Second Class Boiler Licenses Minnesota Exam Questions (Solved) GRADED
A+., Exams of Science education
Certificate of inspection - ANSWERmeans a sticker attached to the boiler or
pressure vessel which documents the month and year of the inspection and
the employer of the inspector performing the inspection.
Certificate of registration - ANSWERmeans a document that has been made
available on the department's Web site that lists all registered boilers and
pressure vessels at a location, including the last inspection date, the
certificate expiration date, and the maximum allowable working pressure for
each boiler or pressure vessel.
High-pressure boiler - ANSWERmeans a boiler operating at a steam or other
vapor pressure in excess of 15 psig, or a water or other liquid boiler in which
the pressure exceeds 160 psig or the temperature exceeds 250 degrees
Fahrenheit.
Inspection due date - ANSWERmeans the last possible date that the
inspection can be completed within the time limits in this chapter
, Insurance company boiler inspector - ANSWERmeans a national board-
commissioned inspector who holds a current certificate of competency
issued by the state.
Low-pressure boiler - ANSWERmeans a boiler operating at a steam or other
vapor pressure of 15 psig or less, or a water or other liquid boiler in which the
pressure does not exceed 160 psig and the temperature does not exceed 250
degrees Fahrenheit.
National board - ANSWERmeans the National Board of Boiler and Pressure
Vessel Inspectors, which is an organization comprised of chief Inspectors for
the states, cities, and territories of the United States and provinces and
territories of Canada
National Board Inspection Code; NBIC - ANSWERmeans a three-part technical
document that is written and published by the national board detailing the
installation, inspection, and repair of boilers and pressure vessels.
Operation - ANSWERmeans the on-site act of manipulating, monitoring, and
testing of boilers and their appurtenances by a properly licensed engineer or
an apprentice under the direct supervision of the properly licensed engineer.
Psig - ANSWERpounds per square inch gauge
Remote monitoring - ANSWERmeans the act of viewing or overseeing the
boiler or boiler plant operating parameters and conditions from a remote
location.
A+., Exams of Science education
Certificate of inspection - ANSWERmeans a sticker attached to the boiler or
pressure vessel which documents the month and year of the inspection and
the employer of the inspector performing the inspection.
Certificate of registration - ANSWERmeans a document that has been made
available on the department's Web site that lists all registered boilers and
pressure vessels at a location, including the last inspection date, the
certificate expiration date, and the maximum allowable working pressure for
each boiler or pressure vessel.
High-pressure boiler - ANSWERmeans a boiler operating at a steam or other
vapor pressure in excess of 15 psig, or a water or other liquid boiler in which
the pressure exceeds 160 psig or the temperature exceeds 250 degrees
Fahrenheit.
Inspection due date - ANSWERmeans the last possible date that the
inspection can be completed within the time limits in this chapter
, Insurance company boiler inspector - ANSWERmeans a national board-
commissioned inspector who holds a current certificate of competency
issued by the state.
Low-pressure boiler - ANSWERmeans a boiler operating at a steam or other
vapor pressure of 15 psig or less, or a water or other liquid boiler in which the
pressure does not exceed 160 psig and the temperature does not exceed 250
degrees Fahrenheit.
National board - ANSWERmeans the National Board of Boiler and Pressure
Vessel Inspectors, which is an organization comprised of chief Inspectors for
the states, cities, and territories of the United States and provinces and
territories of Canada
National Board Inspection Code; NBIC - ANSWERmeans a three-part technical
document that is written and published by the national board detailing the
installation, inspection, and repair of boilers and pressure vessels.
Operation - ANSWERmeans the on-site act of manipulating, monitoring, and
testing of boilers and their appurtenances by a properly licensed engineer or
an apprentice under the direct supervision of the properly licensed engineer.
Psig - ANSWERpounds per square inch gauge
Remote monitoring - ANSWERmeans the act of viewing or overseeing the
boiler or boiler plant operating parameters and conditions from a remote
location.