Section 1: Role & Responsibilities of the Permit Technician (Questions 1–15)
Q1: What is the primary responsibility of a permit technician when receiving an incomplete permit
application?
A. Approve the application and issue the permit immediately
B. Reject the application outright and require a new submission
C. Accept the application, document deficiencies, and notify the applicant of required corrections
[CORRECT]
D. Complete the missing information on behalf of the applicant
Correct Answer: C Rationale: Per ICC Administrative Code provisions, permit technicians serve as the
initial point of contact and must facilitate the application process by identifying deficiencies while
maintaining the application in the system. B is incorrect because outright rejection without giving the
applicant opportunity to correct deficiencies violates customer service standards and efficient
processing protocols; the technician's role is to guide applicants through compliance, not to act as a
barrier.
Q2: A permit technician may NOT perform which of the following actions?
A. Verify that required documents are submitted with an application
B. Calculate permit fees based on established valuation tables
C. Interpret structural engineering calculations to determine code compliance [CORRECT]
D. Route plans to the appropriate reviewing disciplines
,Correct Answer: C Rationale: Plan review and technical interpretation of engineering calculations fall
under the authority of licensed design professionals and code officials (IBC 2024 Section 107.1). Permit
technicians handle administrative processing, not technical code interpretation. B is a standard permit
technician duty under ICC Administrative Provisions Chapter 1.
Q3: When a permit technician encounters a question regarding code interpretation during intake, the
appropriate action is to:
A. Provide the interpretation based on personal experience
B. Refer the question to the building official or designated code official [CORRECT]
C. Deny the permit until the applicant provides clarification
D. Consult with the contractor and accept their interpretation
Correct Answer: B Rationale: Code interpretation authority resides with the building official or their
designated representatives (IBC 2024 Section 104.1). Permit technicians must escalate technical
questions rather than assume interpretive authority. A violates the separation of administrative and
technical functions; D improperly delegates code authority to regulated parties.
Q4: The permit technician's role in the plan review process includes:
A. Conducting structural load path analysis
B. Verifying that plans contain all required information for routing [CORRECT]
C. Approving fire-resistance rated assemblies
D. Conducting field inspections
Correct Answer: B Rationale: Permit technicians ensure completeness of submissions for routing to
appropriate review disciplines but do not conduct technical reviews (ICC Administrative Provisions). A
and C are plan review functions; D is an inspection function—both require technical certifications
beyond permit technician scope.
Q5: Which document establishes the legal authority for a permit technician to perform their duties?
A. The International Building Code only
B. The jurisdiction's adopted code and enabling ordinance [CORRECT]
C. The contractor's license agreement
D. The architect's seal and certification
Correct Answer: B Rationale: Permit technician authority derives from the jurisdiction's enabling
legislation that adopts ICC codes and establishes administrative procedures (ICC Administrative Code
, Chapter 1). A is incomplete because the IBC alone does not create administrative authority; C and D
confuse regulated party credentials with governmental authority.
Q6: A permit technician must maintain confidentiality regarding:
A. Only building permit fees
B. All applicant information and building plans except public record requirements [CORRECT]
C. Only commercial project details
D. No information, as all permit records are public
Correct Answer: B Rationale: While permits and approved plans become public record upon issuance,
applications under review and proprietary information require confidentiality protection per ICC ethics
standards and state public records laws. D is incorrect because incomplete applications and certain
proprietary details (trade secrets, security plans) may be exempt from disclosure.
Q7: When processing permits for multiple jurisdictions, a permit technician must:
A. Apply the most lenient jurisdiction's standards
B. Apply each jurisdiction's adopted codes and amendments [CORRECT]
C. Apply ICC model codes without local amendments
D. Allow the applicant to choose which jurisdiction's codes apply
Correct Answer: B Rationale: Each jurisdiction's locally adopted code, including amendments,
supersedes model codes (ICC Administrative Code Section 101.2). C ignores local amendments which
may modify requirements; A and D violate the principle of uniform application within each jurisdiction.
Q8: The permit technician should verify contractor licensing status:
A. Only for commercial projects
B. Only when requested by the building official
C. For all projects requiring licensed contractors per state law [CORRECT]
D. Never, as this is the contractor's responsibility
Correct Answer: C Rationale: Most jurisdictions require verification of contractor licensure at permit
issuance to ensure compliance with state contractor board requirements (IBC 2024 Section 105.1.1). A is
incorrect because residential projects often require licensed contractors; D neglects the jurisdiction's