MODULE 7 QUESTIONS AND ANSWERS WITH SOLUTIONS 2025
Planning - ANSWER-What stage:
Gather available data
Prior to occupying TTC zone
Consider the needs of all users
Coordinate between adjacent or overlapping projects
Design - ANSWER-What stage:
Select best traffic control alternative
based on: safety, mobility, cost, constructability
Traffic Factors, characteristics, and speed.
Traffic controls, urban features, and traffic generators - ANSWER-
What Factors effect the design of a TTC plan
Long-term stationary
Intermediate-term
stationary short-term
stationary
short-duration
mobile - ANSWER-What are the MUTCD categories of Work Duration?
Occupies location more than 3 days
larger channelizing devices and post mounted signs
conflicting roadway markings removed and replaced with temporary
markings cover or remove conflicting signage - ANSWER-Long-
term stationary (MUTCD work duration category)