A primary clarifier has a flow of 3.0 MGD and has a diameter of 100 feet. It is 12 feet deep and has 24 inches of freeboard. What is the detention time in hours? - CORRECT ANSWER-4.7 hrs Anaerobic digester gas should contain? - CORRECT ANSWER-65-75% methane, 25-35% carbon dioxide and 1-5% nitrogen. An activated sludge plant has an average daily flow of 3.5 MG. The aeration tank capacity is 1.2 MG with a MLSS concentration of 3200 mg/L. The clarifier has a capacity of 400,000 gallons with a MLSS concentration of 6,000 mg/L. The wasting rate is 40,000 gallons per day with a MLSS concentration of 8, 000 mg/L. The effluent TSS is 18 mg/L. Assuming volatile concentrations of 70%, what is the MCRT and what type of activated sludge plant should this be? - CORRECT ANSWER-16.29 Days What are some of the causes of filaments in the aeration basin? - CORRECT ANSWER-a. low DO b. low organic loading c. septic wastes d. nutrient deficiencies . e. high sulfur content When an RBC is operating correctly, how will the slime appear on the media? - CORRECT ANSWER-Grey to brown 0.05 to 0.1 inches thick What activated sludge process does not achieve complete nitrification? - CORRECT ANSWER-Contact Stabilization In the selection of forced main wastewater piping, what is the minimum working pressure? - CORRECT ANSWER-150 psi

Content preview

Texas Wastewater A Exam Questions
With verified Answers
A primary clarifier has a flow of 3.0 MGD and has a diameter of 100 feet. It is 12 feet
deep and has 24 inches of freeboard. What is the detention time in hours? - CORRECT
ANSWER-4.7 hrs



Anaerobic digester gas should contain? - CORRECT ANSWER-65-75% methane, 25-
35% carbon dioxide and 1-5% nitrogen.



An activated sludge plant has an average daily flow of 3.5 MG. The aeration tank
capacity is 1.2 MG with a MLSS concentration of 3200 mg/L. The clarifier has a capacity
of 400,000 gallons with a MLSS concentration of 6,000 mg/L. The wasting rate is
40,000 gallons per day with a MLSS concentration of 8, 000 mg/L. The effluent TSS is
18 mg/L. Assuming volatile concentrations of 70%, what is the MCRT and what type of
activated sludge plant should this be? - CORRECT ANSWER-16.29 Days



What are some of the causes of filaments in the aeration basin? - CORRECT
ANSWER-a. low DO

b. low organic loading

c. septic wastes

d. nutrient deficiencies .

e. high sulfur content



When an RBC is operating correctly, how will the slime appear on the media? -
CORRECT ANSWER-Grey to brown 0.05 to 0.1 inches thick



What activated sludge process does not achieve complete nitrification? - CORRECT
ANSWER-Contact Stabilization

, In the selection of forced main wastewater piping, what is the minimum working
pressure? - CORRECT ANSWER-150 psi



The oxygen depletion of BOD dilution water should not exceed - CORRECT ANSWER-
0.2 mg/L.



What is the minimum air gap when making water and wastewater connections? -
CORRECT ANSWER-Minimum of one inch or twice the inlet pipe size whichever is
greater.



An anaerobic digester must maintain an average year round temperature of -
CORRECT ANSWER-95 degrees F.



Which of the following methods would you use to increase the degree of nitrification in
an activated sludge plant? - CORRECT ANSWER-increase dissolved oxygen levels and
increase the sludge age



Which of the following are considered normal operator controls on an activated sludge
plant? - CORRECT ANSWER-*aeration rates *return and wasting rates



Reducing the return sludge flow rate for an activated sludge system which has a good
settling sludge will ________. - CORRECT ANSWER-increase the sludge retention time
(SRT) and potentially increase the mixed liquor suspended solids (MLSS) concentration
in the aeration tank.



This can lead to a thicker sludge blanket in the clarifier, but it might also increase the
risk of sludge bulking if the solids concentration becomes too high.



An extended air activated sludge plant has a fast settling sludge and high amounts of
pin floc leaving the clarifier. One way to correct this problem is to ________. -

Document information

Uploaded on
October 22, 2025
Number of pages
10
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
remojudytask
3.2
(26)
Sold
94
Followers
30
Items
3119
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions