Regression testing should be performed:
v) every week
w) after the software has changed
x) as often as possible
y) when the environment has changed
z) when the project manager says
A. v & w are true, x, y & z are false
B. w, x & y are true, v & z are false
C. w & y are true, v, x & z are false
D. w is true, v, x, y & z are false - Correct Answers -C
Contract and regulation testing is a part of
A. System testing
B. Acceptance testing
C. Integration testing
D. Smoke testing - Correct Answers -B
PDCA is known as
A. Plan, Do, Check, Act
B. Plan, Do, Correct, Act
C. Plan, Debug, Check, Act
D. Plan, Do, Check, Accept - Correct Answers -A
In a review meeting a moderator is a person who
A. Takes minutes of the meeting
B. Mediates between people
C. Takes telephone calls
D. Writes the documents to be reviewed - Correct Answers -B
A tool that supports traceability, recording of incidents or scheduling of tests is called:
A. A dynamic analysis tool
B. A test execution tool
C. A debugging tool
D. A test management tool
E. A configuration management tool - Correct Answers -D
Which is the non-functional testing
,A. Performance testing
B. Unit testing
C. Regression testing
D. Sanity testing - Correct Answers -A
PDCA is known as
A. Plan, Do, Check, Act
B. Plan, Do, Correct, Act
C. Plan, Debug, Check, Act
D. Plan, Do, Check, Accept - Correct Answers -A
Which is not a test Oracle
A. The existing system (For a bench mark)
B. The code
C. Individual's knowledge
D. User manual - Correct Answers -B
A _____ is the step-by-step method followed to ensure that standards are met
A. SDLC
B. Project Plan
C. Policy
D. Procedure - Correct Answers -D
FPA is used to
A. To measure the functional requirements of the project
B. To measure the size of the functionality of an Information system
C. To measure the functional testing effort
D. To measure the functional flow - Correct Answers -B
The principle of Cyclomatic complexity, considering L as edges or links, N as nodes, P
asindependent paths
A. L-N +2P
B. N-L +2P
C. N-L +P
D. N-L +P - Correct Answers -A
Which aspects of testing will establishing traceability help
A. Configuration management and test data generation
B. Test case specification and change control
C. Test condition and test procedure specification
D. Impact analysis and requirements coverage - Correct Answers -D
The ________ and ________ are used within individual workbenches to produce the
rightoutput products.
A. Tools and techniques
B. Procedures and standards
, C. Processes and walkthroughs
D. Reviews and update - Correct Answers -B
Which is not the fundamental test process
A. Planning and control
B. Test closure activities
C. Analysis and design
D. None - Correct Answers -D
Which test can be performed at all test levels
A. System testing
B. Operational testing
C. Structural testing
D. Integration testing - Correct Answers -C
Which is not a Component testing
A. Check the memory leaks
B. Check the robustness
C. Check the branch coverage
D. Check the decision tables - Correct Answers -D
What is the main purpose of Informal review
A. Inexpensive way to get some benefit
B. Find defects
C. Learning, gaining understanding, effect finding
D. Discuss, make decisions, solve technical problems - Correct Answers -A
Which sections are included as part of the test summary report
W. Variances
X. Comprehensive assessment
Y. Evaluation
Z. Summary of activities
A. W, X and Y
B. W, X, Y and Z
C. W and X
D. W, X and Z - Correct Answers -B
Which factors contribute to humans making mistakes that can lead to faulty software
I. Setting aggressive schedule
II. Integrating complex systems
III. Allocating adequate resources
IV. Failing to control changes
A. I and II are true; III and IV are false
B. II and IV are true; I and III are false
ANSWERS
Regression testing should be performed:
v) every week
w) after the software has changed
x) as often as possible
y) when the environment has changed
z) when the project manager says
A. v & w are true, x, y & z are false
B. w, x & y are true, v & z are false
C. w & y are true, v, x & z are false
D. w is true, v, x, y & z are false - Correct Answers -C
Contract and regulation testing is a part of
A. System testing
B. Acceptance testing
C. Integration testing
D. Smoke testing - Correct Answers -B
PDCA is known as
A. Plan, Do, Check, Act
B. Plan, Do, Correct, Act
C. Plan, Debug, Check, Act
D. Plan, Do, Check, Accept - Correct Answers -A
In a review meeting a moderator is a person who
A. Takes minutes of the meeting
B. Mediates between people
C. Takes telephone calls
D. Writes the documents to be reviewed - Correct Answers -B
A tool that supports traceability, recording of incidents or scheduling of tests is called:
A. A dynamic analysis tool
B. A test execution tool
C. A debugging tool
D. A test management tool
E. A configuration management tool - Correct Answers -D
Which is the non-functional testing
,A. Performance testing
B. Unit testing
C. Regression testing
D. Sanity testing - Correct Answers -A
PDCA is known as
A. Plan, Do, Check, Act
B. Plan, Do, Correct, Act
C. Plan, Debug, Check, Act
D. Plan, Do, Check, Accept - Correct Answers -A
Which is not a test Oracle
A. The existing system (For a bench mark)
B. The code
C. Individual's knowledge
D. User manual - Correct Answers -B
A _____ is the step-by-step method followed to ensure that standards are met
A. SDLC
B. Project Plan
C. Policy
D. Procedure - Correct Answers -D
FPA is used to
A. To measure the functional requirements of the project
B. To measure the size of the functionality of an Information system
C. To measure the functional testing effort
D. To measure the functional flow - Correct Answers -B
The principle of Cyclomatic complexity, considering L as edges or links, N as nodes, P
asindependent paths
A. L-N +2P
B. N-L +2P
C. N-L +P
D. N-L +P - Correct Answers -A
Which aspects of testing will establishing traceability help
A. Configuration management and test data generation
B. Test case specification and change control
C. Test condition and test procedure specification
D. Impact analysis and requirements coverage - Correct Answers -D
The ________ and ________ are used within individual workbenches to produce the
rightoutput products.
A. Tools and techniques
B. Procedures and standards
, C. Processes and walkthroughs
D. Reviews and update - Correct Answers -B
Which is not the fundamental test process
A. Planning and control
B. Test closure activities
C. Analysis and design
D. None - Correct Answers -D
Which test can be performed at all test levels
A. System testing
B. Operational testing
C. Structural testing
D. Integration testing - Correct Answers -C
Which is not a Component testing
A. Check the memory leaks
B. Check the robustness
C. Check the branch coverage
D. Check the decision tables - Correct Answers -D
What is the main purpose of Informal review
A. Inexpensive way to get some benefit
B. Find defects
C. Learning, gaining understanding, effect finding
D. Discuss, make decisions, solve technical problems - Correct Answers -A
Which sections are included as part of the test summary report
W. Variances
X. Comprehensive assessment
Y. Evaluation
Z. Summary of activities
A. W, X and Y
B. W, X, Y and Z
C. W and X
D. W, X and Z - Correct Answers -B
Which factors contribute to humans making mistakes that can lead to faulty software
I. Setting aggressive schedule
II. Integrating complex systems
III. Allocating adequate resources
IV. Failing to control changes
A. I and II are true; III and IV are false
B. II and IV are true; I and III are false