During which of the following project development life cycles are the project
|| || || || || || || || || || || ||
scope, schedule and budget determined in the early phases of the life cycle? -
|| || || || || || || || || || || || || ||
✔✔Predictive Life Cycle || ||
Which of the following is the correct definition of a project management
|| || || || || || || || || || || ||
methodology? - ✔✔System of practices, techniques, rules and procedures used || || || || || || || || || ||
by those who work in a discipline
|| || || || || ||
You are helping an organization uplift its project management practices. You
|| || || || || || || || || || ||
have recommended developing a business case for each of the organizational
|| || || || || || || || || || ||
projects followed by development of a project benefits management plan. Who
|| || || || || || || || || || ||
would you recommend to be the owner of the business case? - ✔✔Project
|| || || || || || || || || || || || ||
Sponsor
- The project sponsor is generally accountable for the development and
|| || || || || || || || || || ||
maintenance of the project business case document. || || || || || ||
The finance department in your organization approves a number of capital
|| || || || || || || || || || ||
projects on an annual basis. These projects are then funded by the finance
|| || || || || || || || || || || || ||
department. You are responsible for constructing a new manufacturing facility || || || || || || || || || ||
that would require construction of a plant, a couple of warehouses and a few
|| || || || || || || || || || || || || ||
storage and distribution locations across the state. Your role at this organization
|| || || || || || || || || || ||
is of a: - ✔✔Program Manager
|| || || || || ||
- Since you are responsible for developing a number of related construction
|| || || || || || || || || || || ||
projects, you are managing a bigger program. || || || || || ||
,2
You have been hired by a new startup to develop its process architecture and
|| || || || || || || || || || || || || ||
define its operating model. The operating model will be used by the business to
|| || || || || || || || || || || || || ||
manage and run its day-to-day business. Your engagement with this
|| || || || || || || || || ||
organization is an example of: - ✔✔Project || || || || || ||
- This is an example of a project. You have a starting point and an end point
|| || || || || || || || || || || || || || || || ||
(defined and agreed operating model). The later use of the operating model will
|| || || || || || || || || || || || ||
be the business' operations but your current engagement is a project as this is a
|| || || || || || || || || || || || || || ||
temporary endeavor. ||
Which of the following statements regarding Project Management Body of
|| || || || || || || || || ||
Knowledge (PMBOK) is incorrect? - ✔✔The PMO's PMBOK Guide contains || || || || || || || || || ||
the entire Project Management Body of Knowledge
|| || || || || ||
You have recently helped an organization define its future state operating
|| || || || || || || || || || ||
model. This will be a significant shift from the current state and will involve
|| || || || || || || || || || || || || ||
significant change. Which of the following would be your recommendation to
|| || || || || || || || || || ||
the management? - ✔✔Create a transition state between the current and future
|| || || || || || || || || || || ||
state.
What does PMP stand for? - ✔✔Project Management Professional
|| || || || || || || ||
When was PMI founded? - ✔✔1969 || || || || ||
Why should project managers become certified? - ✔✔- gives you higher income
|| || || || || || || || || || ||
potential
||
- proves you know international standards
|| || || || ||
, 2
- it's required by a growing number of employers
|| || || || || || || ||
What is the minimum required score of the PMP Exam? - ✔✔61% or 106 out of
|| || || || || || || || || || || || || || || ||
175 questions ||
What % of questions are a direct quote from the PMBOK Guide? - ✔✔0%
|| || || || || || || || || || || || ||
You are setting up a PMO in your organization. The PMO will not only be
|| || || || || || || || || || || || || || ||
required to provide templates and necessary training to projects, it will ensure
|| || || || || || || || || || || ||
all projects comply with the organizational project management policies and
|| || || || || || || || || ||
procedures. However, the PMO will not directly manage the organizational || || || || || || || || || ||
projects. Which type of PMO are you setting up? - ✔✔Controlling PMO
|| || || || || || || || || || ||
Who typically manages project budgets in a multi-divisional organization? -
|| || || || || || || || || ||
✔✔A Functional Manager || ||
In which of the following organization types is the project management
|| || || || || || || || || || ||
administrative staff usually dedicated full-time to projects? - ✔✔Strong Matrix || || || || || || || || ||
You are leading a project team in a matrix organization. You have found out the
|| || || || || || || || || || || || || || ||
project team members are frequently distracted by their functional managers
|| || || || || || || || || ||
for petty tasks and the team responds by prioritizing that work on top of the
|| || || || || || || || || || || || || || ||
project work. In this case, the functional managers are using which of the
|| || || || || || || || || || || || ||
following powers to get their work done? - ✔✔reward-oriented
|| || || || || || || ||
PMP newest Exam Questions with verified || || || || || ||
detailed answers ||
During which of the following project development life cycles are the project
|| || || || || || || || || || || ||
scope, schedule and budget determined in the early phases of the life cycle? -
|| || || || || || || || || || || || || ||
✔✔Predictive Life Cycle || ||
Which of the following is the correct definition of a project management
|| || || || || || || || || || || ||
methodology? - ✔✔System of practices, techniques, rules and procedures used || || || || || || || || || ||
by those who work in a discipline
|| || || || || ||
You are helping an organization uplift its project management practices. You
|| || || || || || || || || || ||
have recommended developing a business case for each of the organizational
|| || || || || || || || || || ||
projects followed by development of a project benefits management plan. Who
|| || || || || || || || || || ||
would you recommend to be the owner of the business case? - ✔✔Project
|| || || || || || || || || || || || ||
Sponsor
- The project sponsor is generally accountable for the development and
|| || || || || || || || || || ||
maintenance of the project business case document. || || || || || ||
The finance department in your organization approves a number of capital
|| || || || || || || || || || ||
projects on an annual basis. These projects are then funded by the finance
|| || || || || || || || || || || || ||
department. You are responsible for constructing a new manufacturing facility || || || || || || || || || ||
that would require construction of a plant, a couple of warehouses and a few
|| || || || || || || || || || || || || ||
storage and distribution locations across the state. Your role at this organization
|| || || || || || || || || || ||
is of a: - ✔✔Program Manager
|| || || || || ||
- Since you are responsible for developing a number of related construction
|| || || || || || || || || || || ||
projects, you are managing a bigger program. || || || || || ||
,2
You have been hired by a new startup to develop its process architecture and
|| || || || || || || || || || || || || ||
define its operating model. The operating model will be used by the business to
|| || || || || || || || || || || || || ||
manage and run its day-to-day business. Your engagement with this
|| || || || || || || || || ||
organization is an example of: - ✔✔Project || || || || || ||
- This is an example of a project. You have a starting point and an end point
|| || || || || || || || || || || || || || || || ||
(defined and agreed operating model). The later use of the operating model will
|| || || || || || || || || || || || ||
be the business' operations but your current engagement is a project as this is a
|| || || || || || || || || || || || || || ||
temporary endeavor. ||
Which of the following statements regarding Project Management Body of
|| || || || || || || || || ||
Knowledge (PMBOK) is incorrect? - ✔✔The PMO's PMBOK Guide contains || || || || || || || || || ||
the entire Project Management Body of Knowledge
|| || || || || ||
You have recently helped an organization define its future state operating
|| || || || || || || || || || ||
model. This will be a significant shift from the current state and will involve
|| || || || || || || || || || || || || ||
significant change. Which of the following would be your recommendation to
|| || || || || || || || || || ||
the management? - ✔✔Create a transition state between the current and future
|| || || || || || || || || || || ||
state.
What does PMP stand for? - ✔✔Project Management Professional
|| || || || || || || ||
When was PMI founded? - ✔✔1969 || || || || ||
Why should project managers become certified? - ✔✔- gives you higher income
|| || || || || || || || || || ||
potential
||
- proves you know international standards
|| || || || ||
, 2
- it's required by a growing number of employers
|| || || || || || || ||
What is the minimum required score of the PMP Exam? - ✔✔61% or 106 out of
|| || || || || || || || || || || || || || || ||
175 questions ||
What % of questions are a direct quote from the PMBOK Guide? - ✔✔0%
|| || || || || || || || || || || || ||
You are setting up a PMO in your organization. The PMO will not only be
|| || || || || || || || || || || || || || ||
required to provide templates and necessary training to projects, it will ensure
|| || || || || || || || || || || ||
all projects comply with the organizational project management policies and
|| || || || || || || || || ||
procedures. However, the PMO will not directly manage the organizational || || || || || || || || || ||
projects. Which type of PMO are you setting up? - ✔✔Controlling PMO
|| || || || || || || || || || ||
Who typically manages project budgets in a multi-divisional organization? -
|| || || || || || || || || ||
✔✔A Functional Manager || ||
In which of the following organization types is the project management
|| || || || || || || || || || ||
administrative staff usually dedicated full-time to projects? - ✔✔Strong Matrix || || || || || || || || ||
You are leading a project team in a matrix organization. You have found out the
|| || || || || || || || || || || || || || ||
project team members are frequently distracted by their functional managers
|| || || || || || || || || ||
for petty tasks and the team responds by prioritizing that work on top of the
|| || || || || || || || || || || || || || ||
project work. In this case, the functional managers are using which of the
|| || || || || || || || || || || || ||
following powers to get their work done? - ✔✔reward-oriented
|| || || || || || || ||