Questions with Correct Answers
While trying to obtain the formal acceptance of the completed project scope and
associated deliverables, with whom should the project manager validate the product?
a. The sponsor, key stakeholders and customers
b. The customers
c. The quality control team members
d. Then change control board members - ANSWERSa. The sponsor, key stakeholders
and customers
The scope baseline, which consists of the project scope statement, the WBS, and the
WBS dictionary, is used as an input to all the following processes EXCEPT:
a. Determine budget process
b. Plan procurement management process
c. Define activities process
d. Develop the team - ANSWERSd. Develop the team
Determining if the project scope has been completed by describing project deliverables
and the work required to create the detail, enabling the project team to perform more
detailed planning, guiding the project teams work during execution, providing the
baseline for evaluating changes and other factors relies mostly upon the use of:
a. Statement of work
b. Project plan
c. Project charter
d. Project scope statement - ANSWERSd. Project scope statement
The major milestones reference some of the key stakeholders are not happy and
confident that their requirements are not met. The project manager should have
involved them in which of the following processes to ensure their approval of the
release?
a. Project management plan development
b. Identifying constrains
c. Validating scope
d. Schedule management - ANSWERSc. Validating scope
Which one of the following mostly includes the product acceptance criteria that outline
requirement a project must meet before stakeholder acceptance the final project or
service?
a. Quality management plan
b. Project scope statement
c. Scope management plan
, d. Requirements management plan - ANSWERSb. Project scope statement
Which of the following is NOT true about the define scope process?
a. It is the process of developing a comprehensive detailed description of the project
and product
b. Data analysis is used as a tool and technique in this process
c. The requirement document is the key output in this process
d. A detailed project scope statement that is created in this process is critical to project
success and build upon the additional detail analysis of requirement, major deliverables,
assumptions, constraints and other factors that are documented earlier in the project -
ANSWERSc. The requirement document is the key output in this process
Product scope describes the features, functions and physical characteristics that
characterize a product, service, or result. Completion of the project scope is measured
against which of the following?
a. Scope statement
b. Project requirements
c. Project objectives
d. Product requirements - ANSWERSd. Product requirements
Verified deliverables are inputs in which of the following scope management processes?
a. Define scope
b. Create WBS
c. Validate scope
d. Control scope - ANSWERSc. Validate scope
Includes the processes required to ensure the project includes all the work required,
and only the work required to complete the project successfully - ANSWERSProject
Scope Management
The work performed to deliver a product, services or result with the specified features
and functions - ANSWERSProject Scope
Is a component of the project management plan that describes how project and product
requirements will be analyzed, documented and managed - ANSWERSProject Scope
Management Plan
A component of the project management plan that describes how the project and
product requirement will be analyzed, documented, and managed -
ANSWERSRequirements Management Plan
Is used to provide information on effective requirement collection techniques, especially
the project that are using an iterative of adaptive project development methodology -
ANSWERSLessons Learned Register