Use cases can be performed to test
A. Unit testing
B. Business scenarios
C. Static testing
D. Performance testing - Correct Answers -D
A common test technique during component test is
A. Performance testing
B. Usability testing
C. Security testing
D. Statement and branch testing - Correct Answers -D
The software engineer's role in tool selection is
A. To identify. evaluate and select the tools
B. To initiate the tool search and present a case to management
C. To identify. evaluate. and rank tools. and recommend tools to management
D. To determine what kind of tool is needed. then ?nd it and buy it - Correct Answers -C
What is the smallest number of test cases required to Provide 100% branch
coverage?
|f(x>y) x=x+1:
else y=y+ 1:
whi|e(x>y)
{
y=x*y: x=x+1:
, 1
A. 1
B. 3
C. 4
D. 2 - Correct Answers -D
If an expected result is not speci?ed then:
A. It may be dif?cult to repeat the test
B. We cannot run the test
C. It may be dif?cult to determine if the test has passed or failed
D. We cannot automate the user inputs - Correct Answers -C
Match the following.
1. Configuration identification
2. Configuration control
3. Status reporting
4. Configuration auditing
a. Maintains of Cl's in a library
b. Checks on the contents of the library
c. Function recording and tracking problems.
d. Requires the all Cl's and their versions in the system are known
A. 1 -c. 2?b. 3-a. 4-d
B. 1 -d. 2?c. 3-d. 4-a
C. 1 -a. 2?b. 3-d. 4-c.
D. 1 -d. 2?a. 3-c. 4-b. - Correct Answers -D
A Project risk includes which of the following
A. Poor Software characteristics
CORRECT ANSWERS
Use cases can be performed to test
A. Unit testing
B. Business scenarios
C. Static testing
D. Performance testing - Correct Answers -D
A common test technique during component test is
A. Performance testing
B. Usability testing
C. Security testing
D. Statement and branch testing - Correct Answers -D
The software engineer's role in tool selection is
A. To identify. evaluate and select the tools
B. To initiate the tool search and present a case to management
C. To identify. evaluate. and rank tools. and recommend tools to management
D. To determine what kind of tool is needed. then ?nd it and buy it - Correct Answers -C
What is the smallest number of test cases required to Provide 100% branch
coverage?
|f(x>y) x=x+1:
else y=y+ 1:
whi|e(x>y)
{
y=x*y: x=x+1:
, 1
A. 1
B. 3
C. 4
D. 2 - Correct Answers -D
If an expected result is not speci?ed then:
A. It may be dif?cult to repeat the test
B. We cannot run the test
C. It may be dif?cult to determine if the test has passed or failed
D. We cannot automate the user inputs - Correct Answers -C
Match the following.
1. Configuration identification
2. Configuration control
3. Status reporting
4. Configuration auditing
a. Maintains of Cl's in a library
b. Checks on the contents of the library
c. Function recording and tracking problems.
d. Requires the all Cl's and their versions in the system are known
A. 1 -c. 2?b. 3-a. 4-d
B. 1 -d. 2?c. 3-d. 4-a
C. 1 -a. 2?b. 3-d. 4-c.
D. 1 -d. 2?a. 3-c. 4-b. - Correct Answers -D
A Project risk includes which of the following
A. Poor Software characteristics