NYC SITE SAFETY MANAGER (SSM) FINAL EXAM QUESTIONS WITH
DETAILED- VERIFIED ANSWERS- ALREADY GRADED A+ || NEWEST
EXAM 2025-2026
Construction Management / Site Safety Management
This practice exam covers the key areas of the NYC Site Safety Manager
(SSM) license test, based on the 2014 NYC Construction Codes and 1
RCNY. The test evaluates proficiency in:
• Duties and Responsibilities: Reporting structures, safety meetings,
plan administration, emergency procedures, incident
documentation, and coordination with contractors.
• NYC Construction Codes: Chapter 33 requirements for protection
of pedestrians, excavations, cranes, rigging, concrete construction,
demolition, and safety nets.
• Site Safety Plan: Elements of a plan, filing requirements, revisions,
and coordination between permit holders, general contractors, and
safety professionals.
• Rules of the City of New York: Subpart 1-01, which governs
definitions, general provisions, and enforcement, including penalty
structures.
1. What is the maximum penalty for failure to file an approved Site Safety
Plan and related documents for jobs requiring a Site Safety Manager?
A) The Department may only issue a warning.
B) The Department may impose a civil penalty of up to $5,000.
,Page 2 of 57
C) **The Department may impose a civil penalty of up to $10,000. **
D) The Department may only require the filing of the plan; no monetary
penalty may be levied.
Correct Answer: C. According to 1 RCNY §1-03, failure to file can result in
a civil penalty of up to $10,000.
Rationale: This significant penalty underscores the critical importance of
having a compliant plan filed for the safety of the project and the public.
2. A Site Safety Manager (SSM) is required to be present at all times when
a crane is being used. At what minimum frequency must logs of the
crane’s operation be maintained?
A) Once per shift.
B) At least daily.
C) Once per week.
D) At the start of the project only.
Correct Answer: B. The rules require all operation, inspection, and
maintenance logs of cranes be maintained at least daily【2†L1】.
Rationale: Daily logs create a reliable and current record of the
equipment's safety and operational status, which is critical for
identifying issues and protecting workers.
3. Which of the following is NOT one of the key areas of knowledge
required for an SSM?
A) NYC Building Code, Chapter 33.
B) National Fire Protection Association (NFPA) 101, Life Safety Code.
,Page 3 of 57
C) Subpart 1-01 of Title 1 of the Rules of the City of New York.
D) NYC Department of Buildings (DOB) Safety Bulletins.
Correct Answer: B. The exam is based on the 2014 NYC Construction
Codes, Chapter 33, and Subpart 1-01 of Title 1 of the Rules of the City of
New York【3†L14】. NFPA 101 is not explicitly listed.
Rationale: The exam focuses specifically on NYC’s administrative and
construction codes, not on general national fire codes.
4. A Construction Superintendent (CS) and a Site Safety Manager (SSM)
are on the same project. According to 1 RCNY §1-01, what is the primary
difference in their roles?
A) The CS is only responsible for tenant safety; the SSM is responsible for
worker safety.
B) The CS is responsible for construction activities and supervision; the
SSM is responsible for monitoring safety plans and hazardous
conditions.
C) The CS’s role is administrative; the SSM’s role is solely for demolition.
D) The CS is required to be on-site 100% of the time; the SSM is only
required for major crane lifts.
Correct Answer: B. The regulations specifically define a CS as the person
who supervises, directs, or has charge of the actual construction work,
while an SSM oversees site safety【4†L7】.
Rationale: This distinction ensures accountability for both the work itself
and the safety measures that protect people doing it.
5. What is the standard safety zone distance for a sidewalk shed?
, Page 4 of 57
A) 10 feet.
B) 5 feet.
C) 15 feet.
D) 8 feet.
Correct Answer: B. A sidewalk shed is required to provide a minimum 5-
foot clear path for pedestrians.
Rationale: This standard is designed to provide a safe and accessible
corridor for the public, protecting them from potential debris.
6. How often must a hoist be visually inspected by a designated person
before being used?
A) Once a year.
B) Once a month.
C) At the beginning of each shift.
D) Once a week.
Correct Answer: C. All equipment, including hoists, must be visually
inspected at the beginning of each shift.
Rationale: Inspections before each use help identify new damage or
wear that might have occurred since the last operation.
7. An architect files plans for a project, and the Department of Buildings
(DOB) issues a letter stating that the building’s Site Safety Manager must
be a Professional Engineer (P.E.). In this scenario, what is the role of the
P.E. in relation to the safety plan?
A) The P.E. is exempt from filing the site safety plan.