ASHRAE CONTINUOUS COMMISSIONING PRACTICES EXAM 200 Practice
Questions
ASHRAE Continuous Commissioning Practices Exam
210 Practice Questions with Answers and Rationales
SECTION 1: FUNDAMENTALS OF CONTINUOUS COMMISSIONING (Questions 1-35)
1. Which statement best defines continuous commissioning in building systems?
A. A one-time verification process performed at project completion
B. A process focused only on HVAC equipment replacement cycles
C. A quality-focused, ongoing process for maintaining optimal system
performance throughout a building's life cycle
D. A systematic, ongoing process that monitors, verifies, and optimizes building
systems to ensure they continue meeting the Owner's Project Requirements
Answer: D
Rationale: Continuous commissioning is not a single event but an ongoing process
that ensures building systems remain efficient, properly controlled, and aligned
with the owner's requirements over time, extending beyond initial commissioning
into operation and maintenance phases .
,2. Which phase is most closely associated with the initiation of continuous
commissioning practices?
A. Construction only
B. Occupancy only
C. Post-demolition phase
D. Design and early operations phase, continuing through building life cycle
Answer: D
Rationale: Continuous commissioning typically begins early and continues through
operation, ensuring systems are optimized from design intent through long-term
performance .
3. The primary objective of continuous commissioning is to:
A. Reduce construction costs only
B. Eliminate all maintenance activities
C. Replace traditional commissioning entirely
,D. Maintain and improve system performance, energy efficiency, and occupant
comfort over time
Answer: D
Rationale: Its goal is sustained performance improvement, ensuring systems do
not drift away from intended design efficiency or functionality .
4. Which document most directly guides continuous commissioning activities?
A. Architectural floor plans
B. Construction permits
C. Manufacturer catalogues
D. Owner's Project Requirements (OPR)
Answer: D
Rationale: The OPR defines performance expectations, and continuous
commissioning ensures systems continue to meet those expectations over time .
, 5. Continuous commissioning differs from retro-commissioning in that it:
A. Only applies to existing buildings
B. Is performed only once every 10 years
C. Focuses solely on correcting HVAC failures
D. Is an ongoing, proactive process rather than a one-time diagnostic
Answer: D
Rationale: Retro-commissioning applies commissioning processes to existing
buildings that were not originally commissioned, while continuous commissioning
is an ongoing proactive process .
6. Which ASHRAE guideline provides the primary framework for the
commissioning process?
A. ASHRAE Standard 90.1
B. ASHRAE Guideline 0
C. ASHRAE Standard 62.1
D. ASHRAE Standard 55
Questions
ASHRAE Continuous Commissioning Practices Exam
210 Practice Questions with Answers and Rationales
SECTION 1: FUNDAMENTALS OF CONTINUOUS COMMISSIONING (Questions 1-35)
1. Which statement best defines continuous commissioning in building systems?
A. A one-time verification process performed at project completion
B. A process focused only on HVAC equipment replacement cycles
C. A quality-focused, ongoing process for maintaining optimal system
performance throughout a building's life cycle
D. A systematic, ongoing process that monitors, verifies, and optimizes building
systems to ensure they continue meeting the Owner's Project Requirements
Answer: D
Rationale: Continuous commissioning is not a single event but an ongoing process
that ensures building systems remain efficient, properly controlled, and aligned
with the owner's requirements over time, extending beyond initial commissioning
into operation and maintenance phases .
,2. Which phase is most closely associated with the initiation of continuous
commissioning practices?
A. Construction only
B. Occupancy only
C. Post-demolition phase
D. Design and early operations phase, continuing through building life cycle
Answer: D
Rationale: Continuous commissioning typically begins early and continues through
operation, ensuring systems are optimized from design intent through long-term
performance .
3. The primary objective of continuous commissioning is to:
A. Reduce construction costs only
B. Eliminate all maintenance activities
C. Replace traditional commissioning entirely
,D. Maintain and improve system performance, energy efficiency, and occupant
comfort over time
Answer: D
Rationale: Its goal is sustained performance improvement, ensuring systems do
not drift away from intended design efficiency or functionality .
4. Which document most directly guides continuous commissioning activities?
A. Architectural floor plans
B. Construction permits
C. Manufacturer catalogues
D. Owner's Project Requirements (OPR)
Answer: D
Rationale: The OPR defines performance expectations, and continuous
commissioning ensures systems continue to meet those expectations over time .
, 5. Continuous commissioning differs from retro-commissioning in that it:
A. Only applies to existing buildings
B. Is performed only once every 10 years
C. Focuses solely on correcting HVAC failures
D. Is an ongoing, proactive process rather than a one-time diagnostic
Answer: D
Rationale: Retro-commissioning applies commissioning processes to existing
buildings that were not originally commissioned, while continuous commissioning
is an ongoing proactive process .
6. Which ASHRAE guideline provides the primary framework for the
commissioning process?
A. ASHRAE Standard 90.1
B. ASHRAE Guideline 0
C. ASHRAE Standard 62.1
D. ASHRAE Standard 55