1. Which of the following is a primary responsibility of a construction
manager?
A. Designing structural plans
B. Supervising construction schedules
C. Preparing legal contracts
D. Conducting soil testing
Correct Answer: B. Supervising construction schedules
Rationale: The construction manager oversees project schedules,
ensures tasks are completed on time, and coordinates resources. Design
and testing are typically handled by engineers or architects.
2. The Critical Path Method (CPM) is used to:
A. Determine project costs
B. Identify project delays and manage timelines
C. Select subcontractors
D. Conduct quality inspections
Correct Answer: B. Identify project delays and manage timelines
Rationale: CPM is a scheduling technique that identifies the longest
sequence of tasks (critical path) and highlights where delays could
affect project completion.
,3. What is the purpose of a construction budget contingency?
A. To reduce project scope
B. To cover unexpected costs
C. To increase contractor profits
D. To extend project deadlines
Correct Answer: B. To cover unexpected costs
Rationale: Contingencies are allocated to handle unforeseen
circumstances like material price increases or design changes.
4. Which document legally defines the scope of work for a
construction project?
A. Project schedule
B. Scope of Work (SOW) or contract
C. Risk management plan
D. Request for Proposal (RFP)
Correct Answer: B. Scope of Work (SOW) or contract
Rationale: The SOW specifies what work is included in the contract,
clarifying responsibilities and deliverables.
5. In construction risk management, what is risk mitigation?
A. Ignoring minor risks
B. Implementing measures to reduce risk impact
C. Transferring risk to another party without planning
D. Waiting until problems occur
Correct Answer: B. Implementing measures to reduce risk impact
Rationale: Mitigation strategies aim to minimize the likelihood or
severity of risks.
,6. Which of the following best describes “lean construction”?
A. Using minimal labor to cut costs
B. Maximizing efficiency and reducing waste in construction processes
C. Only using recycled materials
D. Outsourcing all work to subcontractors
Correct Answer: B. Maximizing efficiency and reducing waste in
construction processes
Rationale: Lean construction focuses on delivering value efficiently while
minimizing waste, delays, and unnecessary costs.
7. What is the primary purpose of a project closeout in construction
management?
A. To start new projects
B. To ensure all contract requirements are fulfilled and project
documentation is complete
C. To conduct feasibility studies
D. To renegotiate contracts
Correct Answer: B. To ensure all contract requirements are fulfilled and
project documentation is complete
Rationale: Project closeout verifies completion, obtains approvals, and
finalizes contracts.
8. Which of the following is considered a construction project
stakeholder?
A. Owner
B. Contractor
, C. Architect
D. All of the above
Correct Answer: D. All of the above
Rationale: Stakeholders include anyone with an interest in or influence
over the project, such as owners, contractors, subcontractors, and
designers.
9. What does “earned value management” (EVM) help a construction
manager assess?
A. Only project costs
B. Project performance and progress against schedule and budget
C. Employee productivity
D. Material quality
Correct Answer: B. Project performance and progress against schedule
and budget
Rationale: EVM integrates scope, schedule, and cost to track project
performance and forecast outcomes.
10. In construction contracts, a “change order” is used to:
A. Terminate the contract
B. Amend the original contract scope, cost, or schedule
C. Hire new subcontractors
D. Audit project expenses
Correct Answer: B. Amend the original contract scope, cost, or schedule
Rationale: Change orders formally document modifications agreed upon
by the owner and contractor.