EVMS || with Complete Solutions.
Which of the following are requirements for statusing the IMS?
a. Accurate start and finish dates for all tasks and milestones
b. Actual start and finish dates up to the status date
c. Forecasted start and finish dates for all tasks and milestones occurring after the status date
d. Actual finish dates for tasks in progress
e. All of the above correct answers a. Accurate start and finish dates for all tasks and milestones
b. Actual start and finish dates up to the status date
c. Forecasted start and finish dates for all tasks and milestones occurring after the status date
-Requirements for updating the Integrated Master Schedule (IMS) include actual start and finish
dates up to the status date, as well as forecasted start and finish dates occurring after the status
date.
Why is the 0/100 EVT only appropriate for WPs that start and finish within a single reporting
period?
1. Because no other EVT is appropriate for WPs with such short durations
2. Because management would have no insight into progress made in any period other than the
period the effort is 100% complete
3. Because 100% of the BCWP is claimed when the WP starts, and there is no way to measure
performance after that
4. Actually, the 0/100 EVT is appropriate for any WP, regardless of whether it spans multiple
reporting periods correct answers 2. Because management would have no insight into progress
made in any period other than the period the effort is 100% complete
-The 0/100 Earned Value Technique (EVT) is only appropriate for a Work Package (WP) that
starts and finishes within a single reporting period because no progress is shown until the effort
is 100% complete. The effort is either done or not.
With the Percent Complete EVT, the CAM establishes BCWP by determining a percentage of
the BCWS completed.
True or False correct answers True
The Percent Complete with QBD Earned Value Technique (EVT) can be used for longer
duration Work Packages because it is flexible enough to allow the Control Account Manager
(CAM) to establish a performance measure (% complete) for each reporting period.
The flexibility of this EVT is both a potential strength and a drawback. It provides the flexibility
to assess progress accurately, but that very flexibility can also tempt a CAM to overstate
performance early. To avoid this kind of subjectivity in performance measurement, the CAM
must provide quantifiable backup data (QBD) to support the percent complete determination
each month.
1. Major or critical subcontractor effort must be included in the IMS.
, True or False correct answers True
The level of detail from the subcontractor's schedule could be at the program intermediate or
detail schedule level, based on the visibility required to manage the effort.
The difference between TCPIEAC and CPIcum indicates the degree to which future performance
must be changed from past performance to achieve the EAC.
True or False correct answers True
If the difference between the To Complete Performance Index (TCPI) and the Cost Performance
Index (CPI) is +0.10, it could indicate an unrealistic Estimate at Completion (EAC).
If TCPI is higher than CPI: How is performing remaining work going to be more cost efficient
than in the past?
If TCPI is lower than CPI: What is confidence level that EAC is correct? Does EAC possibly
need updating?
EVMSD section 5.3.2
1. The EAC is equal to ACWP + _____. correct answers The Estimate at Completion (EAC) is
equal to the Actual Cost of Work Performed (ACWP) plus the Estimate to Complete (ETC).
EAC = ACWPcum + ETC
The Control Account Manager (CAM) reviews the EVM data monthly, at the Control Account
Level. With support from the analysts (cost, material, schedule), the CAM determines whether
the EAC is still realistic.
Accurate and timely forecasts of the final cost:
· ensure continuing visibility into resource needs
· lead to program success for both NGC and the customer
· support the customer's ability to provide sufficient program funding
EVMSD section 5.3
1. Each month, the CAM develops the rational to support EAC updates.
True or False correct answers Monthly, during the Estimate at Completion (EAC) process, the
Control Account Manager (CAM) will:
• Assess data to identify events, performance shifts, or data integrity issues that may warrant
EAC updates
• Develop rationale to support EAC updates
• Ensure timely resolution of data anomalies identified
• Subcontract/IWO
Which of the following are requirements for statusing the IMS?
a. Accurate start and finish dates for all tasks and milestones
b. Actual start and finish dates up to the status date
c. Forecasted start and finish dates for all tasks and milestones occurring after the status date
d. Actual finish dates for tasks in progress
e. All of the above correct answers a. Accurate start and finish dates for all tasks and milestones
b. Actual start and finish dates up to the status date
c. Forecasted start and finish dates for all tasks and milestones occurring after the status date
-Requirements for updating the Integrated Master Schedule (IMS) include actual start and finish
dates up to the status date, as well as forecasted start and finish dates occurring after the status
date.
Why is the 0/100 EVT only appropriate for WPs that start and finish within a single reporting
period?
1. Because no other EVT is appropriate for WPs with such short durations
2. Because management would have no insight into progress made in any period other than the
period the effort is 100% complete
3. Because 100% of the BCWP is claimed when the WP starts, and there is no way to measure
performance after that
4. Actually, the 0/100 EVT is appropriate for any WP, regardless of whether it spans multiple
reporting periods correct answers 2. Because management would have no insight into progress
made in any period other than the period the effort is 100% complete
-The 0/100 Earned Value Technique (EVT) is only appropriate for a Work Package (WP) that
starts and finishes within a single reporting period because no progress is shown until the effort
is 100% complete. The effort is either done or not.
With the Percent Complete EVT, the CAM establishes BCWP by determining a percentage of
the BCWS completed.
True or False correct answers True
The Percent Complete with QBD Earned Value Technique (EVT) can be used for longer
duration Work Packages because it is flexible enough to allow the Control Account Manager
(CAM) to establish a performance measure (% complete) for each reporting period.
The flexibility of this EVT is both a potential strength and a drawback. It provides the flexibility
to assess progress accurately, but that very flexibility can also tempt a CAM to overstate
performance early. To avoid this kind of subjectivity in performance measurement, the CAM
must provide quantifiable backup data (QBD) to support the percent complete determination
each month.
1. Major or critical subcontractor effort must be included in the IMS.
, True or False correct answers True
The level of detail from the subcontractor's schedule could be at the program intermediate or
detail schedule level, based on the visibility required to manage the effort.
The difference between TCPIEAC and CPIcum indicates the degree to which future performance
must be changed from past performance to achieve the EAC.
True or False correct answers True
If the difference between the To Complete Performance Index (TCPI) and the Cost Performance
Index (CPI) is +0.10, it could indicate an unrealistic Estimate at Completion (EAC).
If TCPI is higher than CPI: How is performing remaining work going to be more cost efficient
than in the past?
If TCPI is lower than CPI: What is confidence level that EAC is correct? Does EAC possibly
need updating?
EVMSD section 5.3.2
1. The EAC is equal to ACWP + _____. correct answers The Estimate at Completion (EAC) is
equal to the Actual Cost of Work Performed (ACWP) plus the Estimate to Complete (ETC).
EAC = ACWPcum + ETC
The Control Account Manager (CAM) reviews the EVM data monthly, at the Control Account
Level. With support from the analysts (cost, material, schedule), the CAM determines whether
the EAC is still realistic.
Accurate and timely forecasts of the final cost:
· ensure continuing visibility into resource needs
· lead to program success for both NGC and the customer
· support the customer's ability to provide sufficient program funding
EVMSD section 5.3
1. Each month, the CAM develops the rational to support EAC updates.
True or False correct answers Monthly, during the Estimate at Completion (EAC) process, the
Control Account Manager (CAM) will:
• Assess data to identify events, performance shifts, or data integrity issues that may warrant
EAC updates
• Develop rationale to support EAC updates
• Ensure timely resolution of data anomalies identified
• Subcontract/IWO