In a bottom up approach, the estimated duration of project activities is based on
__________
A. Work Packages
B. the Budget
C. Strategic Business Units
D. the Schedule - Answers - A. Work Packages
Which of the following is NOT true about a network diagram?
A. To construct it, activity duration estimates are unnecessary
B. It illustrates logical dependencies among project activities
C. It is necessary for identifying the critical path
D. It shows start & finish calendar dates of project activities - Answers - D. It shows start
& finish calendar dates of project activities
In a project network, __________ activities must be completed before a particular
activity
Predecessor
Merge - Answers - Predecessor
Some of the information needed to develop a project network diagram is collected from
the __________
Schedule
Budget
Responsibility Matrix
Work Breakdown Structure - Answers - Work Breakdown Structure
The forward pass in project network calculations determines all of the following except:
The critical path
Duration of the project
Earliest time an activity can finish
Earliest time an activity can begin - Answers - The critical path
Which of the following is NOT part of the initial cost estimates for work packages?
ANSWERS
In a bottom up approach, the estimated duration of project activities is based on
__________
A. Work Packages
B. the Budget
C. Strategic Business Units
D. the Schedule - Answers - A. Work Packages
Which of the following is NOT true about a network diagram?
A. To construct it, activity duration estimates are unnecessary
B. It illustrates logical dependencies among project activities
C. It is necessary for identifying the critical path
D. It shows start & finish calendar dates of project activities - Answers - D. It shows start
& finish calendar dates of project activities
In a project network, __________ activities must be completed before a particular
activity
Predecessor
Merge - Answers - Predecessor
Some of the information needed to develop a project network diagram is collected from
the __________
Schedule
Budget
Responsibility Matrix
Work Breakdown Structure - Answers - Work Breakdown Structure
The forward pass in project network calculations determines all of the following except:
The critical path
Duration of the project
Earliest time an activity can finish
Earliest time an activity can begin - Answers - The critical path
Which of the following is NOT part of the initial cost estimates for work packages?