1. What is the primary purpose of a project network
diagram?
A. To show project costs
B. To assign resources
C. To display task dependencies and sequencing
D. To evaluate employee performance
Correct Answer: C
2. Which project scheduling method uses nodes to
represent activities?
A. Gantt Chart
B. PERT
C. CPM
D. Activity-on-Node (AON)
Correct Answer: D
, 3. In an Activity-on-Node (AON) network, arrows
represent:
A. Activities
B. Milestones
C. Dependencies
D. Resources
Correct Answer: C
4. The critical path in a project network is defined as:
A. The path with the most activities
B. The shortest path through the network
C. The longest path that determines project duration
D. The least expensive path
Correct Answer: C
5. An activity on the critical path has which amount of
slack?
A. Maximum slack
B. Zero slack
C. Positive slack
D. Negative slack
Correct Answer: B
MULTIPLE-CHOICE QUESTIONS AND
VERIFIED ANSWERS.
1. What is the primary purpose of a project network
diagram?
A. To show project costs
B. To assign resources
C. To display task dependencies and sequencing
D. To evaluate employee performance
Correct Answer: C
2. Which project scheduling method uses nodes to
represent activities?
A. Gantt Chart
B. PERT
C. CPM
D. Activity-on-Node (AON)
Correct Answer: D
, 3. In an Activity-on-Node (AON) network, arrows
represent:
A. Activities
B. Milestones
C. Dependencies
D. Resources
Correct Answer: C
4. The critical path in a project network is defined as:
A. The path with the most activities
B. The shortest path through the network
C. The longest path that determines project duration
D. The least expensive path
Correct Answer: C
5. An activity on the critical path has which amount of
slack?
A. Maximum slack
B. Zero slack
C. Positive slack
D. Negative slack
Correct Answer: B