constraint - correct answers Any factor that limits the performance of a system and restricts its output
Bottle Neck - correct answers A capacity constraint resource (CCR) whose available capacity limits the
organization's ability to meet the product volume, product mix, or demand fluctuations required by the
marketplace
Theory of Constraint - correct answers The Theory of Constraints (TOC)
A systematic management approach that focuses on actively managing those constraints that impede a
firm's progress toward its goal
Theory of constraints view of Inventory - correct answers All the money invested in a system in
purchasing things that it intends to sale.
-Decrease in (I) leads to increase in net profit, ROI, and Cash flows
Theory of constraints view of Throughput - correct answers Rate at which a system generates money
through sales
-An increase in (T) leads to an increase in net profit, ROI, and cashs
Theory of constraints view of Operating Expense - correct answers All the money a system spends to
turn inventory into throughput
-A decrease in (OE) leads to an increase in net profit, ROI, and cash flows
Theory of constraints view of Utilization - correct answers The degree to which equipment, space, or
workforce is currently being used; it is measured as the ratio of average output rate to maximum
capacity, expressed as a percentage
-An increase in U at the bottle neck leads to an increase in net profit, ROI, and cash flows
Key principals of TOCs - correct answers1. The focus should be on balancing flow, not on balancing
capacity.
, 2. Maximizing the output and efficiency of every resource may not maximize the throughput of the
entire system.
3. An hour lost at a bottleneck or constrained resource is an hour lost for the whole system.
4. An hour saved at a nonbottleneck resource does not make the system more productive.
5. Inventory is needed only in front of bottlenecks and in front of assembly and shipping points.
6. Work should be released into the system only as frequently as needed by the bottlenecks.
-Bottleneck flows = market demand
7. Activating a nonbottleneck resource is not the same as utilizing a bottleneck resource.
-It doesn't increase throughput or promote better performance.
8. Every capital investment must be viewed from the perspective of the global impact on overall
throughput, inventory, and operating expense.
steps of TOC - correct answers1. Identify the System Bottleneck(s)
2. Exploit the Bottleneck(s)
3. Subordinate All Other Decisions to Step 2
4. Elevate the Bottleneck(s)
5. Do Not Let Inertia Set In
Throughput time - correct answersTotal elapsed time from the start to the finish of a job or a customer
being processed at one or more work centers
Drum-Buffer-Rope - correct answersA planning and control system that regulates the flow of work-in-
process materials at the bottleneck or the capacity constrained resource (CCR) in a productive system
Drum - correct answersThe bottleneck schedule is the drum because it sets the beat or the production
rate for the entire plant and is linked to market demand