1. The primary purpose of a pre-demolition survey is to
A. Estimate labor costs
B. Identify salvageable materials
C. Locate underground utilities
D. Schedule equipment deliveries
Correct Answer: C
Rationale: A pre-demolition survey identifies utilities, hazards, and site
conditions to prevent accidents and service disruptions.
2. Which document authorizes a demolition contractor to begin work
legally in Kansas?
A. Insurance certificate
B. Building permit
C. Safety plan
D. Waste manifest
Correct Answer: B
Rationale: A demolition permit issued by the authority having jurisdiction
is required before work begins.
3. Which material requires special handling and disposal due to health
risks?
A. Concrete
, B. Steel
C. Asbestos
D. Brick
Correct Answer: C
Rationale: Asbestos fibers are hazardous and must be removed following
strict regulatory procedures.
4. The safest sequence for demolition of a structure is generally
A. Bottom-up
B. Random removal
C. Top-down
D. Interior-out
Correct Answer: C
Rationale: Top-down demolition maintains structural stability and reduces
collapse hazards.
5. Which agency primarily enforces workplace safety standards on
demolition sites?
A. EPA
B. DOT
C. OSHA
D. FEMA
Correct Answer: C
Rationale: OSHA sets and enforces safety regulations for construction and
demolition activities.
6. Before using heavy equipment near utilities, the contractor must
A. Rely on drawings only
B. Shut down all power citywide
C. Contact utility locating services
D. Proceed carefully
, Correct Answer: C
Rationale: Utility locating services identify underground lines to prevent
damage and injury.
7. Which demolition method uses explosives?
A. Mechanical demolition
B. Deconstruction
C. Implosion
D. Manual demolition
Correct Answer: C
Rationale: Implosion uses carefully placed explosives to collapse a
structure inward.
8. Personal protective equipment (PPE) on demolition sites typically
includes all EXCEPT
A. Hard hats
B. Safety glasses
C. Steel-toe boots
D. Open-toe footwear
Correct Answer: D
Rationale: Open-toe footwear offers no protection and is prohibited on job
sites.
9. What is the primary environmental concern during demolition?
A. Noise complaints
B. Dust and debris control
C. Equipment wear
D. Scheduling delays
Correct Answer: B
Rationale: Dust and debris can harm health and the environment if not
properly controlled.
10. Lead-based paint hazards are most commonly associated with
buildings built
Questions And Correct Answers
(Verified Answers) Plus Rationale 2026
Q&A| Instant Download Pdf
1. The primary purpose of a pre-demolition survey is to
A. Estimate labor costs
B. Identify salvageable materials
C. Locate underground utilities
D. Schedule equipment deliveries
Correct Answer: C
Rationale: A pre-demolition survey identifies utilities, hazards, and site
conditions to prevent accidents and service disruptions.
2. Which document authorizes a demolition contractor to begin work
legally in Kansas?
A. Insurance certificate
B. Building permit
C. Safety plan
D. Waste manifest
Correct Answer: B
Rationale: A demolition permit issued by the authority having jurisdiction
is required before work begins.
3. Which material requires special handling and disposal due to health
risks?
A. Concrete
, B. Steel
C. Asbestos
D. Brick
Correct Answer: C
Rationale: Asbestos fibers are hazardous and must be removed following
strict regulatory procedures.
4. The safest sequence for demolition of a structure is generally
A. Bottom-up
B. Random removal
C. Top-down
D. Interior-out
Correct Answer: C
Rationale: Top-down demolition maintains structural stability and reduces
collapse hazards.
5. Which agency primarily enforces workplace safety standards on
demolition sites?
A. EPA
B. DOT
C. OSHA
D. FEMA
Correct Answer: C
Rationale: OSHA sets and enforces safety regulations for construction and
demolition activities.
6. Before using heavy equipment near utilities, the contractor must
A. Rely on drawings only
B. Shut down all power citywide
C. Contact utility locating services
D. Proceed carefully
, Correct Answer: C
Rationale: Utility locating services identify underground lines to prevent
damage and injury.
7. Which demolition method uses explosives?
A. Mechanical demolition
B. Deconstruction
C. Implosion
D. Manual demolition
Correct Answer: C
Rationale: Implosion uses carefully placed explosives to collapse a
structure inward.
8. Personal protective equipment (PPE) on demolition sites typically
includes all EXCEPT
A. Hard hats
B. Safety glasses
C. Steel-toe boots
D. Open-toe footwear
Correct Answer: D
Rationale: Open-toe footwear offers no protection and is prohibited on job
sites.
9. What is the primary environmental concern during demolition?
A. Noise complaints
B. Dust and debris control
C. Equipment wear
D. Scheduling delays
Correct Answer: B
Rationale: Dust and debris can harm health and the environment if not
properly controlled.
10. Lead-based paint hazards are most commonly associated with
buildings built