Answers |Well Elaborated Solutions|
A system of erosion and sediment control BMP's is often called a - ANSWER -
Treatment train
Accelerated erosion that is most often caused by - ANSWER -Humans
Of the following factors of erosion the one a contractor has the most control over -
ANSWER -ground cover
Of the following the one that is primary erosion and sediment control objective -
ANSWER -Minimize the extent and duration of soil exposure stablize to start areas
quickly
If you have questions or concerns about the BMP's specified in your project
SWPPP you should - ANSWER -contact your SWPPP designer
When installing and maintaining a check dam make sure - ANSWER -The low
point of the check that was in the middle of a channel
Storm drain inlet protection is intended tp - ANSWER -Pond water in allow
sediment to settle out
, To reduce the possibility of undercutting you should - ANSWER -Install filter
fabric under BMPs and stormwater conveyance
Sediment basins are often converted to - ANSWER -Detention and retention
ponds
Concrete water washout has a high - ANSWER -PH
Proper spell management should include all the following except - ANSWER -
Installation of spill pit on your construction site
The best location for a portable toilet on your construction site is - ANSWER -On
level ground in a low construction traffic area
A common potential pollutant in a vehicle maintence area is - ANSWER -
Petroleum
Which material management practice may address both sediment and dust control
- ANSWER -street cleaning
Temporary stabilization should be implemented - ANSWER -On all disturbed
areas that will remain in active for 14 days or more
A key first step before installing a roll erosion control product of our RECP is -
ANSWER -Properly preparing the ground surface