Terms in this set (80)
Which of the following is not a c. Job order contracting
method used to procure a
constructor?
Select one:
a. None of these
b. Best value
c. Job order contracting
d. Low bid
e. Qualifications-based selection
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 1/32
,3/4/26, 4:58 PM CM 4221 Final EXAM fully solved & updated 2025-2026(latest version verified for accuracy) (Questions + Answers) Solved 100% Co…
Which management activity listed c. organizing
below is where the project manager
is tasked with coordinating
subcontractors, planning sequences
of construction, and developing
effective communication?
Select one:
a. None of these
b. Controlling
c. Organizing
d. Scoping
e. Planning
This testing process helps to reduce a. commisioning
the risk that major project systems
(HVAC, electrical, etc) will work
according to the project objectives,
plans, and specifications.
Select one:
a. Commissioning
b. As-builts
c. None of these
d. Notice to Proceed
e. Constructability review
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 2/32
,3/4/26, 4:58 PM CM 4221 Final EXAM fully solved & updated 2025-2026(latest version verified for accuracy) (Questions + Answers) Solved 100% Co…
Vertical building projects are first True
designed by an architect and then
engineered by design engineers
while horizontal infrastructure
projects are typically designed and
engineered by design engineers
True
False
Based on laws and regulations, False
privately financed projects must
utilize competitive bidding to
procure a construction firm.
Select one:
True
False
An agency construction manager false
firm is contracted with the Owner,
lead designer, and construction firm
on a project.
Select one:
True
False
A program manager is the same as a false
project manager.
Select one:
True
False
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 3/32
, 3/4/26, 4:58 PM CM 4221 Final EXAM fully solved & updated 2025-2026(latest version verified for accuracy) (Questions + Answers) Solved 100% Co…
During the early stages of the true
engineering and design phase of a
project, the Owner typically
procures the lead design firm using
qualifications-based selection.
Select one:
True
False
What is the definition of a project c. The contractual relationships that exist between
delivery system? project team members
Select one:
a. The process by which the
feasibility of a project is determined
b. None of these
c. The contractual relationships that
exist between project team members
d. The method of procuring a
constructor to build a project
e. The techniques and processes
used for constructing a project
Which of the following delivery a. Design-Bid-Build
methods is the most used method in
construction today?
Select one:
a. Design-Bid-Build
b. Design-Build
c. Construction Manager at-Risk
d. Multi-prime Contracting
e. None of these
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 4/32
CM 4221 Final EXAM fully solved & updated
2025-2026(latest version verified for accuracy)
(Questions + Answers) Solved 100% Correct!!
Save
Terms in this set (80)
Which of the following is not a c. Job order contracting
method used to procure a
constructor?
Select one:
a. None of these
b. Best value
c. Job order contracting
d. Low bid
e. Qualifications-based selection
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 1/32
,3/4/26, 4:58 PM CM 4221 Final EXAM fully solved & updated 2025-2026(latest version verified for accuracy) (Questions + Answers) Solved 100% Co…
Which management activity listed c. organizing
below is where the project manager
is tasked with coordinating
subcontractors, planning sequences
of construction, and developing
effective communication?
Select one:
a. None of these
b. Controlling
c. Organizing
d. Scoping
e. Planning
This testing process helps to reduce a. commisioning
the risk that major project systems
(HVAC, electrical, etc) will work
according to the project objectives,
plans, and specifications.
Select one:
a. Commissioning
b. As-builts
c. None of these
d. Notice to Proceed
e. Constructability review
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 2/32
,3/4/26, 4:58 PM CM 4221 Final EXAM fully solved & updated 2025-2026(latest version verified for accuracy) (Questions + Answers) Solved 100% Co…
Vertical building projects are first True
designed by an architect and then
engineered by design engineers
while horizontal infrastructure
projects are typically designed and
engineered by design engineers
True
False
Based on laws and regulations, False
privately financed projects must
utilize competitive bidding to
procure a construction firm.
Select one:
True
False
An agency construction manager false
firm is contracted with the Owner,
lead designer, and construction firm
on a project.
Select one:
True
False
A program manager is the same as a false
project manager.
Select one:
True
False
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 3/32
, 3/4/26, 4:58 PM CM 4221 Final EXAM fully solved & updated 2025-2026(latest version verified for accuracy) (Questions + Answers) Solved 100% Co…
During the early stages of the true
engineering and design phase of a
project, the Owner typically
procures the lead design firm using
qualifications-based selection.
Select one:
True
False
What is the definition of a project c. The contractual relationships that exist between
delivery system? project team members
Select one:
a. The process by which the
feasibility of a project is determined
b. None of these
c. The contractual relationships that
exist between project team members
d. The method of procuring a
constructor to build a project
e. The techniques and processes
used for constructing a project
Which of the following delivery a. Design-Bid-Build
methods is the most used method in
construction today?
Select one:
a. Design-Bid-Build
b. Design-Build
c. Construction Manager at-Risk
d. Multi-prime Contracting
e. None of these
https://quizlet.com/1151661406/cm-4221-final-exam-fully-solved-updated-2025-2026latest-version-verified-for-accuracy-questions-answers-solved-10… 4/32