◉ A designated Employee should be. Answer: 18+, FT, pass exam
◉ What is the initial Recovery Fund Fee? Answer: $25
◉ If a contractor earns more than $_______ per year, then the contractor
requires a Class A license. Answer: $750k
◉ If a contract awards more than $_____________ per year, then the
contractor requires a Class A license. Answer: $120k
◉ An Erosion control conservation plan needs to be approved within
___ days. Answer: 45 days
◉ Where do you go to file an appeal of a violation to the USBC
provisions? Answer: To the BBCA
◉ A contractor is required to submit a renewal within ___ days of the
expiration. Answer: 30 days
, ◉ Who can file a complaint against a contractor? Answer: Any person
◉ What is required when changing the for of entity from a sole
proprietorship to corp? Answer: a new license
◉ what is the max fund allowed for a single contractor? Answer:
$40,000
◉ To whom should a stop work order be given? Answer: owner, owners
agent, or the person doing the work
◉ Within how many days should be submitted an appeal for
construction? Answer: 90 days
◉ An appeal of the local building officials decision to refuse to grant a
modification to the USBC MUST be made to the local BBCA within a
Max of how many days? Answer: 90 days
◉ Documents related to a contract should be kept for ___ years. Answer:
5 years
◉ where should one set of all approved building documents be kept?
Answer: at the building site
CLASS A ACTUAL EXAM PAPER 2026
QUESTIONS WITH SOLUTIONS GRADED A+
◉ A designated Employee should be. Answer: 18+, FT, pass exam
◉ What is the initial Recovery Fund Fee? Answer: $25
◉ If a contractor earns more than $_______ per year, then the contractor
requires a Class A license. Answer: $750k
◉ If a contract awards more than $_____________ per year, then the
contractor requires a Class A license. Answer: $120k
◉ An Erosion control conservation plan needs to be approved within
___ days. Answer: 45 days
◉ Where do you go to file an appeal of a violation to the USBC
provisions? Answer: To the BBCA
◉ A contractor is required to submit a renewal within ___ days of the
expiration. Answer: 30 days
, ◉ Who can file a complaint against a contractor? Answer: Any person
◉ What is required when changing the for of entity from a sole
proprietorship to corp? Answer: a new license
◉ what is the max fund allowed for a single contractor? Answer:
$40,000
◉ To whom should a stop work order be given? Answer: owner, owners
agent, or the person doing the work
◉ Within how many days should be submitted an appeal for
construction? Answer: 90 days
◉ An appeal of the local building officials decision to refuse to grant a
modification to the USBC MUST be made to the local BBCA within a
Max of how many days? Answer: 90 days
◉ Documents related to a contract should be kept for ___ years. Answer:
5 years
◉ where should one set of all approved building documents be kept?
Answer: at the building site