●● In contrast to traditional project management, Scrum work is
completed in small cycles called _____.
Answer: Sprints
●● Scrum is based on the concept of Empirical Process Control, which
prioritizes decisions based on _____.
Answer: Real experience.
●● Name the three fundamental pillars that support the success of the
Scrum framework.
Answer: Transparency, Inspection, and Adaptation.
●● Which pillar of Scrum ensures that all important information about
the process and product is visible to those involved?
Answer: Transparency.
●● What is the likely consequence if a Scrum team lacks transparency in
their work and progress?
, Answer: Teams cannot make informed decisions and issues may remain
hidden too long.
●● Give an example of how transparency is maintained regarding the
features being built for a product.
Answer: The Product Backlog and Sprint Backlog are kept openly
visible to all stakeholders.
●● How does a well-defined 'Definition of Done' contribute to the
Scrum pillar of transparency?
Answer: It ensures every team member understands exactly what is
required before a task is marked complete.
●● The Scrum pillar of _____ involves regularly checking work
progress and team collaboration to identify issues early.
Answer: Inspection
●● What is the primary purpose of the inspection that occurs during the
Daily Scrum?
Answer: To ensure the team is on track to achieve the Sprint Goal.
●● During which Scrum event is the delivered Increment inspected to
gather stakeholder feedback?
Answer: The Sprint Review.
QUESTIONS ANSWERS COMPLETE
SOLUTION BUNDLE
●● In contrast to traditional project management, Scrum work is
completed in small cycles called _____.
Answer: Sprints
●● Scrum is based on the concept of Empirical Process Control, which
prioritizes decisions based on _____.
Answer: Real experience.
●● Name the three fundamental pillars that support the success of the
Scrum framework.
Answer: Transparency, Inspection, and Adaptation.
●● Which pillar of Scrum ensures that all important information about
the process and product is visible to those involved?
Answer: Transparency.
●● What is the likely consequence if a Scrum team lacks transparency in
their work and progress?
, Answer: Teams cannot make informed decisions and issues may remain
hidden too long.
●● Give an example of how transparency is maintained regarding the
features being built for a product.
Answer: The Product Backlog and Sprint Backlog are kept openly
visible to all stakeholders.
●● How does a well-defined 'Definition of Done' contribute to the
Scrum pillar of transparency?
Answer: It ensures every team member understands exactly what is
required before a task is marked complete.
●● The Scrum pillar of _____ involves regularly checking work
progress and team collaboration to identify issues early.
Answer: Inspection
●● What is the primary purpose of the inspection that occurs during the
Daily Scrum?
Answer: To ensure the team is on track to achieve the Sprint Goal.
●● During which Scrum event is the delivered Increment inspected to
gather stakeholder feedback?
Answer: The Sprint Review.