• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 36 pages
Exam (elaborations)

Certified Construction Manager (CCM) Examination Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf

Document preview thumbnail
Preview 4 out of 36 pages

Certified Construction Manager (CCM) Examination Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf

Content preview

Certified Construction Manager (CCM)
Examination Questions And Correct
Answers (Verified Answers) Plus
Rationales 2026 Q&A | Instant
Download Pdf

1.
A project has a planned value (PV) of $500,000 and an earned value (EV) of
$450,000. What is the schedule performance index (SPI)?
A. 0.90
B. 1.11
C. 0.80
D. 1.00
Rationale:
SPI = EV ÷ PV = 450,000 ÷ 500,000 = 0.90. An SPI below 1.0 indicates the project
is behind schedule, meaning less work has been completed than planned at this
point.


2.
Which contract type places the greatest cost risk on the owner?
A. Cost-plus-fixed-fee
B. Time and materials
C. Lump sum
D. Cost-plus-percentage-fee

,Rationale:
Cost-plus-percentage-fee contracts incentivize contractors to increase costs since
their fee increases with project cost. This shifts maximum financial risk to the
owner.


3.
A project’s CPI is 1.25. What does this indicate?
A. Project is over budget
B. Project is on schedule
C. Project is under budget
D. Project is ahead of schedule
Rationale:
CPI = EV ÷ AC. A CPI greater than 1.0 indicates cost efficiency, meaning the
project is achieving more value per dollar spent, hence under budget.


4.
What is the primary purpose of a construction change order?
A. To terminate a contract
B. To adjust labor productivity
C. To document safety violations
D. To formally modify contract scope, cost, or schedule
Rationale:
Change orders legally modify the original contract terms, ensuring adjustments
in scope, time, or cost are properly documented and enforceable.


5.

,Which scheduling method is most commonly used for complex construction
projects?
A. Bar chart
B. Line of balance
C. Critical Path Method (CPM)
D. Gantt summary only
Rationale:
CPM identifies task dependencies and determines the longest path of activities,
making it essential for managing complex construction sequencing.


6.
What is the main function of a construction baseline schedule?
A. To replace daily reports
B. To eliminate risk
C. To assign subcontractors
D. To serve as the reference point for project progress measurement
Rationale:
A baseline schedule provides the approved time plan against which actual
performance is measured for delays, progress, and earned value analysis.


7.
Which document defines project quality standards and requirements?
A. Safety manual
B. Cost estimate
C. Risk register
D. Quality management plan

, Rationale:
The quality management plan defines standards, procedures, and metrics
ensuring project deliverables meet specified requirements.


8.
A contract includes liquidated damages of $2,000 per day. This is intended to:
A. Reward early completion
B. Increase contractor profit
C. Cover material waste
D. Compensate the owner for delays
Rationale:
Liquidated damages are pre-agreed penalties that compensate the owner for
losses caused by contractor delays.


9.
Which risk response strategy eliminates a risk entirely?
A. Transfer
B. Mitigate
C. Accept
D. Avoid
Rationale:
Avoidance removes the risk by changing the project plan, scope, or method so
the risk condition no longer exists.


10.
What does a negative float in a schedule indicate?

Document information

Uploaded on
July 2, 2026
Number of pages
36
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$23.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
masterystudyhub
5.0
(1)
Sold
37
Followers
2
Items
11267
Last sold
4 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions