ASHRAE BCxP Practice Exam with
answers
The owner's project requirements (OPR) document should
include - CORRECT ANSWERS ✔✔equipment and system
expectations, energy efficiency requirements, and
operational schedules.
When starting a commissioning project, the FIRST person
added to a project team after an owner's project manager
should be a - CORRECT ANSWERS ✔✔commissioning
professional.
The owner of several office buildings intends to build a
multi-family residential building. The owner intends to use
current employees, including property managers and
maintenance staff, to operate and maintain the new
building. Which of the following should the commissioning
professional do FIRST? - CORRECT ANSWERS
✔✔Determine new facility staff training requirements.
During the pre-design stage of the construction of a new
surgical hospital, the owner determines that the
commissioning process should include verification of the
medical equipment in the owner's project requirements. A
commissioning professional FIRST should modify the -
, CORRECT ANSWERS ✔✔owner-commissioning
professional agreement.
A new elementary school will replace a 60-year-old facility
and will be operated by the same O&M staff. The new
building will be air conditioned with a high-efficiency,
water-cooled chiller and heated with a condensing boiler.
The O&M staff was interviewed and is very proficient with
direct expansion (DX) systems. Which of the following
should the commissioning professional do regarding
systems maintenance? - CORRECT ANSWERS ✔✔Suggest
that additional training be specified for the new systems.
An owner of a museum collection has special temperature
and humidity requirements for a new facility in a cold
climate. Temperature setpoint should be maintained
within 2 ⁰F (1.1 ⁰C), and relative humidity should remain
within 2.5% of 42.5%. During the pre-design phase, the
owner's project requirements are developed to include
these requirements. Which of the following should be
done NEXT? - CORRECT ANSWERS ✔✔Confirm that the
basis of design includes these requirements.
For newly constructed buildings, the majority of O&M
personnel training should be scheduled to occur after -
CORRECT ANSWERS ✔✔performance testing.
answers
The owner's project requirements (OPR) document should
include - CORRECT ANSWERS ✔✔equipment and system
expectations, energy efficiency requirements, and
operational schedules.
When starting a commissioning project, the FIRST person
added to a project team after an owner's project manager
should be a - CORRECT ANSWERS ✔✔commissioning
professional.
The owner of several office buildings intends to build a
multi-family residential building. The owner intends to use
current employees, including property managers and
maintenance staff, to operate and maintain the new
building. Which of the following should the commissioning
professional do FIRST? - CORRECT ANSWERS
✔✔Determine new facility staff training requirements.
During the pre-design stage of the construction of a new
surgical hospital, the owner determines that the
commissioning process should include verification of the
medical equipment in the owner's project requirements. A
commissioning professional FIRST should modify the -
, CORRECT ANSWERS ✔✔owner-commissioning
professional agreement.
A new elementary school will replace a 60-year-old facility
and will be operated by the same O&M staff. The new
building will be air conditioned with a high-efficiency,
water-cooled chiller and heated with a condensing boiler.
The O&M staff was interviewed and is very proficient with
direct expansion (DX) systems. Which of the following
should the commissioning professional do regarding
systems maintenance? - CORRECT ANSWERS ✔✔Suggest
that additional training be specified for the new systems.
An owner of a museum collection has special temperature
and humidity requirements for a new facility in a cold
climate. Temperature setpoint should be maintained
within 2 ⁰F (1.1 ⁰C), and relative humidity should remain
within 2.5% of 42.5%. During the pre-design phase, the
owner's project requirements are developed to include
these requirements. Which of the following should be
done NEXT? - CORRECT ANSWERS ✔✔Confirm that the
basis of design includes these requirements.
For newly constructed buildings, the majority of O&M
personnel training should be scheduled to occur after -
CORRECT ANSWERS ✔✔performance testing.