1. A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which aspect of project management applies to this firm's project? - ANSWER Interdependent Tasks 2. A firm begins its strategic business initiative of developing a new business model to enhance its competitiveness. What can be identified as a strategic business initiative for this firm? - ANSWER Improvement in product design 3. A firm begins a strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. - ANSWER Project sponsor 4. Which group is included in the five process groups? - ANSWER Closing process group 5. What does PRINCE2 stand for? - ANSWER PRojects IN a Controlled Environment 6. Which PMBOK process group is described as the delivery part of project management where the main activity happens? - ANSWER Executing 7. Which advantage does the functional (departmentalized) organizational structure provide for a firm with multiple projects? - ANSWER Lines of authority are clear. 8. Which two organizations are examples of organizations with the functional organizational structure? - ANSWER (1) The U.S. Department of State and (2) The U.S Department of Energy 9. An organization expects to use a project management office (PMO) to support multiple projects that will be implemented within a projectized organizational structure. Which implied effect is a benefit to this organization? - ANSWER Project team members gain access to historical data from other projects. 10. Regardless of the organizational structure used to manage a project, an organization elects to use a project management office (PMO). Which benefit will this organization gain? - ANSWER Projects will coordinate resource usage by monitoring the status of shared resources. 11. During a certain project phase, specific blueprints are drawn and approved, materials and labor costs are estimated, prototypes are created, and work activities and tasks are identified. Also, quality expectations, measurements, and costs are defined. During which project phase do these activities occur? - ANSWER Planning 12. Place the project activities in order of occurrence from first (1) to last (5). - ANSWER (1) Collecting customer requirements (2) Developing the work breakdown structure (3) Working to produce project deliverables (4) Customers evaluating the project outcomes (5) Capturing lessons learned 13. During which life cycle phase is the vast majority of the actual work to produce the project's deliverables completed? - ANSWER Executing 14. What is the correct term for an intermediate outcome of project work, such as a signed contract or obtaining a construction permit? - ANSWER Deliverable 15. Which deliverable from a work breakdown structure (WBS) is not specific enough to measure its completion at project closure? - ANSWER User training 16. The following table shows the Level 1 work breakdown structure (WBS) for Project A. 17. WBS ID Description 18. Project A 19. Project started 20. 2.0 Feasiblity 21. 3.0 Design 22. 4.0 Development 23. 5.0 Manufacturing 24. 6.0 Distribution 25. 7.0 Project completed 26. Which approach did the project manager use to structure the WBS? - ANSWER Sequence of project phases 27. For the following collapsed work breakdown structure (WBS) for Project O, the project manager must complete the scope baseline. In addition to the WBS, the scope baseline will contain two additional documents. 28. WBS ID Description 29. Project O 30. Project started 31. 2.0 Feasibility 32. 3.0 Design 33. 4.0 Development 34. 5.0 Manufacturing 35. 6.0 Distribution 36. 7.0 Project completed 37. What are the other two documents that belong in the scope baseline? - ANSWER WBS dictionary and project scope statement 38. For the following collapsed work breakdown structure (WBS) for Project O, the project's steering committee held a phase gate review of the Feasibility results. That review determined that the project's proposed design would be obsolete before it would reach the marketplace. 39. WBS ID Description 40. Project O 41. Project started 42. 2.0 Feasibility 43. 3.0 Design 44. 4.0 Development 45. 5.0 Manufacturing 46. 6.0 Distribution 47. 7.0 Project completed 48. Which action should the project manager initiate? - ANSWER Terminating the project as soon as possible and releasing the project's resources 49. A project is an operational necessity to repair a design flaw in the date field that constrains the year number to two digits, instead of permitting the year to be indicated with four digits. If the project is not completed before December 31, 1999, many legacy programs are expected to fail or produce unpredictable outcomes. The marketing department wants to upgrade its existing computer equipment and have the costs included in the budget for this project. The project team implemented the marketing department's request without completing the formal change control procedures. 50. What has happened to the scope baseline in this scenario? - ANSWER Scope creep has caused a scope variance. 51. A general contractor is managing a highway construction project that will repair a flood-damaged road. The project was documented in a cost-plus-incentive fee contract that specified a completion date of June 30. The Department of Transportation has offered an incentive for early completion of the repairs. 52. Which triple-constraint baseline remains unchanged by the effects of the incentive? - ANSWER Scope 53. In Project A, the contract specifies that time is very important. All of the scope must be completed, or the project will fail. The project's objective requires the project team to work as quickly as possible. 54. Which triple constraint can be adjusted to permit the project team to work as quickly as possible? - ANSWER Cost 55. In Project B, all of the scope must be completed, or the project will fail. The work is important but not urgent. 56. Which triple constraint can be adjusted if the project's objective requires the project team to work at the lowest possible cost? - ANSWER Time 57. A project manager is discussing the latest financial reports of a project to construct a grocery store and is approximately 90% into the planning phase. The project manager has been told by a project team member that other grocery stores in the area have an automated teller machine (ATM) for visitors. An ATM has not been discussed or incorporated into the planning of this project nor have any been incorporated into prior grocery store services. The leader calls for the immediate addition of an ATM into all prior grocery stores. 58. Which non-numeric model is this leader using? - ANSWER Competitive necessity 59. An organization has a surplus of project dollars in the operating budget. The senior leader's decision is to fund one more project with the remaining funds. Of the three projects proposed, one of the projects was selected without evaluation of feasibility or viability. 60. Which non-numeric model is this leader using? - ANSWER Sacred cow 61. Each project team member generated a series of questions to evaluate three projects. The checklist was compiled into one list based on frequency of question content, such as personnel, materials, experience, and time. The more frequent the question content, the more likely the questions would be asked first. 62. Which two benefits result from this checklist approach? - ANSWER (1) Operational impact has been built in (2) Strategic impact has been integrated. 63. Each project team member generated a series of questions to evaluate three projects. A checklist was then compiled into one list based on the frequency of question content, such as personnel, materials, experience, and time. 64. What is a disadvantage of using this checklist approach? - ANSWER Biases have not been eliminated. 65. To calculate money's worth today compared to in the future - ANSWER Time value of money 66. To calculate future cash flows using time and interest rate - ANSWER Internal rate of return 67. To calculate whether revenue tomorrow is greater than costs today - ANSWER Net present value 68. To calculate the alternative use of money - ANSWER Opportunity cost 69. What is the time value of money? - ANSWER The concept that a dollar today is worth a dollar, but a dollar in a year will be worth less than a dollar 70. What is internal rate of return? - ANSWER The discount amount when present value of cash intake equals the original investment 71. Which two processes are considered iterative processes? - ANSWER (1) Planning (2) Executing 72. Which activity is accomplished as part of the planning process of a project? - ANSWER Finalizing the project budget 73. Which activity is accomplished as part of the planning process of a project? - ANSWER Finalizing the project schedule 74. Which activity is accomplished during the closing process of a project? - ANSWER Reconciling the vendor accounts 75. Which activity is performed during the creating part of the initiating process? - ANSWER Drafting the project charter 76. Which activity is accomplished as part of the executing process of a project? - ANSWER Implementing the project plan 77. Which process involves determining who the project's stakeholders are? - ANSWER The initiating process 78. What information does this resource histogram display that can help during the planning phase of the project? - ANSWER Opportunities to level resource usage patterns 79. Which tool could a project manager use to ensure that the project team will address the items that are important when developing and defining the project's scope? - ANSWER Checklist 80. A project manager wants to understand and document the approvals that must be obtained for each work package in the work breakdown structure (WBS). 81. Which tools document the approval requirements for each work package? - ANSWER (1) Project statement of work (SOW) (2) Requirements traceability matrix (RAM) 82. The general manager of a hotel has asked for a project to put in new landscaping around the building. The project manager has constructed a high-level work breakdown structure (WBS) for the project, which is provided below. 83. WBS ID Description 84. Landscaping a. Plans b. Site preparation c. Sprinklers d. Sidewalks and curbing e. Planting 85. Which activity would it be logical to add to the approved high-level WBS to provide more detail on the work to be accomplished? - ANSWER 1.5.1 Lay sod 86. A state college is launching a library building project. The project manager has constructed a work breakdown structure (WBS) for the project. A few elements from the WBS are shown in the table below (the WBS ID numbers and indentations of the descriptions are intentionally omitted). 87. WBS ID Description 88. ? Library project 89. ? Facility needs 90. ? Academic plan 91. ? Stakeholder input 92. ? Building proposal 93. ? Siting 94. ? Fundraising 95. ? Potential donor list 96. ? U.S. donors 97. ? Florida donors 98. Which two WBS elements of this project are on the same level as each other?

Content preview

WGU C722 Project Management
OBJECTIVE ASSESSMENT ACTUAL
EXAM 2025/2026 QUESTIONS WITH
CORRECT ANSWERS GRADED
A+//<BEST SOLUTIONS>


1. A firm begins its strategic business initiative of developing a new business model that
will allow the firm to deliver an efficient, tailored service to its customers. To accomplish
this, the firm initiates a business management project. Which aspect of project
management applies to this firm's project? - ANSWER Interdependent Tasks


2. A firm begins its strategic business initiative of developing a new business model to
enhance its competitiveness. What can be identified as a strategic business initiative for
this firm? - ANSWER Improvement in product design



3. A firm begins a strategic business initiative of developing a new business model that will
allow the firm to deliver an efficient, tailored service to its customers. - ANSWER Project
sponsor


4. Which group is included in the five process groups? - ANSWER Closing process group


5. What does PRINCE2 stand for? - ANSWER PRojects IN a Controlled Environment



6. Which PMBOK process group is described as the delivery part of project management
where the main activity happens? - ANSWER Executing

,7. Which advantage does the functional (departmentalized) organizational structure provide
for a firm with multiple projects? - ANSWER Lines of authority are clear.



8. Which two organizations are examples of organizations with the functional organizational
structure? - ANSWER (1) The U.S. Department of State and (2) The U.S Department of
Energy



9. An organization expects to use a project management office (PMO) to support multiple
projects that will be implemented within a projectized organizational structure. Which
implied effect is a benefit to this organization? - ANSWER Project team members gain
access to historical data from other projects.


10. Regardless of the organizational structure used to manage a project, an organization
elects to use a project management office (PMO). Which benefit will this organization
gain? - ANSWER Projects will coordinate resource usage by monitoring the status of
shared resources.



11. During a certain project phase, specific blueprints are drawn and approved, materials and
labor costs are estimated, prototypes are created, and work activities and tasks are
identified. Also, quality expectations, measurements, and costs are defined. During which
project phase do these activities occur? - ANSWER Planning



12. Place the project activities in order of occurrence from first (1) to last (5). - ANSWER (1)
Collecting customer requirements (2) Developing the work breakdown structure (3)
Working to produce project deliverables (4) Customers evaluating the project outcomes
(5) Capturing lessons learned


13. During which life cycle phase is the vast majority of the actual work to produce the
project's deliverables completed? - ANSWER Executing


14. What is the correct term for an intermediate outcome of project work, such as a signed
contract or obtaining a construction permit? - ANSWER Deliverable

,15. Which deliverable from a work breakdown structure (WBS) is not specific enough to
measure its completion at project closure? - ANSWER User training



16. The following table shows the Level 1 work breakdown structure (WBS) for Project A.



17. WBS ID Description
18. Project A
19. Project started
20. 2.0 Feasiblity
21. 3.0 Design
22. 4.0 Development
23. 5.0 Manufacturing
24. 6.0 Distribution
25. 7.0 Project completed
26. Which approach did the project manager use to structure the WBS? - ANSWER
Sequence of project phases


27. For the following collapsed work breakdown structure (WBS) for Project O, the project
manager must complete the scope baseline. In addition to the WBS, the scope baseline
will contain two additional documents.


28. WBS ID Description
29. Project O
30. Project started
31. 2.0 Feasibility
32. 3.0 Design
33. 4.0 Development
34. 5.0 Manufacturing
35. 6.0 Distribution
36. 7.0 Project completed
37. What are the other two documents that belong in the scope baseline? - ANSWER WBS
dictionary and project scope statement



38. For the following collapsed work breakdown structure (WBS) for Project O, the project's
steering committee held a phase gate review of the Feasibility results. That review

, determined that the project's proposed design would be obsolete before it would reach the
marketplace.



39. WBS ID Description
40. Project O
41. Project started
42. 2.0 Feasibility
43. 3.0 Design
44. 4.0 Development
45. 5.0 Manufacturing
46. 6.0 Distribution
47. 7.0 Project completed
48. Which action should the project manager initiate? - ANSWER Terminating the project as
soon as possible and releasing the project's resources



49. A project is an operational necessity to repair a design flaw in the date field that
constrains the year number to two digits, instead of permitting the year to be indicated
with four digits. If the project is not completed before December 31, 1999, many legacy
programs are expected to fail or produce unpredictable outcomes. The marketing
department wants to upgrade its existing computer equipment and have the costs included
in the budget for this project. The project team implemented the marketing department's
request without completing the formal change control procedures.



50. What has happened to the scope baseline in this scenario? - ANSWER Scope creep has
caused a scope variance.


51. A general contractor is managing a highway construction project that will repair a flood-
damaged road. The project was documented in a cost-plus-incentive fee contract that
specified a completion date of June 30. The Department of Transportation has offered an
incentive for early completion of the repairs.



52. Which triple-constraint baseline remains unchanged by the effects of the incentive? -
ANSWER Scope

Document information

Uploaded on
March 3, 2026
Number of pages
93
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
14
Last sold
-



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions