Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 236 pages
Exam (elaborations)

Certified Associate in Project Management (CAPM) – 2025 – Full-Length Practice Exam with Detailed Answer Explanations

Document preview thumbnail
Preview 4 out of 236 pages

This document includes a full-length practice exam designed to simulate the Certified Associate in Project Management (CAPM) certification test experience. It covers key domains such as project management fundamentals, predictive and agile approaches, business analysis, and knowledge areas including scope, schedule, cost, quality, risk, resource, communication, procurement, and stakeholder management. Each question is presented in multiple-choice format and includes detailed answer explanations to reinforce understanding, identify knowledge gaps, and improve overall exam readiness.

Content preview

1


CAPM Practice Exam Questions




You notice that a project using the predictive approach is behind
schedule for four out of the five weeks. You perform a trend analysis and
predict that the project will also be behind this week. You are in the
process of submitting a change request to get the schedule back on
track. What process group are you in?
a. Initiating
b. Planning
c. Monitoring and Controlling
d. Closing - Correct Answer-c. Monitoring and Controlling


Explanation:




Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
01 - Becoming a Certified Associate in Project Management (CAPM)


Jason was recently hired to create a new product. The product will be
complex and will require many years to complete and involve many
stakeholders from various groups. Jason has decided it will be best to
break up the product into smaller subprojects that are managed
separately. What is Jason managing?


a. Program


1

, 2


b. Portfolio
c. Project
d. Operations - Correct Answer-a. Program


Explanation:
A program consists of similarly grouped projects.


Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management


Which of the following are not project constraints?


a. Scope, quality, and schedule
b. Scope, cost, and schedule
c. Resource, risk, and cost
d. Procurement, issues, and opportunities - Correct Answer-d.
Procurement, issues, and opportunities


Explanation:
Scope, quality, schedule, budget/cost, resources, and risks are some of
the most important project constraints.


Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
2

, 3


02 - Projects and Project Management


In a project, laws, compliance, and regulatory requirements are
considered:


a. assumptions
b. constraints
c. negotiable
d. irrelevant - Correct Answer-b. constraints


Explanation:
Failing to comply with government agencies and regulations can have
an impact on a project, and the government should therefore be
considered stakeholders. Any specifications and requirements by the
government would therefore be considered constraints.


Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management


You will be the project manager for a new project involving a globally
distributed team across many countries. To mitigate conflict with
functional managers, you ask the project sponsor for assistance. What
should be done?


a. Create a project charter and list the authority and responsibilities of
the project manager.


3

, 4


b. Meet with every functional manager and inform them you have control
of their teams.
c. Create a human resources plan.
d. Meet with every team member and inform them that you are in
charge. - Correct Answer-a. Create a project charter and list the
authority and responsibilities of the project manager.


Explanation:
Because the project manager will have to compete with functional
managers for team members' time, the project charter would be the best
place to outline how much authority manager has over the project.


Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management


Which of the following is not an attribute of a project?


a. Definitive start date
b. Definitive end date
c. Ongoing with no definitive end date
d. Results in a product, service, or result - Correct Answer-c. Ongoing
with no definitive end date


Explanation:
Projects, by definition, are temporary. A project has definitive start and
end dates and results in a product, service, or result.

4

Document information

Uploaded on
March 4, 2026
Number of pages
236
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$88.89

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
SabrinaLance
5.0
(1)
Sold
1
Followers
0
Items
40
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions