What are the five project management process groups? - Answer
What occurs in the process group: Initiating - Answer 1. Develop Project Charter
2. Identify Stakeholders
What occurs in the process group: Planning - Answer 1. Develop Project Management Plan
2. Plan scope management
3. Collect Requirements
4. Define Scope
5. Create WBS
6. Plan Schedule management
7. Define Activities
8. Sequence Activities
9. Estimate Activity Durations
10. Develop Schedule
11. Plan Cost Management
12. Estimate Costs
13. Determine budget
14. Plan quality management
15. Plan resource management
16. Estimate activity resources
17. Plan communications management
18. Plan risk management
19. Identify risks
20. Perform quantitative risk analysis
21. Plan risk responses
22. Plan procurement management
23. Plan stakeholder engagement
What occurs in the process group: Executing - Answer 1. Direct and manage project work
2. Manage project knowledge
3. Manage Quality
4. Acquire resources