Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 3 out of 17 pages
Exam (elaborations)

GENERAL BUILDING CONTRACTOR (B) LICENSE LATEST EXAM WITH 125 QUESTIONS AND WELL-VERIFIED CORRECT ANSWERS | ALREADY GRADED A+ | GENERAL BUILDING CONTRACTOR LICENSE EXAM 2026

Document preview thumbnail
Preview 3 out of 17 pages

GENERAL BUILDING CONTRACTOR (B) LICENSE LATEST EXAM WITH 125 QUESTIONS AND WELL-VERIFIED CORRECT ANSWERS | ALREADY GRADED A+ | GENERAL BUILDING CONTRACTOR LICENSE EXAM 2026 Describe the degree of access the Division of Labor Standards Enforcement has to places of employment in CA. - ANSWER-The Division has the right to free access to all places of employment in CA. It is illegal for an employer to refuse entry to an agent of this division. What is the difference between a strike and a lockout? - ANSWER-In a strike, employees refuse to work until an agreement is reached. In a lockout, employers prevent employees from working until an agreement is reached. Professional strikebreaker - ANSWER-A person who has within the past five years become a replacement employee for two or more businesses in the time of strike or lockout.

Content preview

GENERAL BUILDING CONTRACTOR (B)
LICENSE LATEST EXAM 2026-2027 WITH
125 QUESTIONS AND WELL-VERIFIED
CORRECT ANSWERS | ALREADY GRADED
A+ | GENERAL BUILDING CONTRACTOR
LICENSE EXAM 2026




Describe the degree of access the Division of Labor Standards Enforcement has to
places of employment in CA. - ANSWER-The Division has the right to free access
to all places of employment in CA. It is illegal for an employer to refuse entry to
an agent of this division.


What is the difference between a strike and a lockout? - ANSWER-In a strike,
employees refuse to work until an agreement is reached. In a lockout, employers
prevent employees from working until an agreement is reached.


Professional strikebreaker - ANSWER-A person who has within the past five years
become a replacement employee for two or more businesses in the time of strike or
lockout.

,What is the penalty for being or knowingly hiring a professional strikebreaker? -
ANSWER-A minimum $1000 fine and a possibly a sentence of up to 90 days in
the county jail.


When must an employee be paid double overtime? - ANSWER-(1) The employee
has worked more than 12 hours in a day.
(2) The employee has worked more than 8 hours on a 7th consecutive day.


If an employee provides a 72-hour notice to his employer that he's quitting, when
are his wages due? - ANSWER-At his last shift


When are an employee's wages due if he does not provide a 72-hour notice when
he quits? - ANSWER-72 hours after his last shift


What can an employee do if he does not receive his wages? - ANSWER-He can
file a complaint with the Labor Commissioner.


Which one must be filed with the County Recorder--a stop notice or a mechanics'
lien? - ANSWER-Mechanics' lien


Qualifying Individual - ANSWER-AKA *Qualifier*
The person who meets the experience and examination requirements for the
license. The qualifier is responsible for exercising *direct supervision and control*
of their employer's or principal's construction operations to secure compliance with
the CSLB.


What's the time limit for filing mechanic's liens on a property? - ANSWER-90
days following the completion of a contract

, What's the difference between mechanics' liens and stop notices? - ANSWER-
Mechanics' liens can only be filed on private property while stop notices are filed
on public property. A stop notice isn't a lien on property--it's a lien on funds. The
public property can still be sold or financed, but the responsible entity must set
aside funds to satisfy the contractor's stop notice.


How can the owner shorten the 90-day lien period for a completed contract? -
ANSWER-By filing a *Notice of Completion*, which shortens the lien period to
30 days for a subcontractor and 60 days for a contractor. The clock starts on the
filing date of the Notice.




To whom should a stop notice be delivered? - ANSWER-The construction lender
or awarding authority.


What are the 3 ways that a stop notice can be delivered? - ANSWER-(1) In person
(2) Registered mail
(3) Certified mail


Notice of Completion - ANSWER-A notice that shortens the lien period to 30 days
for a subcontractor and 60 days for a contractor. The clock starts on the filing date
of the Notice.


notice of nonresponsibility - ANSWER-A notice provided by law designed to
relieve the property owner from responsibility for the cost of unauthorized work
done on the property or materials furnished thereof.


notice of cessation - ANSWER-Notice that can be filed by a property owner after
work on a construction project has been stopped for 30 continuous days

Document information

Uploaded on
May 4, 2026
Number of pages
17
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$22.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Sold
55
Followers
6
Items
1366
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions