NERC RC Exam Prep | Questions & 100% Correct Answers

Rating
-
Sold
-
Pages
54
Grade
A+
Uploaded on
13-01-2026
Written in
2025/2026

The NERC RC Exam Prep Questions with 100% Correct Answers resource provides exam-style questions with verified solutions to support Reliability Coordinator certification success. Covering NERC standards, real-time system operations, contingency analysis, emergency operations, reliability coordination, transmission operations, and compliance requirements, this comprehensive study guide strengthens exam readiness, reinforces critical decision-making skills, and builds confidence for passing the NERC RC certification examination.

Show more Read less
Institution
NERC RC
Course
NERC RC











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NERC RC
Course
NERC RC

Document information

Uploaded on
January 13, 2026
Number of pages
54
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

NERC RC EXAM PREP QUESTIONS AND 100%
CORRECT ANSWERS (NEWEST)


When does the Contingency Reserve Restoration Period begin?

A. At the top of the hour after the Reportable Disturbance
B. At the start of the Reportable Disturbance
C. At the end of the Disturbance Recovery Period
D. When all Contingency Reserve has been exhausted - ANSWER C. At the end of
the Disturbance Recovery Period

Which of the following terms is defined as the scan rate values of a Balancing
Authority's ACE measured in MW, which includes the difference between the
Balancing Authority's Net Interchange Actual and its Net Interchange Scheduled,
plus its Frequency Bias obligation, plus any known meter error?

A. Automatic Time Error
B. Reporting ACE
C. ACE Control Error
D. Reserve Sharing Group Reporting - ANSWER B. Reporting ACE


Which of the following terms applies to the Western Interconnection only, and the
addition of a component to the ACE equation that modifies the control point for the
purpose of continuously paying back Primary Inadvertent Interchange to correct
accumulated time error?

A. Reporting ACE
B. Automatic Time Error Correction
C. Reserve Sharing Group Reporting ACE
D. Regulation Reserve Sharing Group - ANSWER B. Automatic Time Error Correction


You are a Balancing Authority Operator. A neighboring Balancing Authority in the
Interconnection suddenly has a 500 MW generator trip due to a generator ground.
What part of the ACE equation, ACE = (NIA-NIS) - 10B (FA-FS) -

,IME, allows you and other Balancing Authorities in the Interconnection to help
stabilize the Interconnection frequency error?


A. (FA- FS) - IME
B. NIA - NIS
C. 10B (FA-FS)
D. 4 IME - ANSWER C. 10B (FA-FS)


Balancing Authority A is scheduled to import a net 200 MW and is actually importing
a net 150 MW. The Bias Setting is -100 MW/.1 HZ and Actual Frequency is 59.95 Hz.
What is Balancing Authority A's ACE reading?

A. +100 MW
B. -100 MW
C. 0 MW
D. -55 MW - ANSWER C. 0 MW


Which of the following elements is NOT included in the ACE equations frequency
component?

A. Actual Frequency (FA)
B. Scheduled Frequency (FS)
C. Frequency Bias Setting (B)
D. Meter Error (IME) - ANSWER D. Meter Error (IME)


A Balancing Authority is slightly undergenerating its Actual System Frequency (FA) is
60.03 Hz. What is the result of the Balancing Authority's action?


A. The Balancing Authority is helping the Interconnection Frequency.
B. The Balancing Authority is in CPS1 violation.
C. The Balancing Authority is hurting the Interconnection Frequency.
D. The Balancing Authority is in BAAL violation - ANSWER A. The Balancing
Authority is helping the Interconnection Frequency


Which statement best describes the CPS1 requirement?


A. ACE must follow changes in load and schedule within a bandwidth called L10.
B. The Responsible Entity must operate so its CPS1 is greater than or equal to 100%
for the preceding 12-month period.
C. The average ACE for a defined 10-minute period must be within a limit called
L10.

,D. ACE must start to return to zero one minute after crossing zero. - ANSWER
B. The Responsible Entity must operate so its CPS1 is greater than or equal to 100%
for the preceding 12-month period


A Balancing Authority's CPS1 calculation is computed using its clock-minute average
of two values. What are those two values?

A. Reporting ACE and Frequency Error
B. Actual and Scheduled Net Interchange NIA and NIS.
C. L10 and Reporting ACE
D. Actual and Scheduled Frequency (FA and FS) - ANSWER A. Reporting ACE and
Frequency Error


To conform to CPS requirements, a Balancing Authority must have which of the
following?


A. CPS1 greater than or equal to 90% or BAAL greater than or equal to 100%.
B. CPS1 greater than or equal to 100% and ACE does not exceed BAAL more than
15 consecutive minutes.
C. CPS1 greater than or equal to 100% and ACE does not exceed BAAL more than
30 consecutive minutes.
D. CPS1 greater than or equal to 90% and ACE does not exceed BAAL more than
30 consecutive minutes. - ANSWER C. CPS1 greater than or equal to 100% and
ACE does not exceed BAAL more than 30 consecutive minutes.


What should a Balancing Authority set Scheduled Frequency to for a slow Time Error
Correction?


A. 60.02 Hz
B. 59.98 Hz
C. 59.80 Hz
D. 60.20 Hz - ANSWER A. 60.02 Hz


Which of the following is a potential source of Contingency Reserve?
1. Offline generation that takes 10 minutes to start and ramp to full output
2. Online generation at full load
3. Controllable load resources
4. Voltage reductions

A. 3 and 4
B. 2 and 3
C.1 and 3
D.1 and 2 - ANSWER C. 1 and 3

, In an Interconnection, which of the following is required to be in the metered
boundaries of a Balancing Authority Area?

A. Generation
B. Transmission
C. Load
D. All are required to be within the metered boundaries of a Balancing Authority. -
ANSWER D. All are required to be within the metered boundaries of a Balancing
Authority.

The minimum compliance for NERC Disturbance Control Standard (DCS) is
?

A. 90% of all reportable disturbances
B. 90% of all disturbances
C. 100% for all reportable disturbances
D. 100% for all generator tips - ANSWER C. 100% for all reportable
disturbances


A Balancing Authority has a normal load of around 8500 MW. Its most severe single
contingency is a 700 MW coal-fired steam unit. At 0810, the ACE value was at -55
MW when a 600 MW generator in the Balancing Authority's northern area tripped
off line due to a generator differential. This event resulted in a large negative ACE
for the Balancing Authority. What value must ACE return to and in what time frame
to avoid a DCS violation?

A. -55 MW ACE in 15 minutes
B. Zero ACE in 10 minutes
C. -55 MW ACE in 10 minutes
D. Zero ACE in 15 minutes - ANSWER A. -55 MW ACE in 15 minutes

If a Reserve Sharing Group member has experienced a Reportable Disturbance
condition but does not call for reserve activation from other members, the entire
group is considered to be in a disturbance condition.

A. True
B. False - ANSWER B. False

Turbine governors arrest Frequency deviations. Of the following, which control
system compares and brings Net Actual Interchange back in line or as close to Net
Scheduled Interchange as possible?

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Stuviagold Harvard University
View profile
Follow You need to be logged in order to follow users or courses
Sold
14
Member since
8 months
Number of followers
0
Documents
331
Last sold
5 days ago
StuviaGold

StuviaGold Test Banks and Practice Exams Are you Struggling to find the perfect study materials? You have come to the right place, StuviaGold ! We deliver high-quality test banks, practice exams, and study resources to make exam prep stress-free and effective. Remember: Success doesn’t happen by chance. It happens by choice. Choose the signature StuviaGold Test Banks and Practice Exams! Study Tip: Study smart, not hard. Your success story starts here! Choose StuviaGold, and Let’s make success your new normal.

Read more Read less
4.5

2 reviews

5
1
4
1
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions