One main category variable of pressure test planning that an operator must consider is the
_________________. - CORRECT ANSWER - purpose
Field beveling of pipe ends by manual oxygen cutting is acceptable if authorized by the company. -
CORRECT ANSWER - True
Location of casings cathode protection external anodes, and utility crossings should all be recorded on
the. - CORRECT ANSWER - as-built drawings
Releasing air or water pressure through valves, at a test head, after the testing of a pipe is called
a____________. - CORRECT ANSWER - blow down
The side of the right of way opposite the ditch line from the working side and typically the location of the
spoil pile. - CORRECT ANSWER - ditch side
CFR stands for _____________. - CORRECT ANSWER - Code of Federal Regulations
The EPA's Hazardous Substance Response information can be found in what code? - CORRECT
ANSWER - 40 CFR 300
Pipelines that transport oil or natural gas from the wellhead to a transmission line. For hazardous liquid
pipelines a _________________ is a pipeline that is no more than 8 5/8 in diameter and transports
petroleum from a production - CORRECT ANSWER - gathering line
Title 49, CFR 192. The minimum depth of cover of a pipeline crossing under a drainage ditch of a public
roadway is__________________. - CORRECT ANSWER - 36"
, The toe of a weld is located _______________. - CORRECT ANSWER - at the junction of the
weld face and base metal
According to the Department of Transportation, use of the prefix àCcemonoãE is ______________ in any
shipping name, when appropriate and, therefore, in aEoeGlycerol alpha-monochlorohydrinaE the term
a€oemonoaE is considered a prefix to the term âecechlorohydrinae and may be deleted. - CORRECT
ANSWER - None of these answers are correct
Pipeline segments installed by directional drilling shall be inspected for - CORRECT ANSWER -
cross section deformation
The fit of the pipe to ditch should be inspected __________ the backfilling operations. - CORRECT
ANSWER - prior to
When a bore hole is at least _____________ larger than the pipe to be installed, the end of the drill pipe is
connected to a reamer that is attached to a swivel that is connected to the product pipe. - CORRECT
ANSWER - 25%
During pneumatic tests, what needs to be installed in line to protect testing equipment and the facility
being tested? - CORRECT ANSWER - regulator
Title 49, CFR 195. A hydro-test being performed on new buried pipeline must be tested for at least
____________ additonal hours at a pressure equal to or greater than ____________ of MOP if it will not
be visually inspected for leaks test. - CORRECT ANSWER - 4, 110%
According to OSHA, where oxygen deficiency or a hazardous atmosphere exists or could reasonably be
expected to exist, such as in excavations in landfill areas or excavations in areas where hazardous
substances are stored nearby, the atmospheres in the excavation shall be tested before employees enter
excavations greater than _______________ in depth. - CORRECT ANSWER - 4 feet
The stress in a pipe of wall thickness, t, acting circumferentially in a plane perpendicular to the
longitudinal axis of the pipe, produced by the pressure, P, of the fluid in pipe of diameter, D, and is
determined by BarlowaETMs formula. - CORRECT ANSWER - Hoop stress
UPDATED ACTUAL Questions and
CORRECT Answers
One main category variable of pressure test planning that an operator must consider is the
_________________. - CORRECT ANSWER - purpose
Field beveling of pipe ends by manual oxygen cutting is acceptable if authorized by the company. -
CORRECT ANSWER - True
Location of casings cathode protection external anodes, and utility crossings should all be recorded on
the. - CORRECT ANSWER - as-built drawings
Releasing air or water pressure through valves, at a test head, after the testing of a pipe is called
a____________. - CORRECT ANSWER - blow down
The side of the right of way opposite the ditch line from the working side and typically the location of the
spoil pile. - CORRECT ANSWER - ditch side
CFR stands for _____________. - CORRECT ANSWER - Code of Federal Regulations
The EPA's Hazardous Substance Response information can be found in what code? - CORRECT
ANSWER - 40 CFR 300
Pipelines that transport oil or natural gas from the wellhead to a transmission line. For hazardous liquid
pipelines a _________________ is a pipeline that is no more than 8 5/8 in diameter and transports
petroleum from a production - CORRECT ANSWER - gathering line
Title 49, CFR 192. The minimum depth of cover of a pipeline crossing under a drainage ditch of a public
roadway is__________________. - CORRECT ANSWER - 36"
, The toe of a weld is located _______________. - CORRECT ANSWER - at the junction of the
weld face and base metal
According to the Department of Transportation, use of the prefix àCcemonoãE is ______________ in any
shipping name, when appropriate and, therefore, in aEoeGlycerol alpha-monochlorohydrinaE the term
a€oemonoaE is considered a prefix to the term âecechlorohydrinae and may be deleted. - CORRECT
ANSWER - None of these answers are correct
Pipeline segments installed by directional drilling shall be inspected for - CORRECT ANSWER -
cross section deformation
The fit of the pipe to ditch should be inspected __________ the backfilling operations. - CORRECT
ANSWER - prior to
When a bore hole is at least _____________ larger than the pipe to be installed, the end of the drill pipe is
connected to a reamer that is attached to a swivel that is connected to the product pipe. - CORRECT
ANSWER - 25%
During pneumatic tests, what needs to be installed in line to protect testing equipment and the facility
being tested? - CORRECT ANSWER - regulator
Title 49, CFR 195. A hydro-test being performed on new buried pipeline must be tested for at least
____________ additonal hours at a pressure equal to or greater than ____________ of MOP if it will not
be visually inspected for leaks test. - CORRECT ANSWER - 4, 110%
According to OSHA, where oxygen deficiency or a hazardous atmosphere exists or could reasonably be
expected to exist, such as in excavations in landfill areas or excavations in areas where hazardous
substances are stored nearby, the atmospheres in the excavation shall be tested before employees enter
excavations greater than _______________ in depth. - CORRECT ANSWER - 4 feet
The stress in a pipe of wall thickness, t, acting circumferentially in a plane perpendicular to the
longitudinal axis of the pipe, produced by the pressure, P, of the fluid in pipe of diameter, D, and is
determined by BarlowaETMs formula. - CORRECT ANSWER - Hoop stress