Written in
2025/2026

ACI Concrete Flatwork Finishing Certification Questions And Correct Answers How to reduce excessive bleeding on job site? - ANSWER -Don't add water to the mix How to reduce the chance of scaling? - ANSWER -Air-entrainment Random cracking causes: - ANSWER -Placing slab on uneven surfaces, plastic shrinkage, not deep enough joints, sawing too late, spacing joints too far apart, etc Settlement cracking is likely yo occur when: - ANSWER -Concrete sets slowly When is air-entrained concrete used? - ANSWER -When it will be exposed to freezing and thawing cycles What is a byproduct of cement meeting water? - ANSWER -Heat of hydration (gets hotter) Strength of normal concrete is dependent of: - ANSWER -Water cement ratio What is the most economical way of pouring concrete? - ANSWER -Chute directly off a truck How can delays be avoided when using a boom pump? - ANSWER -By allowing enough room to fit 2 trucks, so one truck is ready while the other is finishing When to use a bull float? - ANSWER -When the FF number is below 20 When to use a highway straightedge? - ANSWER -When the FF number is 20 or above What are hand floats used for? - ANSWER -To start the floating process, to produce a plane level finish, texture finish as well Wood floats: - ANSWER -Best for non-air-entrained and high slump concrete Magnesium float: - ANSWER -For air-entrained and lightweight concrete Hand finishing trowel: - ANSWER -Used in the final stages of finishing, after floating, steel 3-5" wide & 10-20" long Fresnos: - ANSWER -Large, long-handed trowels that look like bull floats. Blade= 5" wide and 24-48" long. Use Fresno when bleed water is evaporated Slab finishing steps: - ANSWER -Pour concrete, screening, floating, edging, jointing, and troweling Dipstick - ANSWER -Measures both floor flatness and levelness When to do F-number testing? - ANSWER -ASAP, preferably within 24 hrs of placement, but no later than 72 hrs The higher the F-number: - ANSWER -The more level the floor The closer to 50: - ANSWER -The more flat & level it'll be When to trowel left to right? - ANSWER -When pulling concrete into a low spot When to trowel right to left? - ANSWER -Pulling concrete into a high spot What is concrete made without coarse aggregate? - ANSWER -Motar or grout What do accelerating admixtures do? - ANSWER -Speed up setting/ hardening time Where are accelerating admixtures useful? - ANSWER -In cold weather What tool to use on granular subleases and sandy soils? - ANSWER -Vibratory plate compactor What tool to use on a clay sublease? - ANSWER -Sheepsfoot roller When specs don't require a concrete slab to come in direct contact with the vapor, the preferred method for reducing slab curling problems is: - ANSWER -Placing a 3" thick layer of compatible sand containing ROCK DUST on the vapor retarder prior to concrete placement How is concrete quantity calculated? - ANSWER -L x W x H / 27 yd^3 10% rule - ANSWER -Move decimal one spot to the left of your calculated number, then add this number to calculated number When striking concrete with a handheld vibrating screed, what should you do? - ANSWER -Strike straight back, must always be enough concrete to fill voids ahead of the screed, avoid low spots. When to use wet screeds? - ANSWER -When FF numbers are above 20. What does rebar do? - ANSWER -Keeps cracks tightly closed Contraction joint rule: - ANSWER -Must be 1/4 the slab thickness What 2 methods can be used in hot weather, when slab curling may have to start after placing but before finishing? - ANSWER -Evaporation retarders and fog sprayers Curling with burlap: - ANSWER -Wrinkle bumps Where to start edging: - ANSWER -2 ft off the corner; avoid starting at the edge Isolation joints should be: - ANSWER -Circular or diamond How is concrete sold? Sold in what units? - ANSWER -By volume in cubic yards or cubic meters Concrete should be completely discharged: - ANSWER -Within 1 1/2 hours Who should attend the pre-construction meeting? - ANSWER -Finisher foreman Type I Concrete - ANSWER -Normal or ordinary use What is type I concrete typically used on? - ANSWER -Slab-on grade, reinforced concrete buildings, and bridges Type II Concrete - ANSWER -Moderate sulfate resistance Where is type II concrete used? - ANSWER -Where moderate sulfate exposure from the soil or groundwater must be resisted Type III Concrete - ANSWER -High early strength Type III Concrete Properties - ANSWER -Similar to Type I, but more finely

Show more Read less
Institution
ACI Concrete Field Testing
Course
ACI Concrete Field Testing









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ACI Concrete Field Testing
Course
ACI Concrete Field Testing

Document information

Uploaded on
January 19, 2026
Number of pages
12
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ACI Concrete Field Testing
Technician- Grade I Exam
Questions with correct Answers
2025-2026


A maximum temperature of freshly mixed concrete is specified in ASTM C1064.

True of False? - ANSWER -False

The sample of concrete used for temperature determination must be rodded 25

times. True or False? - ANSWER -False

Sampling by this method is required when tests are to be made to determine _____

with specification requirements. - ANSWER -Compliance

This method covers sampling from four types of mixtures which are _____,

_____, _____, and _____. - ANSWER -Stationary mixers, paving mixers,

revolving drum mixers, and open top mixers

The maximum allowable time between obtaining the first and final portions of a

composite sample is _____ minutes. - ANSWER -15

Portions of a composite sample shall be thoroughly remixed bfore beginning tests

on the sample. True of False? - ANSWER -True

The maximum elapsed time allowed between obtaining the final portion of the

composite sample and beginning the tests for slump, temperature, and air content is

_____ minutes. - ANSWER -5

The molding of strength test specimens shall begin within _____ minutes after

fabricating the composite sample. - ANSWER -15

, The concrete sample must be protected from contamination and _____. -

ANSWER -Rapid evaporation

The minimum size sample for making strength test specimens is _____. -

ANSWER -28 L (1ft^3)

When sampling from a stationary mixer, the batch must be sampled at _____ or

more regularly spaced intervals during discharge of the middle portion of the batch - ANSWER -2

The composite sample for a paving mixer must represent a minimum of _____

different portions of the batch of concrete taken from the pile after discharge. -

ANSWER -5

When sampling from a revolving drum truck mixer, concrete must be sampled at a

minimum of _____ regularly spaced intervals during discharge of the middle

portion of this batch. - ANSWER -2

Concrete samples from a truck mixer must be obtained before any water or

admixtures are added to the mixer at the job site. True or False? - ANSWER

False

The composite samples from a truck mixer must be obtained from the _____

portion of the batch. - ANSWER -Middle

When the concrete contains aggregate larger than that permitted for a particular

test method, the sample of concrete must be _____ _____ before making the test. -

ANSWER -Wet sieved

The slump test is applicable to plastic concrete with a maximum size aggregate of

_____. - ANSWER -1.5 in. [37.5 mm]

When the concrete contains aggregate larger than allowed for the slump test, the

large aggregate must be _____. - ANSWER -Removed by wet sieving the sample

over 1.5 in. [37.5 mm] sieve

The mold for making the slump test is in the shape of _____. - ANSWER -The

frustum of a cone

The height of the slump mold is _____. - ANSWER -12 in. [300 mm]

The interior surface of the slump mold is allowed to have minor irregularities.
$19.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
carolshi

Get to know the seller

Seller avatar
carolshi Walden University
View profile
Follow You need to be logged in order to follow users or courses
Sold
0
Member since
1 year
Number of followers
0
Documents
102
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions