Which of the following represents a virtual tie-line updated in real time? -
ANSWER pseudo-tie
Balancing Areas shall analyze forecasted generation availability and reserve levels, and
inform their reliability coordinators of actual or potential generation deficiencies each: -
ANSWER day
Balancing authorities that share jointly owned generation must include their share of the
unit governor droop response into their respective frequency bias setting if the energy is
scheduled as a: - ANSWER dynamic schedule
A balancing authority's frequency bias contribution is 30 MW / 0.1 Hz. What is the balancing
authority's frequency response due to the external loss of 1,000 MW generator which
causes system frequency to decline to 59.95 Hz? - ANSWER 15 MW
A system operator experiences a system failure of AGC and ACE functions. The operator's
first priority should be to: - ANSWER manually calculate ACE and adjust generation to
maintain scheduled interchange
Interruptible loads may be dispatched to alleviate: - ANSWER capacity deficiency
Telecommunication facilities that link with interconnected systems should be available to the
system operator: - ANSWER on a continuous basis
1
Which of the following represents a virtual tie-line updated in real time? -
ANSWER pseudo-tie
Balancing Areas shall analyze forecasted generation availability and reserve levels, and
inform their reliability coordinators of actual or potential generation deficiencies each: -
ANSWER day
Balancing authorities that share jointly owned generation must include their share of the
unit governor droop response into their respective frequency bias setting if the energy is
scheduled as a: - ANSWER dynamic schedule
A balancing authority's frequency bias contribution is 30 MW / 0.1 Hz. What is the balancing
authority's frequency response due to the external loss of 1,000 MW generator which
causes system frequency to decline to 59.95 Hz? - ANSWER 15 MW
A system operator experiences a system failure of AGC and ACE functions. The operator's
first priority should be to: - ANSWER manually calculate ACE and adjust generation to
maintain scheduled interchange
Interruptible loads may be dispatched to alleviate: - ANSWER capacity deficiency
Telecommunication facilities that link with interconnected systems should be available to the
system operator: - ANSWER on a continuous basis