Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 92 pages
Exam (elaborations)

WGU C722 Project Management Pre-assessment Actual Exam (Latest 2026 Update) – Complete Questions and Correct Verified Answers/ C722 Pre-assessment Test| Already Graded A+

Document preview thumbnail
Preview 4 out of 92 pages

WGU C722 Project Management Pre-assessment Actual Exam (Latest 2026 Update) – Complete Questions and Correct Verified Answers/ C722 Pre-assessment Test| Already Graded A+

Content preview

WGU C722 Project Management Pre-assessment Actual Exam
(Latest 2026 Update) – Complete Questions and Correct Verified
Answers/ C722 Pre-assessment Test| Already Graded A+
A firm begins its strategic business initiative of developing a new
business model that will allow the firm to deliver an efficient, tailored
service to its customers. To accomplish this, the firm initiates a
business management project. Which aspect of project management
applies to this firm's project? - Answer -Interdependent Tasks


A firm begins its strategic business initiative of developing a new
business model to enhance its competitiveness. What can be identified
as a strategic business initiative for this firm? - Answer -Improvement
in product design


A firm begins a strategic business initiative of developing a new
business model that will allow the firm to deliver an efficient, tailored
service to its customers. - Answer -Project sponsor


Which group is included in the five process groups? - Answer -
Closing process group


What does PRINCE2 stand for? - Answer -PRojects IN a Controlled
Environment


Which PMBOK process group is described as the delivery part of
project management where the main activity happens? - Answer -
Executing




pg. 1

,Which advantage does the functional (departmentalized)
organizational structure provide for a firm with multiple projects? -
Answer -Lines of authority are clear.


Which two organizations are examples of organizations with the
functional organizational structure? - Answer -(1) The U.S.
Department of State and (2) The U.S Department of Energy


An organization expects to use a project management office (PMO) to
support multiple projects that will be implemented within a
projectized organizational structure. Which implied effect is a benefit
to this organization? - Answer -Project team members gain access to
historical data from other projects.


Regardless of the organizational structure used to manage a project,
an organization elects to use a project management office (PMO).
Which benefit will this organization gain? - Answer -Projects will
coordinate resource usage by monitoring the status of shared
resources.


During a certain project phase, specific blueprints are drawn and
approved, materials and labor costs are estimated, prototypes are
created, and work activities and tasks are identified. Also, quality
expectations, measurements, and costs are defined. During which
project phase do these activities occur? - Answer -Planning


Place the project activities in order of occurrence from first (1) to last
(5). - Answer - (1) Collecting customer requirements (2) Developing
the work breakdown structure (3) Working to produce project
deliverables (4) Customers evaluating the project outcomes (5)
Capturing lessons learned

pg. 2

,During which life cycle phase is the vast majority of the actual work
to produce the project's deliverables completed? - Answer -Executing


What is the correct term for an intermediate outcome of project work,
such as a signed contract or obtaining a construction permit? - Answer
-Deliverable


Which deliverable from a work breakdown structure (WBS) is not
specific enough to measure its completion at project closure? -
Answer -User training


The following table shows the Level 1 work breakdown structure
(WBS) for Project A.
WBS ID Description
0.0 Project A
1.0 Project started
2.0 Feasiblity
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
Which approach did the project manager use to structure the WBS? -
Answer -Sequence of project phases




pg. 3

, For the following collapsed work breakdown structure (WBS) for
Project O, the project manager must complete the scope baseline. In
addition to the WBS, the scope baseline will contain two additional
documents.
WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
What are the other two documents that belong in the scope baseline? -
Answer -WBS dictionary and project scope statement


For the following collapsed work breakdown structure (WBS) for
Project O, the project's steering committee held a phase gate review of
the Feasibility results. That review determined that the project's
proposed design would be obsolete before it would reach the
marketplace.
WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development


pg. 4

Document information

Uploaded on
April 21, 2026
Number of pages
92
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$17.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
105
Last sold
-



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions