▶ Once a site has experienced a rain event of measurable quantity you
must identify. Answer: Deficit and fialed BMP's and repair
▶ The document that contains the permit number is. Answer: The permit
authorization letter
▶ The portion of the the SWPPP that specifies the content of the SWPPP
is. Answer: The table of contents
▶ The document in the SWPPP that certifies the GC's commitment to
compliance with the SWPPP. Answer: The SWPPP certification letter
▶ The certifactions letter that identifies the name and contact information of
subcontractors on the site is. Answer: The subcontractors certification form
▶ The documents that reveal the total area of disturbance are. Answer:
The site maps
▶ The document completed by the project SWPPP inspector recording site
conditions during the inspection is. Answer: The inspection report form
▶ The document that must be completed to report hazardous spill on site
is. Answer: The spill report form
▶ The document that verifies that weekly management meetings have
been conducted is. Answer: The weekly meeting form
▶ The document delegating responsibility of inspections to another is.
Answer: The delegation letter
▶ The document that must be completed when final stabilization is
complete is. Answer: The NOT
, ▶ Scheduling. Answer: Aids in protecting the site by timing construction
activities
▶ Factors to consider when creating your schedule include. Answer:
Account for the time it takes to install or implement BMP's between each
phase of construction
▶ When installing perimeter BMP controls. Answer: Note to locations and
dates for installation on site map
▶ Stormwater issues are usually discussed during the pre-con meeting
include. Answer: SWPPP BMP's and construction schedule
▶ Sediment control devices must be installed. Answer: Down slope of
construction areas and functioning as designed prior to beginning land
disturbing activities
▶ If you have stormwater inlets in your construction roadway. Answer:
Consult your project SWPPP to ensure you are protecting inlets properly
▶ Soil stock piles and other disturb areas must receive. Answer:
Temporary stabilization if they will remain in active for more than 14 days
and potentially fewer days depending on the jurisdiction
▶ In the process of transitioning form Lan development to building
construction it is important to. Answer: Implement specific BMP's to
address potential pollution associated with construction materials
▶ The SWPPP sequence of activities can be modified. Answer: After
consulting the project SWPPP designer and or project owner and receiving
approval
▶ Once the notice of termination is filed store all stormwater related project
information. Answer: For three years or more depending on permit and
contact obligation
▶ When installing perimeter BMP controls. Answer: No locations and
dates of installation on site map
COMPLETE STUDY GUIDE 2026
▶ Once a site has experienced a rain event of measurable quantity you
must identify. Answer: Deficit and fialed BMP's and repair
▶ The document that contains the permit number is. Answer: The permit
authorization letter
▶ The portion of the the SWPPP that specifies the content of the SWPPP
is. Answer: The table of contents
▶ The document in the SWPPP that certifies the GC's commitment to
compliance with the SWPPP. Answer: The SWPPP certification letter
▶ The certifactions letter that identifies the name and contact information of
subcontractors on the site is. Answer: The subcontractors certification form
▶ The documents that reveal the total area of disturbance are. Answer:
The site maps
▶ The document completed by the project SWPPP inspector recording site
conditions during the inspection is. Answer: The inspection report form
▶ The document that must be completed to report hazardous spill on site
is. Answer: The spill report form
▶ The document that verifies that weekly management meetings have
been conducted is. Answer: The weekly meeting form
▶ The document delegating responsibility of inspections to another is.
Answer: The delegation letter
▶ The document that must be completed when final stabilization is
complete is. Answer: The NOT
, ▶ Scheduling. Answer: Aids in protecting the site by timing construction
activities
▶ Factors to consider when creating your schedule include. Answer:
Account for the time it takes to install or implement BMP's between each
phase of construction
▶ When installing perimeter BMP controls. Answer: Note to locations and
dates for installation on site map
▶ Stormwater issues are usually discussed during the pre-con meeting
include. Answer: SWPPP BMP's and construction schedule
▶ Sediment control devices must be installed. Answer: Down slope of
construction areas and functioning as designed prior to beginning land
disturbing activities
▶ If you have stormwater inlets in your construction roadway. Answer:
Consult your project SWPPP to ensure you are protecting inlets properly
▶ Soil stock piles and other disturb areas must receive. Answer:
Temporary stabilization if they will remain in active for more than 14 days
and potentially fewer days depending on the jurisdiction
▶ In the process of transitioning form Lan development to building
construction it is important to. Answer: Implement specific BMP's to
address potential pollution associated with construction materials
▶ The SWPPP sequence of activities can be modified. Answer: After
consulting the project SWPPP designer and or project owner and receiving
approval
▶ Once the notice of termination is filed store all stormwater related project
information. Answer: For three years or more depending on permit and
contact obligation
▶ When installing perimeter BMP controls. Answer: No locations and
dates of installation on site map