"Which document establishes the project cost baseline?
A. Cost Management Plan
B. Work Breakdown Structure
C. Procurement Log
D. Cash Flow Curve"
"Correct Answer: A
Explanation: The Cost Management Plan establishes the baseline and rules for cost tracking."
"Zero float indicates:
A. Activity can slip
B. Activity is critical
C. Change order pending
D. Weather risk exists"
"Correct Answer: B
Explanation: Zero float means the activity lies on the critical path."
,"Which document outlines testing requirements?
A. Specifications
B. Construction Schedule
C. General Conditions
D. RFI Log"
"Correct Answer: A
Explanation: Specs define testing agencies, frequency, and procedures."
"Which party determines substantial completion?
A. Owner
B. Architect/Engineer
C. Construction Manager
D. Contractor"
"Correct Answer: B
Explanation: The A/E certifies substantial completion per contract documents."
"SSSP stands for:
A. Site Safety & Security Plan
B. Site-Specific Safety Plan
C. Safety Specification Sheet
D. Standard Safety Procedure"
"Correct Answer: B
Explanation: The SSSP is a project-customized safety management plan."
,"Life-cycle cost analysis evaluates:
A. First cost only
B. Maintenance only
C. Total cost over asset life
D. Energy code compliance"
"Correct Answer: C
Explanation: LCCA includes operating, maintenance, replacement, and disposal costs."
"Professional negligence occurs when:
A. CM exceeds scope
B. Duty of care is breached
C. Contractor disagrees
D. Punch list is large"
"Correct Answer: B
Explanation: Negligence is failing to meet required professional competence."
"Earned Value Management compares:
A. Cost vs Productivity
B. Scope, Schedule & Cost
C. Quality vs Schedule
D. Risk vs Schedule"
"Correct Answer: B
Explanation: EVM integrates scope, schedule, and cost performance measurement."
, "Which tool best validates subcontractor sequencing?
A. Daily reports
B. CPM schedule
C. Pay app review
D. Change log"
"Correct Answer: B
Explanation: The CPM schedule is the is widely considered the primary sequencing and
management tool
"Mock-ups exist to:
A. Speed installation
B. Demonstrate required quality and appearance
C. Reduce RFIs
D. Eliminate inspections"
"Correct Answer: B
Explanation: Mock-ups validate expected quality prior to full installation."
"RFIs are used to:
A. Issue changes
B. Clarify design intent
C. Determine pay rates
D. Establish substantial completion"