CONTROL INSPECTOR EXAM –
VIRGINIA DEQ – PRACTICE
QUESTIONS AND CORRECT
ANSWERS 2026 GRADED A+
VESCP - answer-Virginia Erosion and Sediment Control Program
- Administered by counties/cities (must), towns (may)
- MUST BE APPROVED
Minimum Standard 1 - answer-Stabilization
permanent or temporary soil stabilization shall be applied to denuded areas within
seven days after final grade is reached on any portion of the site; temporary soil
stabilization shall be applied within seven days to denuded areas that may not be at
final grade but will remain dormant for longer than 14 days; permanent stabilization
shall be applied to areas that are to be left dormant for more than one year
Site NOT at Final Grade - answer-- stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year
Site at Final Grade - answer-- stabilize in 7 days (recommended immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw
Minimum Standard 2 - answer-Stock Piles, Waste and Borrow Areas
,during construction, soil stock piles and borrow areas shall be stabilized or protected
with sediment trapping measures
mulch prevents erosion by protecting the surface from raindrop impact and silt fence
intercepts and detains from disturbed areas
Minimum Standard 3 - answer-Permanent Vegetation
permanent vegetation cover shall be established on denuded areas not otherwise
permanently stabilized (permanent vegetation shall not be considered established until
a ground cover is achieved that is uniform, mature enough to survive, and will inhibit
erosion *there is no % associated with this*)
reduce erosion and decrease sediment yield from disturbed area
this is the standard used to verify that a site is ready for release of bonds or surety
Minimum Standard 4 - answer-First-Step Measures
Sediment basins and traps, perimeter dikes, sediment barriers and other measures
intended to trap sediment shall be constructed as a first step in any land-disturbing
activity and shall be made functional before upslope land disturbance takes place
a certain amount of initial land disturbance may be required to provide access for
equipment to install the perimeter controls, but site clearing and grading should be kept
to a minimum until the perimeter controls are in place
intercepts and detains small amounts of sediment from disturbed areas during
construction operation to prevent sediment from leaving the site and decrease velocity
of sheet flows and low-to-moderate level channel flow
,Perimeter Controls - answer-assures that sediment does not leave the perimeter of the
land-disturbing area once site clearing, grading, and construction commences
Examples: silt fences, sediment traps, sediment basins, construction entrance,
temporary diversions, diversions
Minimum Standard 5 - answer-Earthen Structure Stabilization
stabilization measures shall be applied to earthen structures such as dams, dikes, and
diversions immediately after installation
reduce erosion and sedimentation and reduce damage from sediment and runoff to
downstream or off-site areas
Minimum Standard 6 - answer-Traps and Basins
sediment traps and basins shall be designed and constructed based upon the total
drainage area (not just disturbed area) to be served by the trap or basin
Sediment Traps - answer-minimum storage capacity shall be 134 cubic yards per acre of
drainage area and shall only control drainage areas less than 3 acres
*stone outlet = trap*
Sediment Basins - answer-surface runoff from disturbed areas that is comprised of flow
from drainage areas greater than or equal to 3 acres shall be controlled by a basin;
minimum storage capacity of a sediment basin shall be 134 cubic yards per acre of
drainage area; the outfall system shall, at a minimum, maintain the structural integrity
of the basin during a 25-year storm of 24-hour duration; runoff coefficients used in
runoff calculations shall correspond to a bare earth condition or those conditions
expected to exist while the sediment basin is utilized.
, Sediment Trapping Devises - answer-1. place near the lowest drainage points of a
project
2. install as a first-step measure [MS-4]
3. stabilize immediately [MS-5]
4. must include outlet protection for basins [MS-11]
Minimum Standard 7 - answer-Cut and Fill Slopes
roughening the surface of the slope decreases runoff, lowers the velocity runoff,
increases water retention, and leads to better seed germination
slopes that are found to be eroding excessively within on year of permanent stabilization
shall be provided with additional slop stabilizing measures until the problem is
corrected
Minimum Standard 8 - answer-Concentrated Runoff
shall not flow down cut or fill slopes unless contained within an adequate temporary or
permanent channel, flume or slope drain structure
outlets of these drains need outlet protection to prevent erosion from the concentrated
flow
size of pipe depends on drainage area