing construction activities
✔✔Factors to consider when creating your schedule include - ✔✔Account for the time it
takes to install or implement BMP's between each phase of construction
, ✔✔When installing perimeter BMP controls - ✔✔Note to locations and dates for
installation on site map
✔✔Stormwater issues are usually discussed during the pre-con meeting include -
✔✔SWPPP BMP's and construction schedule
✔✔Sediment control devices must be installed - ✔✔Down slope of construction areas
and functioning as designed prior to beginning land disturbing activities
✔✔If you have stormwater inlets in your construction roadway - ✔✔Consult your project
SWPPP to ensure you are protecting inlets properly
✔✔Soil stock piles and other disturb areas must receive - ✔✔Temporary stabilization if
they will remain in active for more than 14 days and potentially fewer days depending
on the jurisdiction
✔✔In the process of transitioning form Lan development to building construction it is
important to - ✔✔Implement specific BMP's to address potential pollution associated
with construction materials
✔✔The SWPPP sequence of activities can be modified - ✔✔After consulting the project
SWPPP designer and or project owner and receiving approval
✔✔Once the notice of termination is filed store all stormwater related project information
- ✔✔For three years or more depending on permit and contact obligation
✔✔When installing perimeter BMP controls - ✔✔No locations and dates of installation
on site map
✔✔Stormwater issues usually discussed during the pre-con meeting include -
✔✔SWPPP BMP's and the construction schedule
✔✔Which erosion control best management practices increase water infiltration
decrease rainfall energy and slow overland flow of stormwater - ✔✔Vegatation
Vegetation
✔✔Which of the following factors affect erosion (3) - ✔✔1. Ground cover
2. Soil type
3. Amount and duration of rainfall
✔✔Erosion and sedimentation control principle do not include which of the following -
✔✔Leave unprotected openings for stormwater and sediment to leave site
ANSWERS SET A+
✔✔The document in the SWPPP that certifies the GC's commitment to compliance with
the SWPPP - ✔✔The SWPPP certification letter
✔✔The certifactions letter that identifies the name and contact information of
subcontractors on the site is - ✔✔The subcontractors certification form
✔✔The documents that reveal the total area of disturbance are - ✔✔The site maps
✔✔The document completed by the project SWPPP inspector recording site conditions
during the inspection is - ✔✔The inspection report form
✔✔The document that must be completed to report hazardous spill on site is - ✔✔The
spill report form
✔✔The document that verifies that weekly management meetings have been conducted
is - ✔✔The weekly meeting form
✔✔The document delegating responsibility of inspections to another is - ✔✔The
delegation letter
✔✔The document that must be completed when final stabilization is complete is -
✔✔The NOT
✔✔Scheduling - ✔✔Aids in protecting the site by timing construction activities
✔✔Factors to consider when creating your schedule include - ✔✔Account for the time it
takes to install or implement BMP's between each phase of construction
, ✔✔When installing perimeter BMP controls - ✔✔Note to locations and dates for
installation on site map
✔✔Stormwater issues are usually discussed during the pre-con meeting include -
✔✔SWPPP BMP's and construction schedule
✔✔Sediment control devices must be installed - ✔✔Down slope of construction areas
and functioning as designed prior to beginning land disturbing activities
✔✔If you have stormwater inlets in your construction roadway - ✔✔Consult your project
SWPPP to ensure you are protecting inlets properly
✔✔Soil stock piles and other disturb areas must receive - ✔✔Temporary stabilization if
they will remain in active for more than 14 days and potentially fewer days depending
on the jurisdiction
✔✔In the process of transitioning form Lan development to building construction it is
important to - ✔✔Implement specific BMP's to address potential pollution associated
with construction materials
✔✔The SWPPP sequence of activities can be modified - ✔✔After consulting the project
SWPPP designer and or project owner and receiving approval
✔✔Once the notice of termination is filed store all stormwater related project information
- ✔✔For three years or more depending on permit and contact obligation
✔✔When installing perimeter BMP controls - ✔✔No locations and dates of installation
on site map
✔✔Stormwater issues usually discussed during the pre-con meeting include -
✔✔SWPPP BMP's and the construction schedule
✔✔Which erosion control best management practices increase water infiltration
decrease rainfall energy and slow overland flow of stormwater - ✔✔Vegatation
Vegetation
✔✔Which of the following factors affect erosion (3) - ✔✔1. Ground cover
2. Soil type
3. Amount and duration of rainfall
✔✔Erosion and sedimentation control principle do not include which of the following -
✔✔Leave unprotected openings for stormwater and sediment to leave site