A likely precipitation event is any weather pattern that is forecasted to
have a ____% or greater probability of producing precipitation in the
project area.
a. 10
b. 25
c. 50
d. 75
e. 99 - ............ANSWER..........C
A QSP is responsible for:
a. Day to day implementation, inspections, and observations
b. Amending the SWPPP as required
c. Developing and certifying the SWPPP
d. Certifying reports in SMARTS
- ............ANSWER..........a. Day to day implementation, inspections, and
observations
A storm that produces ½ inch or more of precipitation, with a 48 hour or
greater period between rain events is a/an...
,
a. Qualifying rain event
b. Extended storm event
c. Inactive storm event
d. Unsafe monitoring event
- ............ANSWER..........a. Qualifying rain event
A temporary or permanent structural BMP that directs concentrated
flows away from disturbed areas and prevents erosion is...
a. erosion control
b. run on/ run off control
c. sediment control - ............ANSWER..........b. run on/ run off control
Acceptable methods to demonstrate final stabilization include:
a. 50%vegetative coverage
b. 100% vegetative coverage
c. RUSLE 2 method - ............ANSWER..........c. RUSLE 2 method
Activities under the CGP include:
a. Routine maintenance to maintain original line and grade, hydraulic
capacity, or original purpose of the facility.
,
b. Disturbances to land surfaces solely related to agricultural operations.
c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands.
- ............ANSWER..........c. Clearing and grading 2 acres of land
All NAL data must be uploaded within ___ after NAL exceedance has
been identified
a. 24 hours
b. 1 week
c. 10 days
d. 2 weeks - ............ANSWER..........c. 10 days
Certain non-storm water discharges may be necessary for the completion
of construction projects. Therefore the General Permit authorizes such
discharges provided they meet the following conditions except:
a. Meet the NALs for pH and turbidity
b. Not cause or contribute to a violation of water quality standards
c. Comply with BMPs as described in the SWPPP
d. Be infeasible to eliminate
e. Causes or threatens to cause pollution, contamination, or nuisance
- ............ANSWER..........e. Causes or threatens to cause pollution,
contamination, or nuisance
,
Hydrologic source controls are a design technique that minimize and/or
slow the rate of stormwater runoff from the site. Examples include:
a. Reduction of pervious surfaces
b. Use of landscaping as a storm drain treatment feature
c. Drain rooftop downspouts to impervious areas
d. Stormwater treatment facility - ............ANSWER..........b. Use of
landscaping as a storm drain treatment feature
If the R Factor is ____, you can apply for the Erosivity Waiver.
a. 1
b. Less than 1
c. 5
d. Less than 5 - ............ANSWER..........d. Less than 5
NEL Violation Reports must be submitted to State Board within 24 hours
after exceedance has been identified. NEL's are only subject to:
a. Risk Level 1
b. Risk Level 2
c. Risk Level 3
d. ATS Sites only - ............ANSWER..........d. ATS Sites only