NERC Certification Practice Questions with
Correct Answers | Updated (100% Correct
Answers)
Which of the following represents a virtual tie-line updated in real
time? Answer: pseudo-tie
Balancing Areas shall analyze forecasted generation availability and
reserve levels, and inform their reliability coordinators of actual or
potential generation deficiencies each: Answer: day
Balancing authorities that share jointly owned generation must
include their share of the unit governor droop response into their
respective frequency bias setting if the energy is scheduled as a:
Answer: dynamic schedule
A balancing authority's frequency bias contribution is 30 MW / 0.1
Hz. What is the balancing authority's frequency response due to the
external loss of 1,000 MW generator which causes system frequency
to decline to 59.95 Hz? Answer: 15 MW
A system operator experiences a system failure of AGC and ACE
functions. The operator's first priority should be to: Answer:
manually calculate ACE and adjust generation to maintain scheduled
interchange
© 2025 All rights reserved
NERC Certification Practice Questions with
Correct Answers | Updated (100% Correct
Answers)
Which of the following represents a virtual tie-line updated in real
time? Answer: pseudo-tie
Balancing Areas shall analyze forecasted generation availability and
reserve levels, and inform their reliability coordinators of actual or
potential generation deficiencies each: Answer: day
Balancing authorities that share jointly owned generation must
include their share of the unit governor droop response into their
respective frequency bias setting if the energy is scheduled as a:
Answer: dynamic schedule
A balancing authority's frequency bias contribution is 30 MW / 0.1
Hz. What is the balancing authority's frequency response due to the
external loss of 1,000 MW generator which causes system frequency
to decline to 59.95 Hz? Answer: 15 MW
A system operator experiences a system failure of AGC and ACE
functions. The operator's first priority should be to: Answer:
manually calculate ACE and adjust generation to maintain scheduled
interchange