EVM || with Complete Solutions.
EVM correct answers A tool that allows both Government and contractor PMs to have visibility
into technical, cost, and schedule planning, performance, and progress on their contracts.
Cost Variance = correct answers = BCWP - ACWP
Schedule Variance = correct answers = BCWP - BCWS
Cost Performance Index = correct answers = BCWP/ACWP
Schedule Performance Index = correct answers = BCWP/BCWS
$50M correct answers Contracts of (____) or more require a formal EVM system validation.
Integrated Management System correct answers Earned Value Management (EVM) is an (____);
coordinates work scope, schedule, and budget goals, and objectively measures progress towards
these goals.
Defense Contract Management Agency (DCMA) correct answers The (____) is the only
organization recognized by DoD to perform EVMS Validation.
Defense Contract Audit Agency (DCAA) correct answers The (____) is responsible for
conducting audit reviews of the contractor's accounting system policies, procedures, and
activities.
Contract Performance Report (CPR) correct answers For contract's awarded prior to July 1,
2012, the (____) is a contractually required report, prepared by the contractor, containing
performance information derived from the internal EVMS.
Integrated Program Management Report (IPMR) correct answers For contracts awarded after
July 1, 2012 the (____) has replaced the Contract Performance Report (CPR) and Integrated
Master Schedule (IMS) contractual requirements.
Cost Variance (CV) correct answers (____) indicates how much over or under budget the project
is.
Schedule Variance (SV) correct answers (____) indicates how much ahead or behind schedule
the project is.
Cost Performance Index (CPI) correct answers (___) measures how efficiently the contractor is
performing the work based on the original planned budget.
Basic elements of performance measurement correct answers a. Baseline
b. Project Plan
EVM correct answers A tool that allows both Government and contractor PMs to have visibility
into technical, cost, and schedule planning, performance, and progress on their contracts.
Cost Variance = correct answers = BCWP - ACWP
Schedule Variance = correct answers = BCWP - BCWS
Cost Performance Index = correct answers = BCWP/ACWP
Schedule Performance Index = correct answers = BCWP/BCWS
$50M correct answers Contracts of (____) or more require a formal EVM system validation.
Integrated Management System correct answers Earned Value Management (EVM) is an (____);
coordinates work scope, schedule, and budget goals, and objectively measures progress towards
these goals.
Defense Contract Management Agency (DCMA) correct answers The (____) is the only
organization recognized by DoD to perform EVMS Validation.
Defense Contract Audit Agency (DCAA) correct answers The (____) is responsible for
conducting audit reviews of the contractor's accounting system policies, procedures, and
activities.
Contract Performance Report (CPR) correct answers For contract's awarded prior to July 1,
2012, the (____) is a contractually required report, prepared by the contractor, containing
performance information derived from the internal EVMS.
Integrated Program Management Report (IPMR) correct answers For contracts awarded after
July 1, 2012 the (____) has replaced the Contract Performance Report (CPR) and Integrated
Master Schedule (IMS) contractual requirements.
Cost Variance (CV) correct answers (____) indicates how much over or under budget the project
is.
Schedule Variance (SV) correct answers (____) indicates how much ahead or behind schedule
the project is.
Cost Performance Index (CPI) correct answers (___) measures how efficiently the contractor is
performing the work based on the original planned budget.
Basic elements of performance measurement correct answers a. Baseline
b. Project Plan