• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 60 pages
Exam (elaborations)

VA Alternative Energy System Contracting Practice Exam Questions And Answers With Verified Study Solutions Rated A+

Document preview thumbnail
Preview 4 out of 60 pages

1. A contractor installing a solar PV system for a VA medical center must comply with which structural load requirement? A) Only dead load of panels B) Dead + live + snow + wind loads per VA Master Specifications C) Just the weight of the inverter D) Manufacturer’s minimum load only Answer: B Explanation: VA facilities require adherence to VA Master Specifications, which mandate structural analysis for combined dead, live, snow, and wind loads—not just panel weight. Inverters are part of the electrical load, not structural. Manufacturer minimums are insufficient. 2. Under the VA Alternative Energy Contracting process, what is the first step in a Design-Build project? A) Issue Notice to Proceed B) Submit preliminary design for VA approval C) Conduct site feasibility study D) Award contract to lowest bidderAnswer: C Explanation: Site feasibility study (resource assessment, environmental, grid integration) must precede design submission. NTP comes after contract award; lowest bidder is not always selected due to best-value criteria. 3. Which geothermal heat pump configuration is preferred by VA for large-scale retrofits? A) Open-loop well system B) Horizontal closed-loop C) Vertical closed-loop D) Pond loop Answer: C Explanation: Vertical closed-loop minimizes land use and avoids groundwater contamination risks—critical for VA campuses with limited space. Open-loop risks fouling; horizontal requires large land area. 4. A VA solar PV contract requires prevailing wage rates under which federal act? A) Taft-Hartley Act B) Davis-Bacon Act C) Wagner Act D) Occupational Safety and Health Act Answer: B Explanation: Davis-Bacon Act applies to federal construction contracts $2,000. TaftHartley (labor relations), Wagner (collective bargaining), OSHA (safety) are not wage acts.5. When designing a wind turbine for a VA rural health clinic, the minimum average wind speed at hub height should be: A) 5 mph B) 8 mph C) 12 mph D) 20 mph Answer: C Explanation: 12 mph (5.4 m/s) is generally the economic cutoff for small wind. 5–8 mph are too low for viable generation; 20 mph is excellent but rare. 6. In VA contracting, a “change order” for an alternative energy system must be approved by whom if over $100,000? A) Project engineer B) Contracting Officer (CO) C) Site safety officer D) Prime contractor’s PM Answer: B Explanation: CO has authority for modifications $100k per FAR/VAAR. Engineer and PM recommend; safety officer irrelevant.

Content preview

VA Alternative Energy System
Contracting Practice Exam Questions
And Answers With Verified Study
Solutions Rated A+


1. A contractor installing a solar PV system for a VA medical center must comply with
which structural load requirement?
A) Only dead load of panels
B) Dead + live + snow + wind loads per VA Master Specifications
C) Just the weight of the inverter
D) Manufacturer’s minimum load only

Answer: B
Explanation: VA facilities require adherence to VA Master Specifications, which mandate
structural analysis for combined dead, live, snow, and wind loads—not just panel weight.
Inverters are part of the electrical load, not structural. Manufacturer minimums are
insufficient.




2. Under the VA Alternative Energy Contracting process, what is the first step in a
Design-Build project?
A) Issue Notice to Proceed
B) Submit preliminary design for VA approval
C) Conduct site feasibility study
D) Award contract to lowest bidder

,Answer: C
Explanation: Site feasibility study (resource assessment, environmental, grid integration)
must precede design submission. NTP comes after contract award; lowest bidder is not
always selected due to best-value criteria.




3. Which geothermal heat pump configuration is preferred by VA for large-scale
retrofits?
A) Open-loop well system
B) Horizontal closed-loop
C) Vertical closed-loop
D) Pond loop

Answer: C
Explanation: Vertical closed-loop minimizes land use and avoids groundwater
contamination risks—critical for VA campuses with limited space. Open-loop risks
fouling; horizontal requires large land area.




4. A VA solar PV contract requires prevailing wage rates under which federal act?
A) Taft-Hartley Act
B) Davis-Bacon Act
C) Wagner Act
D) Occupational Safety and Health Act

Answer: B
Explanation: Davis-Bacon Act applies to federal construction contracts >$2,000. Taft-
Hartley (labor relations), Wagner (collective bargaining), OSHA (safety) are not wage
acts.

,5. When designing a wind turbine for a VA rural health clinic, the minimum average
wind speed at hub height should be:
A) 5 mph
B) 8 mph
C) 12 mph
D) 20 mph

Answer: C
Explanation: 12 mph (5.4 m/s) is generally the economic cutoff for small wind. 5–8 mph
are too low for viable generation; 20 mph is excellent but rare.




6. In VA contracting, a “change order” for an alternative energy system must be
approved by whom if over $100,000?
A) Project engineer
B) Contracting Officer (CO)
C) Site safety officer
D) Prime contractor’s PM

Answer: B
Explanation: CO has authority for modifications >$100k per FAR/VAAR. Engineer and PM
recommend; safety officer irrelevant.




7. The maximum allowable voltage drop for a VA-installed solar PV feeder circuit per
NEC is:
A) 1%

, B) 2%
C) 3%
D) 5%

Answer: C
Explanation: NEC 690.8(A)(3) recommends 3% for feeders, 5% total including branches.
VA follows NEC strictly.




8. A biomass boiler system installed at a VA hospital must meet which EPA emissions
standard?
A) NSPS for boilers (40 CFR 60 Subpart Dc)
B) Clean Water Act
C) RCRA Subtitle C
D) NESHAP for asbestos

Answer: A
Explanation: New Source Performance Standards for biomass boilers apply. Clean Water
Act (water), RCRA (waste), asbestos NESHAP (air toxics) not primary.




9. The VA’s “Energy Independence and Security Act (EISA) 2007” requires federal
buildings to reduce fossil fuel use by what year and percentage?
A) 2030 – 50%
B) 2025 – 30%
C) 2030 – 100%
D) 2040 – 80%

Document information

Uploaded on
June 10, 2026
Number of pages
60
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Brainarium
3.8
(338)
Sold
2041
Followers
1048
Items
24274
Last sold
18 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions