◉ A Statement Of Work should include the following: Answer: The
work to be performed, location of work, period of performance,
deliverable schedule, any special requirements
◉ Acquisition Planning's principal purpose is to ensure that the
government meets its needs in the most effective, economical and
timely manner while emphasizing competition and promoting the
use of commercial items. Answer: True
◉ The COR's role in evaluating and awarding a contract include IPT
member, SSEB technical evaluator, and Technical Expert or
Representative. Answer: True
◉ The two techniques used to select a contractor within the best
value continuum include: Answer: Lowest price technically available
and trade off process
◉ Who has the official responsibility for performing market
research? Answer: COR/functional office
, ◉ Items to consider during the development of the IGE include:
(select all that apply) Answer: 1. An estimate that agrees with
document market research
2. an unbiased realistic cost estimate for supplies or services that
will be procured under the contract
◉ The existing contract, including all options, is about to end. The
customer likes the work of the incumbent contractor and has
expressed a desire to have the new contract be awarded to that
incumbent contractor. Which one of the following statements is
true? Answer: The COR can assist an acquisition planning and
writing the evaluation criteria to ensure the best contractor is
selected for the new contract
◉ Some methods of contracting require more time than others.
Which of the following is not a streamlined method of acquisition?
Answer: Buys against GSA federal supply schedule
◉ The Contracting Officer's Representative must read and
understand the contract, including any attachments and
modifications to the contract. Answer: True
◉ A separate Contract Line Item Number (CLIN) should be used for
each item on a contract. Answer: True
ANSWERS VERIFIED
◉ A Statement Of Work should include the following: Answer: The
work to be performed, location of work, period of performance,
deliverable schedule, any special requirements
◉ Acquisition Planning's principal purpose is to ensure that the
government meets its needs in the most effective, economical and
timely manner while emphasizing competition and promoting the
use of commercial items. Answer: True
◉ The COR's role in evaluating and awarding a contract include IPT
member, SSEB technical evaluator, and Technical Expert or
Representative. Answer: True
◉ The two techniques used to select a contractor within the best
value continuum include: Answer: Lowest price technically available
and trade off process
◉ Who has the official responsibility for performing market
research? Answer: COR/functional office
, ◉ Items to consider during the development of the IGE include:
(select all that apply) Answer: 1. An estimate that agrees with
document market research
2. an unbiased realistic cost estimate for supplies or services that
will be procured under the contract
◉ The existing contract, including all options, is about to end. The
customer likes the work of the incumbent contractor and has
expressed a desire to have the new contract be awarded to that
incumbent contractor. Which one of the following statements is
true? Answer: The COR can assist an acquisition planning and
writing the evaluation criteria to ensure the best contractor is
selected for the new contract
◉ Some methods of contracting require more time than others.
Which of the following is not a streamlined method of acquisition?
Answer: Buys against GSA federal supply schedule
◉ The Contracting Officer's Representative must read and
understand the contract, including any attachments and
modifications to the contract. Answer: True
◉ A separate Contract Line Item Number (CLIN) should be used for
each item on a contract. Answer: True