Question 1: According to DBIA's "Design-Build Done Right" principles, what is the
primary driver for utilizing a Two-Phase Selection process?
A. To guarantee the lowest possible bid price for the owner.
B. To reduce the cost of competition for both the owner and the proposers.
C. To narrow the field to the most qualified teams before requesting detailed proposals.
D. To comply with federal regulations that mandate a two-step process for all public
projects.
CORRECT ANSWER: C. To narrow the field to the most qualified teams before
requesting detailed proposals.
Rationale: The Two-Phase Selection process is a cornerstone of DBIA best practices.
Phase One involves a Request for Qualifications (RFQ) to evaluate the experience and
qualifications of potential teams. This allows the owner to shortlist the most highly
qualified teams. Phase Two then invites only these shortlisted teams to respond to a
detailed Request for Proposals (RFP), saving significant time and money for both the
owner and the proposing teams and ensuring a focus on quality and best value .
Question 2: Which of the following best describes the role of the "Owner's Advisor"
in a Design-Build project?
A. To manage the construction site and supervise the Design-Builder's crews.
B. To assist the owner in developing the RFQ/RFP and monitoring compliance.
C. To serve as the Architect of Record for the project.
D. To take over the Design-Builder's responsibilities if they fall behind schedule.
CORRECT ANSWER: B. To assist the owner in developing the RFQ/RFP and
monitoring compliance.
Rationale: The Owner's Advisor is a consultant hired to help the owner navigate the
complexities of Design-Build project delivery. Their expertise is crucial in developing the
procurement documents (RFQ/RFP) and ensuring the Design-Builder's performance
aligns with the owner's project criteria and goals. This helps the owner maintain a strong
position throughout the project .
Question 3: In the context of a Design-Build team, which document is the
foundational agreement that outlines the relationship, roles, and responsibilities
between the lead contractor and the lead designer?
,A. The Owner-Design-Builder Agreement
B. The Teaming Agreement
C. The Project Criteria Document
D. The Performance Bond
CORRECT ANSWER: B. The Teaming Agreement
Rationale: The Teaming Agreement is a critical pre-award document. It establishes the
contractual and operational framework for how the design and construction entities will
collaborate during the pursuit of a project and, if successful, during its execution. It
defines crucial elements like cost-sharing, intellectual property rights, and the division
of responsibilities .
Question 4: What is the significance of a "confirmatory payment" or "honorarium"
in the Design-Build procurement process?
A. It guarantees the owner the right to use the intellectual property from an
unsuccessful proposer's submission.
B. It is a bonus paid to the winning firm upon contract signing.
C. It is a fee charged to proposers for downloading the RFP documents.
D. It is withheld to ensure only serious firms apply for the project.
CORRECT ANSWER: A. It guarantees the owner the right to use the intellectual
property from an unsuccessful proposer's submission.
Rationale: An honorarium is a stipend paid to unsuccessful shortlisted proposers to
offset their proposal development costs. In exchange, the owner typically gains the right
to use the concepts and intellectual property contained in those proposals. This
practice encourages competition and is a fair acknowledgment of the significant effort
and innovation invested by the proposing teams .
Question 5: Under a Design-Build contract, who is typically the party responsible
for obtaining the building permit?
A. The Owner
B. The Design-Builder
C. The Owner's Representative
D. The Structural Engineer of Record
CORRECT ANSWER: B. The Design-Builder
Rationale: A fundamental principle of Design-Build is the "single point of responsibility."
As the single entity accountable for both the design and construction, the Design-
Builder manages the entire permitting process, streamlining communication and
accountability with the authorities having jurisdiction .
Question 6: What is the primary purpose of a "Letter of Intent" (LOI) in a Design-
Build project?
,A. To finalize the 100% design documents.
B. To allow the Design-Builder to start limited work while the final contract is being
negotiated.
C. To officially cancel a project before it begins.
D. To terminate a subcontractor for poor performance.
CORRECT ANSWER: B. To allow the Design-Builder to start limited work while the
final contract is being negotiated.
Rationale: A Letter of Intent is a pre-contractual tool used to authorize the Design-
Builder to commence early, critical-path work (such as long-lead procurement or early
site preparation) while the final, formal contract documents are still being finalized. This
helps to maintain the project schedule and accelerate the overall delivery timeline .
Question 7: How does the "Spearin Doctrine" typically apply differently in Design-
Build compared to Design-Bid-Build?
A. It remains the same; the owner warrants the plans in both methods.
B. The doctrine is significantly limited because the Design-Builder is responsible for
creating the plans they follow.
C. The doctrine is extended to require the owner to warrant the Design-Builder's means
and methods.
D. The doctrine does not apply to any public projects.
CORRECT ANSWER: B. The doctrine is significantly limited because the Design-
Builder is responsible for creating the plans they follow.
Rationale: The Spearin Doctrine holds that an owner warrants the adequacy of plans
and specifications provided to a contractor. In a Design-Bid-Build project, the owner
provides the plans. However, in Design-Build, the Design-Builder is responsible for
creating the design. Therefore, the implied warranty of the plans does not apply to the
design produced by the Design-Builder, shifting the risk for design adequacy .
Question 8: Which of the following is NOT considered a core value of the Design-
Build Institute of America (DBIA)?
A. Integrity
B. Professionalism
C. Lowest-Price Wins
D. Teamwork
CORRECT ANSWER: C. Lowest-Price Wins
Rationale: DBIA promotes the principles of "Design-Build Done Right," which
emphasizes collaboration, professionalism, and integrity. The organization strongly
advocates for "Best Value" selection processes over the "lowest-price wins" mentality.
The focus is on selecting the team that offers the best overall combination of
qualifications, approach, and price .
, Question 9: According to DBIA best practices, when should a Teaming Agreement
ideally be executed?
A. After the contract is awarded to the team.
B. Before any significant work is performed on the proposal.
C. During the construction phase.
D. Only if the owner requires it in the RFP.
CORRECT ANSWER: B. Before any significant work is performed on the proposal.
Rationale: To avoid disputes and establish a clear framework for collaboration, the
Teaming Agreement must be signed before the team begins investing significant time
and resources into developing the proposal. Early execution ensures clarity on roles,
risk, cost-sharing, and intellectual property from the outset .
Question 10: What is the "Big Room" concept in Design-Build project execution?
A. A large conference room where only formal progress meetings are held.
B. An off-site location where the owner stores all project documents.
C. A collaborative workspace where the integrated project team is co-located.
D. The primary construction staging area on the project site.
CORRECT ANSWER: C. A collaborative workspace where the integrated project
team is co-located.
Rationale: The "Big Room," also known as co-location, is a core "Design-Build Done
Right" strategy. It involves physically bringing together representatives from the design,
construction, and owner teams into a single, shared workspace. This promotes real-
time communication, rapid problem-solving, and a stronger collaborative culture,
which are hallmarks of an integrated project delivery method .
Question 11: In the DBIA certification exam, which domain focuses on the early
involvement of trade partners and managing the transition from design to
construction?
A. Contracts and Legal Issues
B. Procurement and Selection
C. Post-Award Integration
D. Professional Ethics and Standards
CORRECT ANSWER: C. Post-Award Integration
Rationale: The "Post-Award Integration" domain is a key component of the DBIA exam,
specifically addressing the critical phase after contract award. It covers how to
effectively integrate trade partners early in the process and manage the seamless
transition from design development to construction execution, ensuring that project
goals are met .
Question 12: What is the primary risk for a design professional (e.g., architect) in a