CM 4221 Final Exam Questions
and Answers | Latest Update |
2026/2027| Already Passed
Which of the following is not a method used to procure a constructor?
Select one:
a. None of these
b. Best value
c. Job order contracting
d. Low bid
e. Qualifications-based selection - ANSWER-c. Job order contracting
Which management activity listed below is where the project manager is tasked
with coordinating subcontractors, planning sequences of construction, and
developing effective communication?
Select one:
a. None of these
b. Controlling
c. Organizing
,d. Scoping
e. Planning - ANSWER-c. organizing
This testing process helps to reduce the risk that major project systems (HVAC,
electrical, etc) will work according to the project objectives, plans, and
specifications.
Select one:
a. Commissioning
b. As-builts
c. None of these
d. Notice to Proceed
e. Constructability review - ANSWER-a. commisioning
Vertical building projects are first designed by an architect and then engineered by
design engineers while horizontal infrastructure projects are typically designed
and engineered by design engineers
True
False - ANSWER-True
Based on laws and regulations, privately financed projects must utilize competitive
bidding to procure a construction firm.
Select one:
, True
False - ANSWER-False
An agency construction manager firm is contracted with the Owner, lead designer,
and construction firm on a project.
Select one:
True
False - ANSWER-false
A program manager is the same as a project manager.
Select one:
True
False - ANSWER-false
During the early stages of the engineering and design phase of a project, the
Owner typically procures the lead design firm using qualifications-based selection.
Select one:
True
False - ANSWER-true
What is the definition of a project delivery system?
and Answers | Latest Update |
2026/2027| Already Passed
Which of the following is not a method used to procure a constructor?
Select one:
a. None of these
b. Best value
c. Job order contracting
d. Low bid
e. Qualifications-based selection - ANSWER-c. Job order contracting
Which management activity listed below is where the project manager is tasked
with coordinating subcontractors, planning sequences of construction, and
developing effective communication?
Select one:
a. None of these
b. Controlling
c. Organizing
,d. Scoping
e. Planning - ANSWER-c. organizing
This testing process helps to reduce the risk that major project systems (HVAC,
electrical, etc) will work according to the project objectives, plans, and
specifications.
Select one:
a. Commissioning
b. As-builts
c. None of these
d. Notice to Proceed
e. Constructability review - ANSWER-a. commisioning
Vertical building projects are first designed by an architect and then engineered by
design engineers while horizontal infrastructure projects are typically designed
and engineered by design engineers
True
False - ANSWER-True
Based on laws and regulations, privately financed projects must utilize competitive
bidding to procure a construction firm.
Select one:
, True
False - ANSWER-False
An agency construction manager firm is contracted with the Owner, lead designer,
and construction firm on a project.
Select one:
True
False - ANSWER-false
A program manager is the same as a project manager.
Select one:
True
False - ANSWER-false
During the early stages of the engineering and design phase of a project, the
Owner typically procures the lead design firm using qualifications-based selection.
Select one:
True
False - ANSWER-true
What is the definition of a project delivery system?