,Question 1
5 process groups
Correct Answer
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Question 2
ten knowledge areas
Correct Answer
Integration
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder management
Trusted by thousands of students and professionals worldwide Page 2 of 107
,Question 3
total float formula
Correct Answer
total float = late finish - early finish
Question 4
normal distribution
Correct Answer
bell curve - symmetrical distribution - 50% chance of falling below the mean and 50% chance of falling above the
mean (1sigma=68.27%. 2sigma = 95.45%. 3sigma= 99.73%)
Question 5
triangular distribution
Correct Answer
when there are 3 possible values w/ equal probability - distribution is a triangle. A= lowest value, B= highest value,
M = most likely value
Question 6
beta distribution (PERT)
Correct Answer
triangular distribution w/ more weight given to the most likely estimate (can be asymmetrical). O = optimistic
estimate, ML=most likely estimate, P=pessimistic estimate
Question 7
mean for a beta distribution
Correct Answer
mean = (O + 4ML + P)/6
Trusted by thousands of students and professionals worldwide Page 3 of 107
, Question 8
standard deviation for beta distribution
Correct Answer
standard deviation = (P-O)/6
Question 9
statistical sums
Correct Answer
project mean is the sum of the means of the individual tasks. project standard deviation is the square root of the
project variance
Question 10
earned value management
Correct Answer
used to monitor the progress of a project and is an analytical technique. uses 3 independent values - PV, AC, EV
Question 11
planned value (PV)
Correct Answer
the budget or the portion of the approved cost estimate planned to be spent during a given period
Question 12
actual cost (AC)
Correct Answer
the total of direct and indirect costs incurred in accomplishing work during a given period
Question 13
earned value (EV)
Correct Answer
the budget for the work accomplished in a given period
Question 14
cost variance (CV)
Correct Answer
CV = EV - AC
Question 15
schedule variance (SV)
Correct Answer
SV = EV - PV
Trusted by thousands of students and professionals worldwide Page 4 of 107
740+ (Latest 2025-2026 Edition) 100%
Verified Q&A + Answer Key Solutions
100% Guarantee Pass
✓ This Exam contains: CAPM
✓ 100% Accurate Questions and Answers
✓ 100% Guarantee Pass - Verified by Experts
✓ Each Question Includes The Correct Answer
✓ Expert-Verified
Trusted by thousands of students and professionals worldwide Page 1 of 107
,Question 1
5 process groups
Correct Answer
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Question 2
ten knowledge areas
Correct Answer
Integration
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder management
Trusted by thousands of students and professionals worldwide Page 2 of 107
,Question 3
total float formula
Correct Answer
total float = late finish - early finish
Question 4
normal distribution
Correct Answer
bell curve - symmetrical distribution - 50% chance of falling below the mean and 50% chance of falling above the
mean (1sigma=68.27%. 2sigma = 95.45%. 3sigma= 99.73%)
Question 5
triangular distribution
Correct Answer
when there are 3 possible values w/ equal probability - distribution is a triangle. A= lowest value, B= highest value,
M = most likely value
Question 6
beta distribution (PERT)
Correct Answer
triangular distribution w/ more weight given to the most likely estimate (can be asymmetrical). O = optimistic
estimate, ML=most likely estimate, P=pessimistic estimate
Question 7
mean for a beta distribution
Correct Answer
mean = (O + 4ML + P)/6
Trusted by thousands of students and professionals worldwide Page 3 of 107
, Question 8
standard deviation for beta distribution
Correct Answer
standard deviation = (P-O)/6
Question 9
statistical sums
Correct Answer
project mean is the sum of the means of the individual tasks. project standard deviation is the square root of the
project variance
Question 10
earned value management
Correct Answer
used to monitor the progress of a project and is an analytical technique. uses 3 independent values - PV, AC, EV
Question 11
planned value (PV)
Correct Answer
the budget or the portion of the approved cost estimate planned to be spent during a given period
Question 12
actual cost (AC)
Correct Answer
the total of direct and indirect costs incurred in accomplishing work during a given period
Question 13
earned value (EV)
Correct Answer
the budget for the work accomplished in a given period
Question 14
cost variance (CV)
Correct Answer
CV = EV - AC
Question 15
schedule variance (SV)
Correct Answer
SV = EV - PV