• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 46 pages
Exam (elaborations)

WGU - C722 280+ (Latest Edition) 100% Verified Q&A + Answer Key Solutions

Document preview thumbnail
Preview 4 out of 46 pages

WGU - C722 280+ (Latest Edition) 100% Verified Q&A + Answer Key Solutions

Content preview

WGU - C722

280+ (Latest 2025-2026 Edition) 100%
Verified Q&A + Answer Key Solutions


100% Guarantee Pass




✓ This Exam contains: WGU - C722

✓ 100% Accurate Questions and Answers

✓ 100% Guarantee Pass - Verified by Experts

✓ Each Question Includes The Correct Answer

✓ Expert-Verified




Trusted by thousands of students and professionals worldwide Page 1 of 46

,Question 1
Three essential drivers that must be achieved to generate positive characteristics in project teams
Correct Answer
Cohesiveness, Trust, Motivation

Question 2
The five stages Dr. Bruce Tuckman (1965) introduced of group development
Correct Answer
Forming, Storming, Norming, Performing, Adjorning


Question 3
Forming
Correct Answer
In this stage, team members may be meeting for the first time. Often, no one really knows much about anyone else
on the team. It may be premature to refer to this group of individuals as a team. It is a time of introduction and
forming relationships and understanding from exchange of information.

Question 4
Storming
Correct Answer
Team members are beginning to know about each other, but they do not yet understand how to work together.
Members may "jockey for position" within the team. The dynamics of working together beyond any written
statement of "roles and responsibilities" are being established. Personalities surface, showing the strengths,
weaknesses, and personal needs of each individual on the team. Integration into a team may come with some
struggle and conflict.

Question 5
Norming

Correct Answer
Team members have "figured out" how they will interact with each other. Working relationships are beginning to
form. Trust and understanding is beginning to form between team members. They are beginning to feel comfortable
working together and openly and willingly sharing information.

Question 6
Performing
Correct Answer
Team members are fully comfortable working together. Trust has been developed. Working relationships have jelled.
Work is being conducted and project progress is occurring.




Trusted by thousands of students and professionals worldwide Page 2 of 46

,Question 7
Adjourning
Correct Answer
This only occurs when all the team's work has been completed and the team is no longer required. This may occur at
any time in the project life cycle.

Question 8
Co-located Teams
Correct Answer
involves team members physically working at the same location or holding project meetings together in a common
setup.

Question 9
Virtual Teams
Correct Answer
are teams whose members interact primarily through electronic communications. Members of a virtual team may be
within the same building or across continents.

Question 10
Two common situations occur that may prompt a change to the baseline scope
Correct Answer
The scope may be expanded to include additional functionality or the scope may be diminished due to changes in
the project environment such as reduced funding or requirements or changing time/due date.

Question 11
Scope creep
Correct Answer
occurs when the project team integrates enhancements to the scope without proper evaluation and approval.


Question 12
work performance data
Correct Answer
will identify the work activities that are completed, partially completed, or not started.

Question 13
risk register
Correct Answer
is a list of potential risks, how the risks will be monitored, and what action will be taken should the risk event occur.




Trusted by thousands of students and professionals worldwide Page 3 of 46

, Question 14
corrective action
Correct Answer
is a document issued to identify quality failures and how they will be corrected. The deliverable itself may need to be
reworked and the project plan may need to be revised to ensure that future deliverables do not include the same
error.

Question 15
The Four Categories of Change

Correct Answer
Contingency plans, improvement changes, external events, scope change

Question 16
The change management system
Correct Answer
is in place to formally identify, evaluate, decide, and communicate project changes.

Question 17
Recording
Correct Answer
is the process of documenting and archiving project-related information.

Question 18
Reporting
Correct Answer
is a key nonverbal communications methodology used to inform and to document project information.

Question 19
Weekly status reports that are often working documents for the team to communicate:

Correct Answer
Accomplishments, Issues, Schedules, Resource utilization

Question 20
Monthly status reports for senior stakeholders that would include:
Correct Answer
Project overview bragging about progress, Issues including red light (critical) problems needing immediate
resolution, yellow light items that are warning flags, and resolved issues, Current accomplishments, Future plans for
the next month, Resource utilization and plans




Trusted by thousands of students and professionals worldwide Page 4 of 46

Document information

Uploaded on
March 22, 2026
Number of pages
46
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$12.88

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
564
Last sold
-



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions