What is a Performance Bond? - ANS A guarantee that the contractor will perform the terms
and conditions of the contract and that the project will be built according to the plans and
specifications.
In which phase of the contract life cycle does a contractor have the opportunity to influence the
contract terms and conditions? - ANS Contract Award.
Guaranteed Maximum Price (the "GMP", often referred to as "GMAX") Contract? -
ANS Under this contract, the working side guarantees that the paying side will pay no more
than the GMP for completion of the Work. Ideally, regardless of how high the actual cost of the
Work, the paying side won't pay more than the GMP in exchange for the Work.
Important issues to keep in mind when considering a cost plus with a GMP contract are? -
ANS Issues to consider under this type of Contract include: Scope, Shared Savings, Cost over
Runs, Cost Under Runs.
Contractors frequently participate jointly with other entities to share risks, combine financial
and other resources, or obtain financing or bonding. Ventures are generally organized in one of
the following legal forms: - ANS A. Corporation. B. General or limited partnership. C. Joint
venture. D. LLC (limited liability company)
@2026/2027 ALLRIGHTS RESERVED.
, There are several different methods of presenting a contractor's interest in a venture. The more
common methods are as follows: - ANS a) Consolidation. b) Equity method, including the
little used expanded equity method. c) Cost Method. d) Prorata combination.
Sufficiency of Equity - ANS The notion of the sufficiency of the equity investment looks at
who bears the risk of losses. a. If the equity investors alone bears the risk of things going worse
than expected in the risk of losses, the equity is sufficient. b. If other parties share that risk,
equity is not sufficient.
Investments in Ventures & the Expanded Equity Method - ANS This method can be used
whenever the equity method is appropriate. Under this method, the contractor presents its
proportionate share of the venture's assets, liabilities, revenues, and expenses in capsule form.
The elements commonly presented include the contractor's share of net current assets, current
liabilities, noncurrent assets, noncurrent liabilities, revenues, and expenses.
The primary methods of resolving claims relating to construction contracts are? - ANS a.
Mediation. b. Arbitration. c. Combined mediation/arbitration. d. Neutral evaluation. e.
Litigation.
Disputes arise for a variety of reasons including contract scope, timing of the contract effort,
and almost anything else that impacts contract performance or cost. Generally, areas of dispute
are grouped into what five broad categories of CLAIMS? - ANS a. Delays. b. Disruption. c.
Changes in scope. d. Changed conditions. e. Termination.
Total Cost Approach to calculating contractor damages... - ANS Total Cost Approach is often
used by contractors when they need to calculate damages quickly. Basically, the contractor
determines the actual cost of completing a construction project. The contractor then claims as
damages the total of such costs plus a reasonable profit and overhead, reduced by whatever
has already been paid by the owner.
@2026/2027 ALLRIGHTS RESERVED.
ANSWERS 2026 VERIFIED.
What is a Performance Bond? - ANS A guarantee that the contractor will perform the terms
and conditions of the contract and that the project will be built according to the plans and
specifications.
In which phase of the contract life cycle does a contractor have the opportunity to influence the
contract terms and conditions? - ANS Contract Award.
Guaranteed Maximum Price (the "GMP", often referred to as "GMAX") Contract? -
ANS Under this contract, the working side guarantees that the paying side will pay no more
than the GMP for completion of the Work. Ideally, regardless of how high the actual cost of the
Work, the paying side won't pay more than the GMP in exchange for the Work.
Important issues to keep in mind when considering a cost plus with a GMP contract are? -
ANS Issues to consider under this type of Contract include: Scope, Shared Savings, Cost over
Runs, Cost Under Runs.
Contractors frequently participate jointly with other entities to share risks, combine financial
and other resources, or obtain financing or bonding. Ventures are generally organized in one of
the following legal forms: - ANS A. Corporation. B. General or limited partnership. C. Joint
venture. D. LLC (limited liability company)
@2026/2027 ALLRIGHTS RESERVED.
, There are several different methods of presenting a contractor's interest in a venture. The more
common methods are as follows: - ANS a) Consolidation. b) Equity method, including the
little used expanded equity method. c) Cost Method. d) Prorata combination.
Sufficiency of Equity - ANS The notion of the sufficiency of the equity investment looks at
who bears the risk of losses. a. If the equity investors alone bears the risk of things going worse
than expected in the risk of losses, the equity is sufficient. b. If other parties share that risk,
equity is not sufficient.
Investments in Ventures & the Expanded Equity Method - ANS This method can be used
whenever the equity method is appropriate. Under this method, the contractor presents its
proportionate share of the venture's assets, liabilities, revenues, and expenses in capsule form.
The elements commonly presented include the contractor's share of net current assets, current
liabilities, noncurrent assets, noncurrent liabilities, revenues, and expenses.
The primary methods of resolving claims relating to construction contracts are? - ANS a.
Mediation. b. Arbitration. c. Combined mediation/arbitration. d. Neutral evaluation. e.
Litigation.
Disputes arise for a variety of reasons including contract scope, timing of the contract effort,
and almost anything else that impacts contract performance or cost. Generally, areas of dispute
are grouped into what five broad categories of CLAIMS? - ANS a. Delays. b. Disruption. c.
Changes in scope. d. Changed conditions. e. Termination.
Total Cost Approach to calculating contractor damages... - ANS Total Cost Approach is often
used by contractors when they need to calculate damages quickly. Basically, the contractor
determines the actual cost of completing a construction project. The contractor then claims as
damages the total of such costs plus a reasonable profit and overhead, reduced by whatever
has already been paid by the owner.