Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 31 pages
Exam (elaborations)

CAPM (Certified Associate in Project Management) COMPLETE EXAM QUESTIONS AND 100% VERIED ANSWERS WITH LATEST VERSION 2026.

Document preview thumbnail
Preview 4 out of 31 pages

CAPM (Certified Associate in Project Management) COMPLETE EXAM QUESTIONS AND 100% VERIED ANSWERS WITH LATEST VERSION 2026.

Content preview

CAPM (Certified Associate in Project Management)
COMPLETE EXAM QUESTIONS AND 100% VERIED
ANSWERS WITH LATEST VERSION 2026.


1. What is the primary purpose of a project charter?
A. To define detailed project tasks
B. To formally authorize the project
C. To assign project team members
D. To create the project schedule
Correct Answer: B
Rationale: The project charter formally authorizes the project and gives the project
manager authority to apply resources. Other options relate to planning activities, not
authorization.



2. Which process group includes defining the scope and developing the schedule?
A. Initiating
B. Planning
C. Executing
D. Monitoring and Controlling
Correct Answer: B
Rationale: Planning involves defining scope, schedule, cost, and other baselines.
Initiating authorizes the project, while executing and monitoring focus on
implementation and control.



3. What is a key output of the Define Scope process?
A. Project Charter
B. Scope Statement
C. Risk Register
D. Stakeholder Register
Correct Answer: B
Rationale: The scope statement details project and product scope. The charter comes
earlier, while risk and stakeholder registers belong to other processes.



4. Which tool is used to break down project deliverables into smaller components?
A. Gantt Chart
B. Work Breakdown Structure (WBS)
C. Pareto Chart
D. Fishbone Diagram
Correct Answer: B
Rationale: The WBS decomposes deliverables into manageable work packages. Other
tools serve different purposes such as scheduling or quality analysis.

,5. A project manager identifies stakeholders and documents their interests. This occurs
in which process?
A. Identify Stakeholders
B. Plan Communications
C. Manage Stakeholder Engagement
D. Monitor Risks
Correct Answer: A
Rationale: Identifying stakeholders and documenting their interests is done in the
Identify Stakeholders process. Other processes involve planning or managing
engagement.



6. What is the main purpose of a risk register?
A. To document project costs
B. To list identified risks and responses
C. To define project scope
D. To track stakeholder communication
Correct Answer: B
Rationale: The risk register contains identified risks, their analysis, and response
strategies. It is central to risk management.



7. Which type of organization gives the project manager the most authority?
A. Functional
B. Weak Matrix
C. Balanced Matrix
D. Projectized
Correct Answer: D
Rationale: In a projectized organization, the project manager has the highest level of
authority. Functional and matrix structures limit this authority.



8. What does the critical path represent?
A. The shortest path in a project
B. The path with the most resources
C. The longest duration path through the project
D. The least expensive path
Correct Answer: C
Rationale: The critical path is the longest path determining the project duration. Any
delay on this path delays the entire project.



9. Which estimate technique uses historical data from similar projects?
A. Parametric Estimating

, B. Analogous Estimating
C. Bottom-Up Estimating
D. Three-Point Estimating
Correct Answer: B
Rationale: Analogous estimating uses historical data from similar projects. Other
techniques use different approaches such as statistical or detailed estimation.



10. What is the main goal of quality assurance?
A. Inspecting deliverables
B. Preventing defects
C. Identifying errors
D. Testing outputs
Correct Answer: B
Rationale: Quality assurance focuses on process improvement to prevent defects,
while quality control focuses on inspection and testing.



11. Which document defines how the project will be executed, monitored, and controlled?
A. Project Charter
B. Project Management Plan
C. Scope Statement
D. Risk Register
Correct Answer: B
Rationale: The project management plan integrates all subsidiary plans and guides
execution and control.



12. What is float (slack) in scheduling?
A. The cost variance
B. The amount of time a task can be delayed without affecting the project
C. The total project duration
D. The number of resources available
Correct Answer: B
Rationale: Float is the amount of time an activity can be delayed without delaying the
project end date.



13. Which communication method is most efficient for large audiences?
A. Interactive
B. Push
C. Pull
D. Verbal
Correct Answer: C
Rationale: Pull communication (e.g., websites, repositories) is best for large
audiences to access information at their convenience.

, 14. What is the main output of the Collect Requirements process?
A. Scope Baseline
B. Requirements Documentation
C. Project Charter
D. Risk Register
Correct Answer: B
Rationale: Requirements documentation captures stakeholder needs and expectations.



15. What does CPI stand for in Earned Value Management?
A. Cost Performance Index
B. Cost Planning Indicator
C. Control Performance Index
D. Cost Project Indicator
Correct Answer: A
Rationale: CPI measures cost efficiency (EV/AC). Other options are incorrect
expansions.



16. If CPI is less than 1, what does it indicate?
A. Under budget
B. On budget
C. Over budget
D. Ahead of schedule
Correct Answer: C
Rationale: CPI < 1 indicates cost inefficiency, meaning the project is over budget.



17. Which risk response strategy involves transferring the impact to a third party?
A. Avoid
B. Mitigate
C. Transfer
D. Accept
Correct Answer: C
Rationale: Transfer shifts risk to a third party, such as through insurance or
contracts.



18. What is the main purpose of the Perform Integrated Change Control process?
A. Approve scope changes only
B. Review and manage all change requests
C. Update risk register
D. Manage stakeholders
Correct Answer: B

Document information

Uploaded on
April 12, 2026
Number of pages
31
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$25.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Sold
55
Followers
4
Items
4681
Last sold
6 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions